BLD-Final | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.9
|
BLD-Energy code compliance | 9/17/2018 | 9/18/2018 | 9/18/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Framing/Rough-in | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 8/8/2018 | 8/9/2018 | 8/9/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Foundation | 6/13/2018 | 6/13/2018 | 6/13/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 6/7/2018 | 6/7/2018 | 6/7/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
Inspection Record Card- Bld | | | 5/30/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/30/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/30/2018 | | |
|
|
|
|
Plan assigned to (M_H) | 4/16/2018 | | 4/30/2018 | | DONE |
Michael Hanson
|
|
|
05/03 Townhouse L2 ePlan See BLD18-01280
|
Routing - PLAN CHECK | 4/16/2018 | | 4/30/2018 | | PASS |
Michael Hanson
|
|
|
|
Routing PW Flood Plain | 4/16/2018 | | 4/30/2018 | | PASS |
Jason C. Taylor
|
|
|
Approved LOMR in file. No floodplain review required. JCT
|
Plan Reviewer's activity | | | 4/30/2018 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 4/30/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 4/30/2018 | | DONE |
|
|
|
DO NOT ISSUE WITHOUT BLD18-01280
|
Route to Impact Fee Review | 4/16/2018 | 4/19/2018 | 4/17/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/16/2018 | | 4/17/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/16/2018 | | 4/17/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - Addressing | 4/16/2018 | | 4/16/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/16/2018 | | 4/16/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/16/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/16/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/16/2018 | | DONE |
|
|
|
|
Application received | | | 4/10/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 10 2018 10:39AM
|