BLD-Blower Door Test Results | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | PASS |
Tony Young
|
|
|
Call for access- Steve Phone #: ###-####// 3.86
|
BLD-Final | 12/4/2018 | 12/5/2018 | 12/5/2018 | P | PASS |
Tony Young
|
|
|
Call for access- Steve Phone #: ###-####
|
DOC - Permit Finaled | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 12/4/2018 | 12/4/2018 | 12/4/2018 | P | PART |
Tony Young
|
|
|
Call for access- Steve Phone #: ###-####// needs the blower door test results,, vent wells on exterior or redo the landscape,, firecaulk t-stat wire
|
BLD-Conference | 12/3/2018 | 12/3/2018 | 12/3/2018 | P | PASS |
Tony Young
|
|
|
frame corrections were made and verified at the energy code inspection
|
BLD-Energy code compliance | 7/18/2018 | 7/19/2018 | 7/19/2018 | A | PASS |
Tony Young
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 7/13/2018 | 7/16/2018 | 7/16/2018 | P | PART |
Tony Young
|
|
|
Steve Phone #: ###-####,, see paint notes,, ok to insulate
|
BLD-Wall Bracing | 6/20/2018 | 6/21/2018 | 6/21/2018 | A | PASS |
Jim Storey
|
|
|
shear- Steve Phone #: ###-####
|
BLD-Footing | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
Tony Young
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/4/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/3/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 4/16/2018 | 4/16/2018 | 5/3/2018 | | DONE |
Rob Patrick
|
|
|
4/27 sfd L1 Paper...4/26 Failed: Update Portal Frame, Braced Wall table. Add "TYPE X" to garage rock, delete smokies in kitchen
|
Inspection Record Card- Bld | | | 5/3/2018 | | DONE |
|
|
|
|
Telephone call | | | 5/3/2018 | | DONE |
Christina Prado
|
|
|
Called Steve to advise permit is ready and gave fees due
|
Routing - PLAN CHECK | 5/3/2018 | | 5/3/2018 | | PASS |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 5/3/2018 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/3/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/1/2018 | | DONE |
|
|
|
Resubmittals recieved 2 sets of sheets SP1.0, A0.0, A1.0, A2.0,A3.0, S1.0, S2.0, E1.0-Took to Rob P
|
Routing - PLAN CHECK | 4/19/2018 | | 4/26/2018 | | FAIL |
Rob Patrick
|
|
|
4/26...Failed: Update Portal Frame Detial, Braced Panel Table, Relocate Smoke Det. Add Type X rock in garage.
|
1st review completed | | | 4/26/2018 | | FAIL |
Rob Patrick
|
|
|
4/26...Failed: Update Portal Frame detail, Braced Panel Table, Relocate Smoke Det. Add Type X rock to garage.
|
Routing - MECHANICAL | 4/17/2018 | | 4/19/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/16/2018 | 4/19/2018 | 4/17/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 4/16/2018 | | 4/17/2018 | | PASS |
Colleen T Carroll
|
|
|
Contractor to verify the garage is 20' from edge of common drive.
|
Routing - Addressing | 4/16/2018 | | 4/16/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | | | 4/16/2018 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/16/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/16/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/13/2018 | | DONE |
|
|
|
|
Application received | | 4/13/2018 | | | |
|
|
|
|