Permanent Occupancy | | | 1/15/2020 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/15/2020 | | DONE |
|
|
|
The scope of work was revised to allow occupancy of the future brewery as an employee work area. A separate permit is required to use the future brewery as a large-scale brewery.
|
First Notice | | 11/18/2018 | 12/14/2018 | | DONE |
|
|
|
mailed 12-17
|
BLD-Final | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Jim Sly
|
|
|
Steve 775 250 5860 OK for Perm. Occ.
|
BLD-Final | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | NR |
Jim Sly
|
|
|
Steve Phone #: ###-#### Need Mech
|
Zoning Approval | 11/8/2018 | 11/8/2018 | 11/8/2018 | | PASS |
David Moser
|
|
|
|
Permanent Occupancy | | | 11/8/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/31/2018 | 11/1/2018 | 11/1/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. No brewing equipment present or installed in the future Brewery.
Steve Phone #: ###-####
|
FIRE-Conference | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements
Steve Phone #: ###-####
|
BLD-Energy code compliance | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Jim Sly
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 8/9/2018 | 8/10/2018 | 8/10/2018 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Conference | 8/6/2018 | 8/8/2018 | 8/9/2018 | P | DONE |
Jim Sly
|
|
|
Beth Phone #: ###-####
|
BLD-Framing/Rough-in | 7/19/2018 | 7/20/2018 | 7/20/2018 | P | PART |
Jim Sly
|
|
|
Steve Phone #: ###-#### Framing on Cooler....OK to cover
|
BLD-Framing/Rough-in | 6/8/2018 | 6/11/2018 | 6/11/2018 | A | PART |
Mike Jordan
|
|
|
Steve-please call 30 minutes prior to meet for access Phone #: ###-####. New opening in masonry wall for new cooler. Requires special inspection.
|
Print Occupancy Form | | | 5/31/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/31/2018 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/24/2018 | 4/24/2018 | 5/30/2018 | | PASS |
Carl Westfall
|
|
|
* (1st done) (May 11 - 15 days) (12 sheets) Bear Island Brewing L-3
|
Routing - PLAN CHECK | 5/29/2018 | | 5/30/2018 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLUMBING | 5/30/2018 | | 5/30/2018 | | PASS |
Bill VanDegrift
|
|
|
For Bill to sign off on
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/30/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/30/2018 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED VALUE
|
Plan resubmittals received | | | 5/29/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/18/2018 | 5/21/2018 | 5/18/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/18/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/18/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/24/2018 | | 5/18/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - MECHANICAL | 5/15/2018 | | 5/15/2018 | | PASS |
Chad Schwendiman
|
|
|
The door area meets the 4% per square feet for nautural ventilation
|
Routing - FIRE | 4/24/2018 | 4/24/2018 | 5/14/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLUMBING | 5/10/2018 | | 5/10/2018 | | PASS |
Bill VanDegrift
|
|
|
1) venting required for all traps
2) the water system must be sized per UPC 610
3) verify service sizing and cross connection protection
4) brewery equipment is not a part of this project
|
Routing - MECHANICAL | 5/10/2018 | | 5/10/2018 | | FAIL |
Chad Schwendiman
|
|
|
Need Mechanical drawings including Ventilation design drawn by a Idaho licensed Engineer
|
Routing - PUBLIC WORKS | 4/24/2018 | | 5/9/2018 | | PASS |
Rachael Beierle
|
|
|
TASTING ROOM ONLY. NO FOOD SERVICE OR BREWING ALLOWED UNDER THIS PERMIT.
|
Routing PW Environmental | 4/24/2018 | | 4/27/2018 | | PASS |
Terry Alber
|
|
|
Oil/Sediment Interceptor is already abandoned. No brewing likely until beginning of 2019.
|
Routing - Addressing | 4/24/2018 | | 4/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Drainage | 4/24/2018 | | 4/24/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 4/24/2018 | | 4/24/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Solid Waste | 4/24/2018 | | 4/24/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLANNING | 4/24/2018 | | 4/24/2018 | | PASS |
David Moser
|
|
|
OK as per CUP17-00078
|
Routing - Design Review | 4/24/2018 | | 4/24/2018 | | PASS |
Andrea Tuning
|
|
|
No review required. Not in a D overlay zone.
|
Routing - PLUMBING | 4/24/2018 | | 4/24/2018 | | FAIL |
Bill VanDegrift
|
|
|
Idaho registered engineer required to submit plumbing plan.
|
Intake Approval | | | 4/21/2018 | | PASS |
|
|
|
|
Intake Approval | | | 4/18/2018 | | FAIL |
Michael Hanson
|
|
|
1. Provide stamped signed plumbing plans from an Idaho licensed engineer as the plumbing work is not minor in nature. MDH
|
Application received | | | 4/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 17 2018 9:18AM
|