Permit Information
Permit NumberBLD18-01332
StatusFinaled
Name SUGAR BEAR HOLDINGS LLC
Site Address 1620 N LIBERTY ST
Project NameBear Island Brewing
Customer Number 
ePlanReviewYes
Description
(BEAR ISLAND BREWING – TASTING ROOMS AND EMPLOYEE WORK AREA) (CUP17-00078) This building does not have a fire sprinkler system. To remodel an existing 3,865 square foot building to be used as a bar. This permit is intended to establish a Certificate of Occupancy for the 2,452 square foot remodel area and for the 1,413 square foot future brewery to be used as an employee work area. A separate permit is required for the 1,413 square foot future brewery before it can be used as a large-scale brewery. Meanwhile, that space is allowed to be used as an employee work area. It is not approved for public use. Work is to include interior nonbearing walls, 2 toilet rooms accessible to the disabled, new interior side-hinged swinging doors, an insulated 514 square foot walk-in cooler with an interior side-hinged swinging door, a bar, back bar equipment, new exterior doors, an exterior folding garage door, a fixed panel exterior door to match the folding garage door, and R-30 insulation installed below and up against the underside of the existing roof deck having existing minimum R-20 continuous insulation installed on top of the existing roof deck. A new equipment enclosure at grade surrounded by a 6 foot tall chain link fence will be created. A new 1,351 square foot exterior patio at grade surrounded by a 6 foot tall cedar fence will also be created. Structural work includes enlarging an existing door opening in an interior masonry bearing wall (steel lintel, tube steel columns to resist out of plane lateral loads, steel attachment plates, and masonry anchors) and creating a new opening in an existing wood stud bearing wall (wood header, trimmers, and king studs). Special Inspection is required for welding and for anchors post-installed in masonry or hardened concrete. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  1/15/2020 DONE
Plan Reviewer's activity  1/15/2020 DONE
The scope of work was revised to allow occupancy of the future brewery as an employee work area. A separate permit is required to use the future brewery as a large-scale brewery.
First Notice 11/18/201812/14/2018 DONE
mailed 12-17
BLD-Final11/8/201811/8/201811/8/2018PPASS
DetailsJim Sly
Steve 775 250 5860
OK for Perm. Occ.
BLD-Final11/7/201811/8/201811/8/2018ANR
DetailsJim Sly
Steve Phone #: ###-####
Need Mech
Zoning Approval11/8/201811/8/201811/8/2018 PASS
DetailsDavid Moser
Permanent Occupancy  11/8/2018 DONE
FIRE-Final Inspection10/31/201811/1/201811/1/2018APASS
DetailsTroy Cobbley
Life safety passed. No brewing equipment present or installed in the future Brewery.

Steve Phone #: ###-####
FIRE-Conference10/18/201810/18/201810/18/2018PDONE
DetailsTroy Cobbley
I went over life safety requirements

Steve Phone #: ###-####
BLD-Energy code compliance8/20/20188/20/20188/20/2018PPASS
DetailsJim Sly
Steve Phone #: ###-####
BLD-Framing/Rough-in8/9/20188/10/20188/10/2018APASS
DetailsMike Jordan
Steve Phone #: ###-####
BLD-Conference8/6/20188/8/20188/9/2018PDONE
DetailsJim Sly
Beth Phone #: ###-####
BLD-Framing/Rough-in7/19/20187/20/20187/20/2018PPART
DetailsJim Sly
Steve Phone #: ###-####
Framing on Cooler....OK to cover
BLD-Framing/Rough-in6/8/20186/11/20186/11/2018APART
DetailsMike Jordan
Steve-please call 30 minutes prior to meet for access Phone #: ###-####. New opening in masonry wall for new cooler. Requires special inspection.
Print Occupancy Form  5/31/2018 DONE
Issue PAID IN FULL permit  5/31/2018 DONE
Plan assigned to (CJW)4/24/20184/24/20185/30/2018 PASS
DetailsCarl Westfall
* (1st done) (May 11 - 15 days) (12 sheets) Bear Island Brewing L-3
Routing - PLAN CHECK5/29/2018 5/30/2018 PASS
DetailsCarl Westfall
Routing - PLUMBING5/30/2018 5/30/2018 PASS
DetailsBill VanDegrift
For Bill to sign off on
PLANS/APPL TAKEN TO FRONT DESK  5/30/2018 DONE
Permit Ready to Issue  5/30/2018 DONE
MET
NEED
GC FORM
REVISED VALUE
Plan resubmittals received  5/29/2018 DONE
Route to Impact Fee Review5/18/20185/21/20185/18/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  5/18/2018 DONE
Plan resubmittals requested  5/18/2018 DONE
Routing - PLAN CHECK4/24/2018 5/18/2018 FAIL
DetailsCarl Westfall
Revised drawings required
Routing - MECHANICAL5/15/2018 5/15/2018 PASS
DetailsChad Schwendiman
The door area meets the 4% per square feet for nautural ventilation
Routing - FIRE4/24/20184/24/20185/14/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - PLUMBING5/10/2018 5/10/2018 PASS
DetailsBill VanDegrift
1) venting required for all traps
2) the water system must be sized per UPC 610
3) verify service sizing and cross connection protection
4) brewery equipment is not a part of this project
Routing - MECHANICAL5/10/2018 5/10/2018 FAIL
DetailsChad Schwendiman
Need Mechanical drawings including Ventilation design drawn by a Idaho licensed Engineer
Routing - PUBLIC WORKS4/24/2018 5/9/2018 PASS
DetailsRachael Beierle
TASTING ROOM ONLY. NO FOOD SERVICE OR BREWING ALLOWED UNDER THIS PERMIT.
Routing PW Environmental4/24/2018 4/27/2018 PASS
DetailsTerry Alber
Oil/Sediment Interceptor is already abandoned. No brewing likely until beginning of 2019.
Routing - Addressing4/24/2018 4/24/2018 PASS
DetailsDoug Chausow
Routing PW Drainage4/24/2018 4/24/2018 PASS
DetailsBrian Murphy
Routing PW Street Lights4/24/2018 4/24/2018 PASS
DetailsTom Marshall
Routing PW Solid Waste4/24/2018 4/24/2018 PASS
DetailsEvan Carpenter
Routing - PLANNING4/24/2018 4/24/2018 PASS
DetailsDavid Moser
OK as per CUP17-00078
Routing - Design Review4/24/2018 4/24/2018 PASS
DetailsAndrea Tuning
No review required. Not in a D overlay zone.
Routing - PLUMBING4/24/2018 4/24/2018 FAIL
DetailsBill VanDegrift
Idaho registered engineer required to submit plumbing plan.
Intake Approval  4/21/2018 PASS
Intake Approval  4/18/2018 FAIL
DetailsMichael Hanson
1. Provide stamped signed plumbing plans from an Idaho licensed engineer as the plumbing work is not minor in nature. MDH
Application received  4/17/2018 DONE
Application submitted via PDS Online on Apr 17 2018 9:18AM