Permit Information
Permit NumberBLD18-01336
StatusIssued
Name JORDAN WILCOMB CONSTRUCTION
Site Address 807 N 8TH ST
Project NameSt John's Catherdral
Customer Number 
ePlanReviewYes
Description
(ST. JOHNS CATHEDERAL) ""Special Inspections required"" Replacement of 8th Street Stairs of the existing church with work to include removal of the existing monument stairs, excavation and placement of new footins and foundation for the new monument stairs and the construction of the new sanstone stairs, guards and handrails per the approved plans. This is a scope of work permit with a certificate of compliance to be issued upon completion and approval of the project, CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference8/6/20198/7/20198/7/2019APEND
DetailsTony Young
Cecli Phone #: ###-####,, landing ?s,, need to have architect scope out landing % and have plan review approve or decide
BLD-Conference5/6/20195/7/20195/7/2019PPART
DetailsTony Young
Cecil; Phone #: ###-####,, hand rail ?s,, see plan reviewer for any changes
BLD-Foundation7/13/20187/13/20187/13/2018PPART
DetailsTony Young
pour is at 2 // Cecil Phone #: ###-####
BLD-Footing7/11/20187/11/20187/11/2018PPASS
DetailsBrandon Shaw
early as poss, wants to pour at 2 // Cecil Wilcomb Phone #: ###-####
Issue PAID IN FULL permit  6/15/2018 DONE
Inspection Record Card- Bld  6/15/2018 DONE
OVERRIDE  6/8/2018  
Plan assigned to (CDM)5/7/20185/7/20186/8/2018 PASS
DetailsCarl D Madsen
St. Johns Cathederal L-3 Due 6/1
Routing - PLAN CHECK5/26/2018 6/8/2018 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL5/26/2018 6/8/2018 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  6/8/2018 DONE
Permit Ready to Issue  6/8/2018 DONE
all met-Need
RP-met
GC Form-met
Revised Cert of Value-met
Route to Impact Fee Review5/24/20185/27/20185/29/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE5/7/20185/7/20185/24/2018 PASS
DetailsErika Akin
No comments attached. Inspector to field verify basic life safety for new exterior stairs.
Routing Off Site - STRUCTURAL5/7/2018 5/24/2018 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK5/7/2018 5/24/2018 FAIL
DetailsCarl D Madsen
1st review completed  5/24/2018 FAIL
Routing - PLANNING5/7/2018 5/14/2018 PASS
DetailsSusan Riggs
Routing - Addressing5/7/2018 5/8/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS5/7/2018 5/8/2018 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment5/7/2018 5/8/2018 PASS
DetailsMichael Zawacki
Waiver approved. General contractor will act as RP or assign RP. Concrete washout needed on site. GC/RP will be responsible for keeping site and surrounding area clean.
Routing - Design Review5/7/2018 5/8/2018 PASS
DetailsSarah Schafer
Routing PW Drainage5/8/2018 5/8/2018 PASS
DetailsBrian Murphy
Routing PW Street Lights5/8/2018 5/8/2018 PASS
DetailsTom Marshall
Intake Approval  5/7/2018 PASS
Application received  4/17/2018 DONE
Application submitted via PDS Online on Apr 17 2018 11:23AM