DOC - Permit Finaled | | | 7/18/2018 | | DONE |
|
|
|
Per passing inspection 6/15/18
|
BLD-Final | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | DONE |
Bob Archibald
|
|
|
Demolition and top soil stabilization complete.
|
BLD-Final | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | FAIL |
Bob Archibald
|
|
|
Andrea Phone #: ###-####. Not ready needs final grading work
|
BLD-Other | 5/16/2018 | 5/16/2018 | 5/16/2018 | P | PEND |
Bob Archibald
|
|
|
Vertical demolition completed. Clean up in progress.
|
Issue PAID IN FULL permit | | | 5/4/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/27/2018 | | |
|
|
|
|
Routing - Erosion and Sediment | 4/27/2018 | | 4/27/2018 | | PASS |
Andy J. Long
|
|
|
ESC permit approved. Certified RP designated. See also executed contrart SFB 18-237 (PWE 818): Alto Via Demolition Project #2
Site Final Inspection required.
|
Routing PW Grading-Hillside | 4/27/2018 | | 4/27/2018 | | PASS |
Jason C. Taylor
|
|
|
Site stabilization will be required as per the Hillside Ordinance. Public Works approval of stabilization will be required prior to permit final. Jason Taylor ###-####.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/27/2018 | | DONE |
Christina Prado
|
|
|
All requirements met
|
OVERRIDE | | | 4/26/2018 | | |
|
|
|
|
Application received | | 4/17/2018 | | | |
|
|
|
|