BLD-Final | 12/28/2018 | 12/28/2018 | 12/28/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 12/28/2018 | 12/28/2018 | 12/28/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 12/28/2018 | 12/28/2018 | 12/28/2018 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.31
|
BLD-Framing/Rough-in | 10/15/2018 | 10/16/2018 | 10/16/2018 | A | DONE |
Brandon Shaw
|
|
|
See Documents, dated 10-16-18, for revised Engineering for framing correction... Corrections SAT...
|
BLD-Energy code compliance | 10/11/2018 | 10/11/2018 | 10/11/2018 | P | FAIL |
Brandon Shaw
|
|
|
No corrections made...
|
BLD-Other | 10/10/2018 | 10/11/2018 | 10/11/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 10/5/2018 | 10/5/2018 | 10/5/2018 | A | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick no truss engineering on for roof or floor trusses also looks like hangreproblems and point loads and bearing on 3ply in living room
|
BLD-Wall Bracing | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 8/6/2018 | 8/7/2018 | 8/7/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 8/5/2018 | 8/6/2018 | 8/6/2018 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
Issue PAID IN FULL permit | | | 7/27/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/27/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/27/2018 | | |
|
|
|
|
Plan Reviewer's activity | | | 4/27/2018 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 4/27/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 4/27/2018 | | DONE |
|
|
|
Met
|
Plan assigned to (M_H) | 4/19/2018 | | 4/27/2018 | | DONE |
Michael Hanson
|
|
|
05/03 sfd L1 ePlan
|
Routing - PLAN CHECK | 4/19/2018 | | 4/27/2018 | | PASS |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 4/19/2018 | | 4/24/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/19/2018 | 4/22/2018 | 4/20/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 4/19/2018 | | 4/20/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 4/19/2018 | | 4/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/19/2018 | | 4/19/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/19/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/19/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/19/2018 | | DONE |
|
|
|
|
Application received | | | 4/18/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 18 2018 4:41PM
|
Intake Approval | | | 4/18/2018 | | FAIL |
|
|
|
IECC is 2012
|