BLD-Final | 10/9/2019 | 10/10/2019 | 10/10/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
DOC - Permit Finaled | 10/10/2019 | 10/10/2019 | 10/10/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 10/9/2019 | 10/10/2019 | 10/10/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.5
|
BLD-Energy code compliance | 8/6/2019 | 8/6/2019 | 8/6/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
BLD-Framing/Rough-in | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Wall Bracing | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | PASS |
Brandon Shaw
|
|
|
Call ahead / Guillermo Phone #: ###-####
|
OVERRIDE | | | 7/18/2019 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/18/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/18/2019 | | DONE |
|
|
|
PLAN MOD FOR MANUAL J. FEES IN BLD19-01370
|
Routing - MECHANICAL | 7/17/2019 | | 7/17/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report.
|
Plan Modification Accepted | | | 7/16/2019 | | DONE |
|
|
|
plan mod per Amy at Blackrock - upload Manual J
|
BLD-Conference | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | DONE |
Brandon Shaw
|
|
|
Firewall...
|
BLD-Conference | 2/15/2019 | 2/15/2019 | 2/15/2019 | P | DEFR |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Aging Inspection | 2/15/2019 | 2/15/2019 | 2/15/2019 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 2/14/2019 | 2/14/2019 | 2/14/2019 | | CANC |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 9/24/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/24/2018 | | DONE |
|
|
|
|
Expiration Notice | 9/21/2018 | 10/12/2018 | 9/21/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 5/9/2018 | | |
|
|
|
|
Routing - PLAN CHECK | 5/9/2018 | | 5/9/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 5/9/2018 | | DONE |
|
|
|
please do not issue without the all 3 permits (BLD18-01370, 1374 & 1375)
|
Plan assigned to (M_H) | 4/25/2018 | | 5/9/2018 | | DONE |
Michael Hanson
|
|
|
05/08 triplex L1 ePlan. 1st review completed - Structural, energy, WUI issues. MDH
|
Routing - PLAN CHECK | 4/25/2018 | | 5/7/2018 | | FAIL |
Michael Hanson
|
|
|
Structural, energy, WUI issues. MDH
|
Plan Reviewer's activity | | | 5/7/2018 | | FAIL |
Michael Hanson
|
|
|
|
1st review completed | | | 5/7/2018 | | FAIL |
Michael Hanson
|
|
|
Structural, energy, WUI issues. MDH
|
Routing - MECHANICAL | 4/25/2018 | | 4/27/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/25/2018 | 4/28/2018 | 4/26/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 4/25/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/25/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/25/2018 | | PASS |
|
|
|
|
Routing - PLANNING | 4/25/2018 | | 4/25/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH18-00115
|
Routing - Addressing | 4/25/2018 | | 4/25/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/25/2018 | | 4/25/2018 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | 4/19/2018 | | | |
|
|
|
|