Print Statement | | | 10/9/2019 | | DONE |
|
|
|
sent 1st late notice on final fees
|
Print Statement | | | 6/11/2019 | | DONE |
|
|
|
|
Second Notice | | 5/16/2019 | 6/7/2019 | | DONE |
|
|
|
mailed 6-10
|
First Notice | | 4/18/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
PubWorks Occupancy Approval | 4/8/2019 | 4/8/2019 | 4/8/2019 | | DONE |
Tiffany Lowery
|
|
|
Final Inspection competed 01/08/19.
|
Permanent Occupancy | | | 4/8/2019 | | DONE |
|
|
|
|
Telephone call | | | 4/8/2019 | | DONE |
|
|
|
talked to James-all inspections are done but PW-he will call that in then come get the perm c of o
|
BLD-Final | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | PASS |
Mike Jordan
|
|
|
Overland Taco Bell Phone #: ###-#### Inspection requested via web by Sean Worthington. Ok for perm occ.
|
Zoning Approval | 2/20/2019 | 2/20/2019 | 2/20/2019 | | PASS |
Katelyn Menuge
|
|
|
Landscape complete
|
Temporary Occupancy | 1/7/2019 | 4/7/2019 | 1/7/2019 | | DONE |
Tisha Gallop
|
|
|
pending Planning & Zoning and final inspection on PLM18-03978
|
BLD-Final | 1/3/2019 | 1/4/2019 | 1/4/2019 | P | PEND |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sean Worthington. Will be ok for Temp. occ. once public works signs off. Will be ok for perm. occ. once zoning signs perm.
|
FIRE-Final Inspection | 1/2/2019 | 1/3/2019 | 1/3/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Sean ###-####
|
FIRE-Final Inspection | 12/28/2018 | 1/2/2019 | 1/2/2019 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the project related fire suppression permit is finaled.
Sean Phone #: ###-####
|
Zoning Approval Temp | 1/2/2019 | 1/2/2019 | 1/2/2019 | | PASS |
Katelyn Menuge
|
|
|
Bond for Landscape BND19-00001
|
BLD-Ceiling Grid Inspection | 12/17/2018 | 12/18/2018 | 12/18/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sean Worthington
|
BLD-Wall Bracing | 11/19/2018 | 11/19/2018 | 11/19/2018 | P | PASS |
Mike Jordan
|
|
|
Late pm if possible. Thank you. Interior shear. Phone #: ###-#### Inspection requested via web by Sean Worthington
|
BLD-Energy code compliance | 11/15/2018 | 11/16/2018 | 11/16/2018 | A | PASS |
Mike Jordan
|
|
|
Wall insulation Phone #: ###-#### Inspection requested via web by Sean Worthington
|
BLD-Energy code compliance | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PASS |
Mike Jordan
|
|
|
Marv''s said that they will be complete with energy seal by 10:30. Thank you Phone #: ###-#### Inspection requested via web by Sean Worthington. airseal ok.
|
BLD-Framing/Rough-in | 11/13/2018 | 11/14/2018 | 11/14/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sean Worthington
|
BLD-Foundation | 11/12/2018 | 11/13/2018 | 11/13/2018 | P | DEFR |
Mike Jordan
|
|
|
Rebar inspection for the trash enclosure CMU. Phone #: ###-#### Inspection requested via web by Sean Worthington
|
BLD-Framing/Rough-in | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | PASS |
Mike Jordan
|
|
|
Exterior overbuild so we can cover. Phone #: ###-#### Inspection requested via web by Sean Worthington
|
BLD-Wall Bracing | 11/1/2018 | 11/2/2018 | 11/2/2018 | A | PASS |
Mike Jordan
|
|
|
Inspect shear wall nailing Phone #: ###-#### Inspection requested via web by Sean Worthington. Exterior shear nailing only ok.
|
BLD-Wall Bracing | 10/31/2018 | 11/1/2018 | 11/1/2018 | A | PART |
Mike Jordan
|
|
|
Shear // Dave Phone #: ###-####. roof nailing and hardware ok to cover. Needs to install missing hold downs and provide the additional rows of nailing at holdown locations as per endwall details. Enginner of record to provide alternate nailing detail for stud nailing at corners.
|
OVERRIDE | | | 10/8/2018 | | |
|
|
|
|
BLD-Concrete | 10/5/2018 | 10/8/2018 | 10/8/2018 | A | PART |
Mike Jordan
|
|
|
drive thru- Sean Phone #: ###-####. Welded wire mesh for exterior concrete slab on grade for drive through. Noted some clearance issues. Contractor to fix prior to concrete placement.
|
Plan assigned to (JAR) | 9/27/2018 | 9/27/2018 | 10/8/2018 | | DONE |
Julie Romig
|
|
|
10/08 - Plan Mod - Taco Bell Overland
|
Routing - PLAN CHECK | 10/3/2018 | | 10/8/2018 | | PASS |
Julie Romig
|
|
|
Plan Mod
|
Permit Ready to Issue | | | 10/8/2018 | | DONE |
|
|
|
Plan Mod Approved
Need
Revised Cert of Value
|
CHANGE STATUS TO (ISS) | | | 10/8/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/8/2018 | | DONE |
|
|
|
|
Routing PW Drainage | 10/3/2018 | | 10/5/2018 | | PASS |
Brian Murphy
|
|
|
|
BLD-Other | 10/3/2018 | 10/4/2018 | 10/4/2018 | P | PASS |
Brandon Shaw
|
|
|
BUILDING SLAB // SEAN Phone #: ###-####
|
Plan Modification Accepted | | | 9/27/2018 | | DONE |
Christina Prado
|
|
|
THE OWNER DECIDED TO REPLACE ALL OF THE ASPHALT IN THE PARKING LOT WHEN IT WAS
FOUND TO BE LESS THAN IDEAL CONDITION. AT THAT TIME, MTI TESTED THE SUBGRADE AND
FOUND IT TO BE THE ISSUE. THE SUBGRADE WAS REMOVED DOWN TO 18 INCHES, REPLACED
AND COMPACTED. NEW TESTS HAVE BEEN COMPLETED BY MTI AND FOUND TO PASS
INSPECTION.
|
BLD-Footing | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sean Worthington. Mono pour for dumpster enclosure ok.
|
BLD-Energy code compliance | 9/18/2018 | 9/18/2018 | 9/18/2018 | A | PASS |
Mike Jordan
|
|
|
e Early if possible Phone #: ###-#### Inspection requested via web by Sean Worthington. Rigid insulation on interior of stemwall.
|
BLD-Foundation | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | PART |
Mike Jordan
|
|
|
Late am. Thank you Phone #: ###-#### Inspection requested via web by Sean Worthington. Work in progres on interior mat footing for shear wall. Will be ok for concrete once special inspection has approved placement.
|
BLD-Foundation | 9/11/2018 | 9/12/2018 | 9/12/2018 | P | PART |
Jim Sly
|
|
|
Early pm if possible. Thank you. Phone #: ###-#### Inspection requested via web by Sean Worthington OK pending MTI special inspection, tests and approvals.
|
BLD-Foundation | 9/10/2018 | 9/11/2018 | 9/11/2018 | P | CANC |
Dave Hannah
|
|
|
Late pm if possible. Thank you. Phone #: ###-#### >> Inspection requested via web by Sean Worthington Inspection cancelled from web by: Sean Worthington
|
BLD-Foundation | 9/10/2018 | 9/11/2018 | 9/10/2018 | A | CANC |
Mike Jordan
|
|
|
Late am if possible. Thank you. We hope to pour at 2 pm. Phone #: ###-#### >> Inspection requested via web by Sean Worthington Inspection cancelled from web by: Sean Worthington
|
BLD-Footing | 8/29/2018 | 8/29/2018 | 8/29/2018 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Sean Worthington. Work in progress. Will have special inspection.
|
Print Occupancy Form | | | 8/24/2018 | | DONE |
|
|
|
|
BLD-Conference | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | DONE |
Bob Archibald
|
|
|
Received and approved engineering for below grade materials.
|
BLD-Conference | 8/16/2018 | 8/16/2018 | 8/16/2018 | P | PEND |
Bob Archibald
|
|
|
Complaint that basement footing foundation being left inplace and not to be removed during demolition Spoke with demo contractor and requested a stamped document from design professional indicating that existing/remaining basement footings/walls will not compromise new construction and that failure to receive applicable documentation will result in removal.
|
Issue PAID IN FULL permit | | | 7/25/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/25/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 6/22/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 6/22/2018 | | DONE |
|
|
|
ALL MET
NEED
GC - met
Rev Cert of Val - met
ACHD-no ACHD required
RP - met
|
Route to Impact Fee Review | 6/8/2018 | 6/11/2018 | 6/21/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JAR) | 5/7/2018 | 5/7/2018 | 6/21/2018 | | DONE |
Julie Romig
|
|
|
*1st Rev Comp - 2nd Rec'd 06/18 - 502 Taco Bell
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/18/2018 | | 6/21/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
Routing - PLUMBING | 6/18/2018 | | 6/20/2018 | | PASS |
Daryl Spivey
|
|
|
See redline notes and install per ISPC.
|
Routing - PLAN CHECK | 6/18/2018 | | 6/18/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
Routing PW Solid Waste | 6/18/2018 | | 6/18/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PUBLIC WORKS | 6/18/2018 | | 6/18/2018 | | PASS |
Morgan Webb
|
|
|
|
1st review completed | | | 6/8/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 5/8/2018 | | 6/8/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 5/8/2018 | 5/8/2018 | 6/7/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 5/8/2018 | | 5/23/2018 | | FAIL |
Julie Romig
|
|
|
Corrections Required per ePlanReview
|
Routing PW Drainage | 5/9/2018 | | 5/21/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Environmental | 5/9/2018 | | 5/15/2018 | | PASS |
Rick Christenson
|
|
|
Grease waste lines appear to connect all appropriate fixtures. Site has existing grease interceptor.
|
Routing - MECHANICAL | 5/8/2018 | | 5/14/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLUMBING | 5/8/2018 | | 5/10/2018 | | FAIL |
Daryl Spivey
|
|
|
Sanitary and grease line not per ISPC venting.
See red lines on water plumbing page.
|
Routing PW Solid Waste | 5/9/2018 | | 5/10/2018 | | FAIL |
Evan Carpenter
|
|
|
The solid waste enclosure must have at least 16 feet of unobstructed clearance between gate posts (measured from the innermost points), due to the additional grease container and recycling cart in the enclosure.
|
Routing PW Sewer Design | 5/9/2018 | | 5/10/2018 | | PASS |
DeAnn Brown
|
|
|
A plug permit will be required to obtain the demo permit. Sewer tap will be plugged at property line to avoid any damage due to demo work entering the mainline. Reconnection may be completed at a later time.
|
Routing - Erosion and Sediment | 5/8/2018 | | 5/10/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan with narrative and site map approved. RP tbd, needs to be designated before permit can be issued.
|
Routing - Addressing | 5/8/2018 | | 5/9/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/8/2018 | | 5/9/2018 | | PASS |
Rachael Beierle
|
|
|
CONTACT west boise sewer district
|
Routing PW Street Lights | 5/9/2018 | | 5/9/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - Design Review | 5/8/2018 | | 5/9/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH17-00588 and DRH18-00067
|
Routing - PLANNING | 5/8/2018 | | 5/8/2018 | | PASS |
David Moser
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/7/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/7/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/7/2018 | | PASS |
|
|
|
|
Intake Approval | | | 4/24/2018 | | FAIL |
Brian McGowan
|
|
|
Form 310 must be filled out and signed by all the required entities.
Thank you,
Brian McGowan
###-####
|
Application received | | | 4/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 20 2018 9:40AM
|