Second Notice | | 8/18/2019 | 8/26/2019 | | DONE |
|
|
|
This permit finaled on the web by Jackie Phelps
|
First Notice | | 7/25/2019 | 8/8/2019 | | DONE |
|
|
|
mailed 8-9-19
|
Permanent Occupancy | | | 7/15/2019 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 7/12/2019 | 7/12/2019 | 7/12/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 7/8/2019 | 7/8/2019 | 7/9/2019 | P | PASS |
Dave Hannah
|
|
|
ALready walked through with Dave Hanna, BLD final Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
Elevation Cert Rec'd-Final | | | 7/9/2019 | | DONE |
|
|
|
The final Elevation Certificate has been received and is acceptable. Final occupancy may be approved by the building department. Jason Taylor ###-####
|
FIRE-Final Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
already inspected with Jim Page. Final Life safety Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
Elevation Cert Rec'd-Midconst | | | 3/5/2019 | | DONE |
|
|
|
Elevation Certificte #2 recieved/approved. Jason Taylor ###-####
|
BLD-Foundation | 1/31/2019 | 2/1/2019 | 2/1/2019 | A | PART |
Brandon Shaw
|
|
|
Rebar inspection for Anteater Walls and Maintenance Footings...
|
Issue PAID IN FULL permit | | | 8/9/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/9/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/4/2018 | | 7/25/2018 | | PASS |
Michael Hanson
|
|
|
|
Routing Off Site - STRUCTURAL | 7/25/2018 | | 7/25/2018 | | PASS |
Michael Hanson
|
|
|
Per ePlan Chris M @ Stapley. MDH
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2018 | | DONE |
Michael Hanson
|
|
|
|
Routing PW Sewer Design | 7/25/2018 | | 7/25/2018 | | PASS |
DeAnn Brown
|
|
|
Passed per DeAnn Brown ePlan. MDH
|
Routing - PLUMBING | 7/25/2018 | | 7/25/2018 | | PASS |
Daryl Spivey
|
|
|
Per ePlan and BLD18-01253 approval. MDH
|
Permit Ready to Issue | | | 7/25/2018 | | DONE |
|
|
|
Need
GC Form
Revised cert of value (for each permit)
Do Not Issue without BLD18-01253
|
Plan assigned to (M_H) | 4/23/2018 | | 7/25/2018 | | DONE |
Michael Hanson
|
|
|
06/01 #520 L3 ePlan - Zoo Boise Anteater project. 1st review completed - See agency comments in ePlan for review documents. MDH 2nd review completed - See agency comments in ePlan for review comments. MDH 3rd review completed - See agency comments in ePlan for review comments. MDH
|
Routing Off Site - STRUCTURAL | 7/10/2018 | | 7/10/2018 | | FAIL |
Michael Hanson
|
|
|
See attached documents and agency documents section in ePlan review document listing required corrections. MDH
|
Route to Impact Fee Review | 6/4/2018 | 6/7/2018 | 6/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 6/4/2018 | | FAIL |
Michael Hanson
|
|
|
see attached documents and agency document reviews in ePlan. MDH
|
Routing - PLUMBING | 4/23/2018 | | 6/4/2018 | | FAIL |
Daryl Spivey
|
|
|
Fail per Daryl Spivey comments. MDH
|
Routing - PLANNING | 4/23/2018 | | 6/4/2018 | | PASS |
David Moser
|
|
|
Per ePlan approval. MDH
|
Routing - PLAN CHECK | 4/23/2018 | | 6/4/2018 | | FAIL |
Michael Hanson
|
|
|
See attached plan review document. MDH
|
Routing Off Site - STRUCTURAL | 4/23/2018 | | 6/4/2018 | | FAIL |
Michael Hanson
|
|
|
See document from Stapley engineering. MDH
|
Routing PW Solid Waste | 4/23/2018 | | 6/4/2018 | | PASS |
Evan Carpenter
|
|
|
Per ePlan approval. MDH
|
Routing PW Sewer Design | 4/23/2018 | | 6/4/2018 | | FAIL |
DeAnn Brown
|
|
|
Fail per Deann Brown. MDH
|
Routing - FIRE | 4/23/2018 | 4/23/2018 | 5/25/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Flood Plain | 4/23/2018 | | 5/8/2018 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor ###-####
|
Routing PW Drainage | 4/23/2018 | | 5/8/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 4/23/2018 | | 4/30/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - Erosion and Sediment | 4/23/2018 | | 4/25/2018 | | PASS |
Andy J. Long
|
|
|
ESC covered under main site permit for Zoo Boise expansion, see ESC17-01473. No new ESC permit required.
|
Routing PW Street Lights | 4/23/2018 | | 4/24/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - Addressing | 4/23/2018 | | 4/23/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/23/2018 | | 4/23/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/23/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/23/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/23/2018 | | PASS |
|
|
|
|
Application received | | 4/23/2018 | | | |
|
|
|
|