Print Statement | | | 2/8/2019 | | DONE |
|
|
|
|
Second Notice | | 12/24/2018 | 1/8/2019 | | DONE |
|
|
|
mailed 1-11-19
|
First Notice | 11/14/2018 | 11/14/2018 | 12/14/2018 | | DONE |
Brandon Shaw
|
|
|
mailed 12-17
|
BLD-Final | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | PASS |
Brandon Shaw
|
|
|
Please call ahead ###-#### the plans for this project are located in the drive up and go space left hand side of the store at the entry.
thanks Mike Teeter Phone #: ###-#### Inspection requested via web by Mike Teeter
|
DOC - Permit Finaled | 11/14/2018 | 11/14/2018 | 11/14/2018 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The thumbturn deadbolt on the Pick and Go room needs removed prior to a building inspection as per our conversation
please give me a call ahead of time ###-#### thanks Mike Teeter Inspection requested via web by Mike Teeter
|
CHANGE STATUS TO (ISS) | | | 8/13/2018 | | DONE |
|
|
|
Plan mod
|
Plan assigned to (JG) | 8/1/2018 | 8/1/2018 | 8/7/2018 | | PASS |
Javier Guzman
|
|
|
Plan Mod 2 - revise locations of floor sinks at starbucks kiosk, pend plumb
|
Routing - PLAN CHECK | 8/3/2018 | | 8/7/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 8/3/2018 | | 8/7/2018 | | PASS |
Dan Ediger
|
|
|
Per ISPC
|
Permit Ready to Issue | | | 8/7/2018 | | DONE |
|
|
|
plan mod do not re issue
|
Routing - PUBLIC WORKS | 8/3/2018 | | 8/3/2018 | | PASS |
Morgan Webb
|
|
|
|
Plan Modification Accepted | | | 8/1/2018 | | DONE |
|
|
|
Plan Mod 2 - revise locations of floor sinks at starbucks kiosk
|
FIRE-Final Inspection | 7/26/2018 | 7/27/2018 | 7/27/2018 | A | PART |
Troy Cobbley
|
|
|
The Star Bucks is being given a temp with Ron's permission until a fire alarm permit is issued/inspected for the over spaced ceiling mounted 30cd horn/strobe in this space. No other areas inspected.
Phone #: ###-#### Inspection requested via web by Mike Teeter
|
BLD-Other | 7/25/2018 | 7/26/2018 | 7/26/2018 | A | PART |
Jim Storey
|
|
|
I would like to schedule a occupancy inspection for the new Starbucks Kiosk for early morning please. this is just to make sure the inspector is ok with opening the Kiosk. Please call with any questions. Mike Teeter ###-#### Phone #: ###-#### Inspection requested via web by Mike Teeter/ need wire ties 3wraps in 1 inch clips at perimitor
|
BLD-Wall cover | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | PASS |
Jim Storey
|
|
|
looking for a rough inspection for Albertsons Park Center to cover Phone #: ###-#### Inspection requested via web by Mike Teeter ok pending trade aprovals
|
BLD-Framing/Rough-in | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | PART |
Jim Storey
|
|
|
looking for a rough inspection for Albertsons Park Center to cover Phone #: ###-#### Inspection requested via web by Mike Teeter ok pending trade aprovals
|
Permit Ready to Issue | | | 6/18/2018 | | DONE |
|
|
|
PLAN MOD
|
CHANGE STATUS TO (ISS) | | | 6/18/2018 | | DONE |
|
|
|
Plan Mod
|
Inspection Record Card- Bld | | | 6/18/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 6/5/2018 | 6/5/2018 | 6/16/2018 | | PASS |
Javier Guzman
|
|
|
Plan Mod Albertsons
|
Routing - PLAN CHECK | 6/13/2018 | | 6/16/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 6/13/2018 | | 6/14/2018 | | PASS |
Troy James
|
|
|
One supply run and electric radiant heater
|
Routing - Design Review | 6/13/2018 | | 6/13/2018 | | PASS |
Katelyn Menuge
|
|
|
No Design Review Required. Not in Design Overlay.
|
Meeting | | | 6/5/2018 | | DONE |
|
|
|
Plan Mod - add online pick-up area to entry vestibule & partial height CMU wall for cart storage under existing canopy
**Need COV from GC for added value prior to re-issuance**
|
Plan Modification Accepted | | | 6/5/2018 | | DONE |
Christina Prado
|
|
|
Plan Mod - add online pick-up area to entry vestibule & partial height CMU wall for cart storage under existing canopy
**Need COV from GC for added value prior to re-issuance**
|
Issue PAID IN FULL permit | | | 6/1/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/1/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 4/25/2018 | 4/25/2018 | 5/31/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 5/08 L2 Albertsons ePlan, pend Mech
|
Routing PW Environmental | 5/25/2018 | | 5/31/2018 | | PASS |
Rick Christenson
|
|
|
Points source approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/31/2018 | | DONE |
|
|
|
NEED- all met
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 5/25/2018 | | 5/29/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 5/25/2018 | | 5/25/2018 | | PASS |
Daryl Spivey
|
|
|
See redline notes and install per ISPC.
|
Route to Impact Fee Review | 5/15/2018 | 5/18/2018 | 5/16/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - MECHANICAL | 5/11/2018 | | 5/15/2018 | | PASS |
Troy James
|
|
|
No mechanical to review
|
1st review completed | | | 5/15/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 4/25/2018 | | 5/11/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 4/25/2018 | 4/25/2018 | 5/7/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Intake Approval | | | 4/25/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 4/25/2018 | | 4/25/2018 | | PASS |
Daryl Spivey
|
|
|
See redline notes. Per plan and ISPC.
|
Routing - Addressing | 4/25/2018 | | 4/25/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/25/2018 | | 4/25/2018 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 4/23/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 23 2018 1:36PM
|
Routing PW Environmental | 4/25/2018 | | | | FAIL |
|
|
|
Starbucks Kiosk need to be connected to Grease Waste Line
|