DOC - Permit Finaled | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 5/6/2019 | 5/6/2019 | 5/6/2019 | | FAIL |
Jim Storey
|
|
|
called arch of record and chief ele about missing ele permit. no insp. exp pending
|
Issue PAID IN FULL permit | | | 6/20/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/10/2018 | 5/13/2018 | 5/11/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 5/1/2018 | 5/1/2018 | 5/11/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 5/08 L1 BOISE In Flight Kitchen ePlan, pend DR
|
Routing - Design Review | 5/11/2018 | | 5/11/2018 | | PASS |
KayCee Babb
|
|
|
Parapet alterations required for energy code compliance. No DR required.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/11/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/11/2018 | | DONE |
|
|
|
Need
Revised cert of value
GC form
|
1st review completed | | | 5/10/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 5/1/2018 | | 5/10/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 5/1/2018 | | 5/1/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 5/1/2018 | | 5/1/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/1/2018 | | 5/1/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 5/1/2018 | | 5/1/2018 | | FAIL |
KayCee Babb
|
|
|
Design Review application required for proposed project.
|
Intake Approval | | | 5/1/2018 | | PASS |
Javier Guzman
|
|
|
|
Print Statement | | | 4/26/2018 | | DONE |
|
|
|
|
Application received | | | 4/23/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 23 2018 3:22PM
|