BLD-Final | 1/2/2020 | 1/3/2020 | 1/3/2020 | A | PASS |
Brandon Shaw
|
|
|
Please call when you are on your way. ###-#### Phone #: ###-#### Inspection requested via web by Mark Roberts
|
DOC - Permit Finaled | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | PASS |
Brandon Shaw
|
|
|
|
Permanent Occupancy | | | 1/3/2020 | | DONE |
|
|
|
|
Zoning Approval | 1/2/2020 | 1/2/2020 | 1/2/2020 | | PASS |
Katelyn Menuge
|
|
|
|
FIRE-Final Inspection | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire aalrm inspection is complete, fire extinguishers are placed with current inspection tags, knox box is located by the FDC. Final life fire safety inspection for area of work complete, signature card was destroyed, no signatures provided.
Please call when on route. Thank you Phone #: ###-#### Inspection requested via web by Mark Roberts
|
FIRE-Final Inspection | 11/19/2019 | 11/19/2019 | 11/19/2019 | P | FAIL |
Jim Page
|
|
|
Site work for fire truck access is not complete, fire truck access must be complete before life fire safety can be signed off per note number 1 of building permit fire code review. Provide signage for fire sprinkler riser room as well as fire alarm control panel per note number 14. Provide address numbers on both east and south sides per boise municipal code 505.3. Fire sprinkler system requires a re-hydro due to the amount of corrections that were made.
Mark - Fire/Life Safety. Working with sprinkler contractor to get inspection for FIR19-00111 this afternoon as well. Phone #: ###-####
|
FIRE-Final Inspection | 11/15/2019 | 11/18/2019 | 11/18/2019 | A | CANC |
Troy Cobbley
|
|
|
Not ready for final due to the project related fire sprinkler permit not being finaled yet. Mark and I did discuss general life safety requirements. It appears the new fire extinguishers need annual inspection. Mark Phone #: ###-####
|
Print Occupancy Form | | | 11/15/2019 | | DONE |
|
|
|
|
BLD-Conference | 11/11/2019 | 11/12/2019 | 11/12/2019 | A | DONE |
Brandon Shaw
|
|
|
Pre final walk thru...
|
BLD-Aging Inspection | 11/12/2019 | 11/12/2019 | 11/12/2019 | | DEFR |
Brandon Shaw
|
|
|
Work in progress...
|
Extend Permit 90/180 days | 11/12/2019 | 11/12/2019 | 11/12/2019 | P | DONE |
Brandon Shaw
|
|
|
|
BLD-Wall cover | 6/28/2019 | 7/1/2019 | 7/1/2019 | A | PASS |
Brandon Shaw
|
|
|
Need to check that RC channel is approved for cover. Please call me when you''re on your way. Phone #: ###-#### Inspection requested via web by Mark Roberts
|
BLD-Other | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | NR |
Tony Young
|
|
|
Need to check that RC channel is approved for cover. Please call me when you''re on your way. Phone #: ###-#### Inspection requested via web by Mark Roberts
|
BLD-Energy code compliance | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Wall cover | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | FAIL |
Jim Storey
|
|
|
First floor inspection please. Phone #: ###-#### Inspection requested via web by Mark Roberts unable to contact missing rc and fire gyp unusable spaces and line sets not fire chalked/ stair glbs not alowed to bear on concrete.
|
BLD-Wall cover | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PASS |
Brandon Shaw
|
|
|
Second floor only please. Thank you Phone #: ###-#### Inspection requested via web by Mark Roberts
|
BLD-Energy code compliance | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PART |
Brandon Shaw
|
|
|
Ok to cover...
|
Plan assigned to (JAR) | 6/13/2019 | 6/13/2019 | 6/17/2019 | | DONE |
Julie Romig
|
|
|
plan mod erroneously assigned to this permit. Should have been assigned to BLD18-3242
|
CHANGE STATUS TO (ISS) | | | 6/17/2019 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 6/13/2019 | | DONE |
|
|
|
Mirroring Carports to avoid sewer and water lines. Assigned to this permit in error. Should have been assigned to BLD18-03242.
|
BLD-Conference | 6/10/2019 | 6/11/2019 | 6/11/2019 | A | DONE |
Brandon Shaw
|
|
|
Talked with Brandon, we are planning on meeting onsite at 9 AM. Thank you Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD-Framing/Rough-in | 6/7/2019 | 6/10/2019 | 6/10/2019 | A | DEFR |
Brandon Shaw
|
|
|
Approved plans are in the riser room Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD-Framing/Rough-in | 6/7/2019 | 6/7/2019 | 6/7/2019 | P | FAIL |
Brandon Shaw
|
|
|
Need Mech rough-in...
|
Telephone call | | | 6/6/2019 | | DONE |
|
|
|
called Ward-he was having issues with downloading the approved drawings-he said the down load arrow was not in there but when i went in it was there. He's going to try again and he'll call if he has any more problems
|
OVERRIDE | | | 6/4/2019 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/4/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/4/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/4/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/4/2019 | | DONE |
|
|
|
plan mod approved *PLEASE DONT ISSUE PERMIT*
|
Plan assigned to (JAR) | 5/24/2019 | 5/24/2019 | 6/3/2019 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - Plan Mod Council Springs - HVAC changes
|
Routing - PLAN CHECK | 6/3/2019 | | 6/3/2019 | | PASS |
Julie Romig
|
|
|
2nd Review
|
Routing - PLAN CHECK | 5/28/2019 | | 6/1/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 5/28/2019 | | 5/31/2019 | | PASS |
Troy James
|
|
|
Pass per ePlan
|
Plan Modification Accepted | | | 5/24/2019 | | DONE |
|
|
|
Removing dryer vents to go ventless, removing EF in laundry and adding transfer grille between bathroom and laundry
|
BLD-Conference | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | PART |
Brandon Shaw
|
|
|
Pre-framing/ Fire caulking...
|
BLD-Framing/Rough-in | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | PART |
Brandon Shaw
|
|
|
Partial framing inspection Soffits and stairwells...
|
BLD-Wall Bracing | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | PASS |
Mike Jordan
|
|
|
Shear inspection. Approved plans are in garage. I would like to meet inspector on site please give me a call ###-#### Phone #: ###-#### Inspection requested via web by Andy Eells. Exterior and interior shear ok.
|
BLD-Conference | 1/23/2019 | 1/23/2019 | 1/23/2019 | P | DONE |
Brandon Shaw
|
|
|
|
BLD-Footing | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PASS |
Brandon Shaw
|
|
|
Frost protection is required...
|
BLD-Foundation | 11/6/2018 | 11/7/2018 | 11/7/2018 | A | PASS |
Brandon Shaw
|
|
|
Jared Draper is concrete guy. Requested 9 am please if possible. 2500 psi concrete spec. Inspection for foundation wall Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD-Footing | 11/2/2018 | 11/5/2018 | 11/5/2018 | A | PASS |
Jim Storey
|
|
|
MTI scheduled for bar placement at 10am on the 5th. 2500psi spec mix. Sawtooth L.S staked out building Phone #: ###-#### Inspection requested via web by Andy Eells rebar ok si pending reports
|
(F) Reprint permit | | | 11/2/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/2/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/1/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/1/2018 | | DONE |
|
|
|
emailed permits to be signed to trav.pinnaclebuilders@gmail.com-included Brittany's email since I'm off 11/2/18
|
OVERRIDE | | | 10/24/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 6/7/2018 | 6/7/2018 | 10/24/2018 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 6th Rev Comp - 506 Council Springs Apartments
|
Routing - PLAN CHECK | 10/24/2018 | | 10/24/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/24/2018 | | DONE |
|
|
|
NEED - ALL MET - email permits to BreeAnn Sjostrom
RP
ACHD
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 10/15/2018 | | 10/16/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - Design Review | 10/15/2018 | | 10/15/2018 | | PASS |
|
|
|
|
Routing PW Sewer Design | 10/15/2018 | | 10/15/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing Off Site - STRUCTURAL | 10/6/2018 | | 10/10/2018 | | PASS |
Julie Romig
|
|
|
5th Review
|
Routing - PLAN CHECK | 10/6/2018 | | 10/10/2018 | | FAIL |
Julie Romig
|
|
|
5th Review. Outstanding corrections required by other departments.
|
Routing PW Sewer Design | 10/6/2018 | | 10/9/2018 | | FAIL |
DeAnn Brown
|
|
|
Both civil site plans and plumbing plans were altered and now the plumbing plan sewer connection location again does not match the civil plan sewer connection. Coordinate and revise either plumbing or civil site plans.
|
Routing - Design Review | 10/6/2018 | | 10/8/2018 | | FAIL |
Katelyn Menuge
|
|
|
Please wait to resubmit until Design Review Approval is issued and drawings have been updated to comply with the conditions.
|
Routing Off Site - STRUCTURAL | 9/19/2018 | | 9/28/2018 | | FAIL |
Julie Romig
|
|
|
4th Review - 1/2 hour review time (KPFF)
|
Routing - PLAN CHECK | 9/19/2018 | | 9/28/2018 | | FAIL |
Julie Romig
|
|
|
Outstanding corrections required by other departments. All building reveiw items resolved.
|
Routing - MECHANICAL | 9/19/2018 | | 9/19/2018 | | PASS |
Troy James
|
|
|
4th Review - Fee Sheet added in ePlan
|
Routing - PLUMBING | 9/19/2018 | | 9/19/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Design Review | 9/19/2018 | | 9/19/2018 | | FAIL |
Katelyn Menuge
|
|
|
4th Review - Fee Sheet added in ePlan. See changemarks.
|
Routing PW Sewer Design | 9/19/2018 | | 9/19/2018 | | FAIL |
DeAnn Brown
|
|
|
Changemarks on sheet C2 for labeling existing manhole and removing water coordination with City of Boise note have not been addressed. Revise and resubmit.
|
Routing Off Site - STRUCTURAL | 9/5/2018 | | 9/14/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 9/5/2018 | | 9/12/2018 | | FAIL |
Julie Romig
|
|
|
Outstanding corrections required by other departments. All building review items resolved.
|
Routing - MECHANICAL | 9/5/2018 | | 9/11/2018 | | FAIL |
Troy James
|
|
|
Waiting for mechanical engineer to upload new mechanical sheet addressing mechanical ventilation.
|
Routing - FIRE | 9/5/2018 | 9/5/2018 | 9/6/2018 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
Routing - Design Review | 9/5/2018 | | 9/5/2018 | | FAIL |
Katelyn Menuge
|
|
|
Need new Harris Ranch Review Board and Boise Design Review approvals prior to building permit sign-off.
|
Routing PW Sewer Design | 9/5/2018 | | 9/5/2018 | | FAIL |
DeAnn Brown
|
|
|
Revise and resubmit sheet C2. Location of sewer service exit from building is different between the plumbing and civil plans. Sewer service exits building on the south wall on civil plans and exits east wall on plumbing plans. Coordinate and revise location of sewer service. Keynote 14 on sheet C2 states coordination with City of Boise for water meter connection. Suez operates the water service, remove coordination with City of Boise. Label existing sewer manhole as SSMH 667A14.
|
Routing Off Site - STRUCTURAL | 8/18/2018 | | 8/29/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 8/18/2018 | | 8/27/2018 | | FAIL |
Troy James
|
|
|
Previous correction has not been addressed. Left message with mechanical engineer. Have not received a call back.
|
Routing - FIRE | 8/18/2018 | 8/18/2018 | 8/24/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - PLAN CHECK | 8/18/2018 | | 8/24/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLUMBING | 8/18/2018 | | 8/20/2018 | | PASS |
Daryl Spivey
|
|
|
See redline notes and install per ISPC.
|
Routing PW Sewer Design | 8/18/2018 | | 8/20/2018 | | FAIL |
DeAnn Brown
|
|
|
Revise and resubmit sheet C2. Location of sewer service exit from building is different between the plumbing and civil plans. Sewer service exits building on the south wall on civil plans and exits east wall on plumbing plans. Coordinate and revise location of sewer service. Keynote 14 on sheet C2 states coordination with City of Boise for water meter connection. Suez operates the water service, remove coordination with City of Boise. Label existing sewer manhole as SSMH 667A14.
|
Routing PW Drainage | 8/18/2018 | | 8/20/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 8/18/2018 | | 8/20/2018 | | FAIL |
Katelyn Menuge
|
|
|
Submittal of written Harris Ranch Review Board approval letter and new Design Review application and approval are required for the design modifications. Pedestrian walkway adjacent to 18 foot long parking stalls shall be a minimum of 8 feet wide. Condenser will require screening.
|
Route to Impact Fee Review | 7/27/2018 | 7/30/2018 | 7/31/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 6/7/2018 | | 7/27/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 6/7/2018 | | 7/27/2018 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 7/27/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 6/7/2018 | 6/7/2018 | 7/19/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect and applicant
|
Routing PW Drainage | 6/8/2018 | | 6/12/2018 | | FAIL |
Brian Murphy
|
|
|
PLAN NOTE STATES NOT FOR CONSTRUCTION.
|
Routing - Addressing | 6/7/2018 | | 6/12/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 6/7/2018 | | 6/11/2018 | | FAIL |
Troy James
|
|
|
Talked to mechanical engineer about the mechanical ventilation requirements.
|
Routing - PLUMBING | 6/7/2018 | | 6/11/2018 | | PASS |
Bill VanDegrift
|
|
|
provide information on shutoff valves for the tub and shower valves.ISPC 606.3
|
Routing - PLANNING | 6/7/2018 | | 6/8/2018 | | PASS |
David Moser
|
|
|
See DRH17-00003
|
Routing - PUBLIC WORKS | 6/7/2018 | | 6/8/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 6/7/2018 | | 6/8/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified PD & RP designated. Site preparation inspection is required
|
Routing PW Solid Waste | 6/8/2018 | | 6/8/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Sewer Design | 6/8/2018 | | 6/8/2018 | | FAIL |
DeAnn Brown
|
|
|
Please make changes to sheet C2 according to changemarks in eplanreview.
|
Routing PW Street Lights | 6/8/2018 | | 6/8/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - Design Review | 6/7/2018 | | 6/8/2018 | | FAIL |
Katelyn Menuge
|
|
|
Submittal of written Harris Ranch Review Board approval letter and new Design Review application and approval are required for the design modifications. Pedestrian walkway adjacent to 18 foot long parking stalls shall be a minimum of 8 feet wide. Condenser will require screening.
|
Intake Approval | | | 6/7/2018 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/7/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/7/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/29/2018 | | FAIL |
Javier Guzman
|
|
|
Please provide and upload the following:
• The previous request for owner’s signature on the already filled out and uploaded #310 form returned without the engineer’s stamp and engineers information on the form, please revise so that a one single completed form #310 is signed by the owner, stamped and signed by the Idaho licensed engineer, and is completely filled out (nothing left blank)
• The following plan sheets were previously requested and Not uploaded again, please provide and upload plumbing plan sheets P6 and P7 (P6 = third floor water plan and P7 = Schedules/details), please upload these sheets.
|
Intake Approval | | | 5/3/2018 | | FAIL |
Javier Guzman
|
|
|
Please provide and upload the following:
• Please provide owners signature and date on the filled out uploaded form #310
• Structural plan sheets S20, S21, S22, S23 are required to be stamped by an Idaho licensed engineer
• The following plan sheets were previously requested and Not uploaded P6 and P7, please upload these sheets
|
Intake Approval | | | 5/2/2018 | | FAIL |
Javier Guzman
|
|
|
Please provide and upload the following:
• Provide A completed form #310 found at our website at https://pds.cityofboise.org/media/104147/final310_special_inspections.pdf
• Provide Erosion & Sediment Control (ESC) Narrative. The Narrative must be designed for the specific project, and be prepared and signed by a plan designer certified by Boise City.
• There are four sheets that need to be uploaded in the landscape horizontal format that have been uploaded in the vertical position (these sheets are 16-100 E-1, 16-100 E-2, 16-100 E-3 and 16-100 E-4) ePlan submittal standards can be found at https://pds.cityofboise.org/media/464072/electronic_standards_full.pdf
• Show Stair details showing tread and riser sizes
• Show carbon monoxide alarm locations
• NO structural “S” sheets have been uploaded, please provide
• Provide an ACCA approved design software analysis output reports (for residential buildings three (3) stories or less where mechanical systems serve individual units) showing compliance with the design requirements of Manual J (load calculations), Manual D (duct systems), and Manual S (equipment selection). Include a duct system layout noting duct sizes, lengths, and termination points with cfm outputs.
• The following plan sheets were Not uploaded A3.1, A5.0, P6 and P7. Please provide
|
Application received | | | 4/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 27 2018 8:41AM
|
First Notice | | 1/13/2020 | | | |
|
|
|
|
First Notice | 1/3/2020 | 1/3/2020 | | | |
Brandon Shaw
|
|
|
|