BLD-Aging Inspection | 6/21/2019 | 6/21/2019 | 6/21/2019 | | CANC |
Mike Jordan
|
|
|
|
Issue PAID IN FULL permit | | | 8/6/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/6/2018 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 6/20/2018 | | 7/19/2018 | | DONE |
Michael Hanson
|
|
|
07/31 #502 L1 ePlan - Modular restroom New
|
Routing - PLAN CHECK | 6/20/2018 | | 7/19/2018 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 7/19/2018 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 7/19/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 7/19/2018 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE
|
Routing - FIRE | 6/20/2018 | 6/20/2018 | 7/17/2018 | | PASS |
Erika Akin
|
|
|
U Occupancy. No comments attached
|
Routing PW Drainage | 6/20/2018 | | 6/21/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING | 6/20/2018 | | 6/21/2018 | | PASS |
David Moser
|
|
|
|
Routing - Addressing | 6/20/2018 | | 6/20/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/20/2018 | | 6/20/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 6/20/2018 | | 6/20/2018 | | PASS |
Andy J. Long
|
|
|
No ESC permit required, see existing ESC permit ESC17-00510
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/20/2018 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/19/2018 | | DONE |
Julie Romig
|
|
|
Accepted prescreen without State Modular Tag Number. Wendy Larimore is in process of getting the Tag Number. Told her we could review while she is waiting for the number, but could not issue the permit until we receive the number.
|
Intake Approval | | | 4/30/2018 | | FAIL |
Julie Romig
|
|
|
1. Upload drawing sheets as individual PDF files for each sheet, named per naming conventions with sheet number and brief description (ex. E1_Electrical Site Plan). All drawings must be a minimum of 18"x24" sheet size. Drawings have been deleted so they can be re-uploaded with proper names, sizes, and as individual sheets.
2. Interior and Exterior Lighting COMcheck for new lighting (can be submitted as 8 1/2"x11" documents).
|
Intake Approval | | | 4/30/2018 | | FAIL |
Julie Romig
|
|
|
Need State Modular Tag Number
|
Application received | | | 4/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 27 2018 9:50AM
|
Print Statement | | | 4/27/2018 | | DONE |
Rita DeYoung
|
|
|
|