Permit Information
Permit NumberBLD18-01504
StatusFinaled
Name REILLY CONSTRUCTION LLC
Site Address 4455 E WARM SPRINGS AVE
Project NameAspen Valley - Early Start
Customer NumberBLD18-00494
ePlanReviewYes
Description
(ASPEN VALLEY SENIOR LIVING – ASSISTED LIVING AND MEMORY CARE FACILITIES – EARLY START FOOTINGS, FOUNDATIONS, UNDER SLAB PLUMBING, AND SLAB ON GRADE PERMIT) To construct the footings, foundations, under slab plumbing, and slab on grade elements for a new 47,379 square foot, one story building with a fire wall to be used as an assisted living facility (50 units) and as a memory care facility (16 units having a total floor area of about 6,853 square feet). The rest of the building will be constructed under permit BLD18-00494. A separate plumbing permit is required for under slab plumbing. Special Inspection is required for soils, concrete, shear walls, and roof diaphragms. The work is required to comply with the approved structural drawings. CJW
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Zoning Approval4/29/20194/29/20194/29/2019 PASS
DetailsKatelyn Menuge
DOC - Permit Finaled  8/22/2018 DONE
BLD-Concrete7/19/20187/19/20187/19/2018PPART
DetailsMike Jordan
rebar-Shane Phone #: ###-####
BLD-Concrete7/5/20187/6/20187/6/2018PPASS
DetailsBrandon Shaw
Shane Phone #: ###-####
BLD-Concrete6/29/20187/2/20187/2/2018PPART
DetailsBrandon Shaw
shane Phone #: ###-####
BLD-Foundation6/27/20186/28/20186/28/2018PPART
DetailsBrandon Shaw
Southeast side
BLD-Foundation6/22/20186/22/20186/22/2018PPASS
DetailsJim Storey
Manuel Phone #: ###-#### west walls pass
BLD-Footing6/20/20186/21/20186/21/2018APASS
DetailsBrandon Shaw
West end footing and car port at main enrty way
BLD-Foundation5/22/20185/22/20185/22/2018PPART
DetailsBrandon Shaw
Noth and South stem walls
BLD-Footing5/21/20185/21/20185/21/2018PPART
DetailsBrandon Shaw
North and South walls footings
BLD-Foundation5/14/20185/15/20185/15/2018APASS
DetailsBrandon Shaw
Interior courtyards
BLD-Footing5/11/20185/11/20185/11/2018PPASS
DetailsBrandon Shaw
Interior walls/ courtyards
BLD-Foundation5/10/20185/10/20185/10/2018PPART
DetailsBrandon Shaw
Exterior foundation, main building- South and East sides
BLD-Footing5/7/20185/8/20185/8/2018APART
DetailsBrandon Shaw
Exterior footings, main building- South and East sides
Issue PAID IN FULL permit  5/3/2018 DONE
OVERRIDE  5/1/2018  
Routing - PLAN CHECK4/27/2018 5/1/2018 PASS
DetailsCarl Westfall
Footing, foundation, underslab plumbing, and concrete slab on grade.
Plan assigned to (CJW)4/27/2018 5/1/2018 PASS
DetailsCarl Westfall
x Early start footings, foundations, under slab plumbing, and concrete slab on grade permit.
1st review completed  5/1/2018 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/1/2018 DONE
Permit Ready to Issue  5/1/2018 DONE
Need
RP
Revised Cert of Value
GC Form
Routing Off Site - STRUCTURAL3/6/2018 4/30/2018 PASS
DetailsCarl Westfall
Jordan Terry (KPFF) - Footing, foundation, underslab plumbing, and concrete slab on grade.
Routing - PLUMBING3/6/2018 3/8/2018 PASS
DetailsBill VanDegrift
Footing, foundation, underslab plumbing, and concrete slab on grade. Separate permit required for under slab plumbing.
Routing - Erosion and Sediment3/6/2018 3/7/2018 PASS
DetailsMichael Zawacki
Footing, foundation, underslab plumbing, and concrete slab on grade.
Application received 4/27/2018  DONE
DetailsCarl Westfall
Footings, foundations, under slab plumbing, and concrete slab on grade permit requested