Print Statement | | | 11/20/2018 | | DONE |
|
|
|
|
Second Notice | | 10/21/2018 | 11/6/2018 | | DONE |
|
|
|
mailed 11-12
|
First Notice | | 9/27/2018 | 10/11/2018 | | DONE |
|
|
|
mailed 10-12-18
|
BLD-Final | 9/14/2018 | 9/17/2018 | 9/17/2018 | A | PASS |
Tony Young
|
|
|
Ken Phone #: ###-####,, ok per 450
|
FIRE-Final Inspection | 9/14/2018 | 9/17/2018 | 9/17/2018 | A | PASS |
Mike Jordan
|
|
|
Ken Phone #: ###-####. All issues have been resolved.
|
Permanent Occupancy | | | 9/17/2018 | | DONE |
|
|
|
|
BLD-Final | 9/14/2018 | 9/14/2018 | 9/14/2018 | P | PEND |
Mike Jordan
|
|
|
Ken-would like as late pm as possible-trying to get C of O today Phone #: ###-####-please call when on way. everything ok. Will be ok for prm occ. once life/safety signs prem.
|
FIRE-Final Inspection | 9/14/2018 | 9/14/2018 | 9/14/2018 | P | FAIL |
Mike Jordan
|
|
|
Ken-would like as early pm as possible-trying to get C of O today Phone #: ###-####. Repair the 2 non functioning emergency lights and remove the thumturn dead bolt.
|
FIRE-Final Inspection | 9/6/2018 | 9/7/2018 | 9/7/2018 | P | PART |
Jim Page
|
|
|
No fire sprinklers, smoke detectors are stand-alone, fire extinguishers are placed with current inspection tags, emergency lighting for exterior discharge landings to be installed as discussed, 30 day TCO authorized contingent on the exterior emergency lighting getting installed, after exterior emergency lighting is installed a follow up life fire safety inspection will need to be completed. Remove thumbturn deadbolts as discussed before next final life fire safety inspection.
Ken Barr Phone #: ###-####
|
Print Occupancy Form | | | 8/30/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PASS |
Tony Young
|
|
|
Ken Phone #: ###-####
|
BLD-Conference | 8/16/2018 | 8/16/2018 | 8/16/2018 | P | PART |
Tony Young
|
|
|
Ken Phone #: ###-####,, fireplace load ?s
|
BLD-Footing | 7/30/2018 | 7/30/2018 | 7/30/2018 | P | PART |
Tony Young
|
|
|
late afternoon- Ken Phone #: ###-####,, work in progress on pergola footings
|
BLD-Footing | 7/23/2018 | 7/24/2018 | 7/24/2018 | P | NR |
Tony Young
|
|
|
pergola - Ken Phone #: ###-####
|
BLD-Footing | 7/20/2018 | 7/23/2018 | 7/23/2018 | P | NR |
Tony Young
|
|
|
pergola - Ken Phone #: ###-####
|
BLD-Footing | 7/19/2018 | 7/20/2018 | 7/21/2018 | P | NR |
Tony Young
|
|
|
as late in pm as possible pergola - Ken Phone #: ###-####
|
BLD-Framing/Rough-in | 7/19/2018 | 7/20/2018 | 7/20/2018 | A | PASS |
Tony Young
|
|
|
Ken Phone #: ###-####
|
BLD-Framing/Rough-in | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | PART |
Tony Young
|
|
|
Ken Phone #: ###-####,, needs headers supported,, ok to insulate,, ok to cover exterior
|
Print Occupancy Form | | | 7/2/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/2/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 5/10/2018 | 5/10/2018 | 6/28/2018 | | DONE |
Julie Romig
|
|
|
*1st Rev Comp - 06/27 4th Rec'd - L3 Edgewater Clubhouse
|
Routing - PLUMBING | 6/27/2018 | | 6/28/2018 | | PASS |
Daryl Spivey
|
|
|
See redline notes. Install per ISPC.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/28/2018 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 6/27/2018 | | 6/27/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 6/20/2018 | | 6/27/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLUMBING | 6/20/2018 | | 6/26/2018 | | FAIL |
Daryl Spivey
|
|
|
Venting not approved per ISPC. Gravity drainage if grade permits.
|
Routing - PLUMBING | 6/11/2018 | | 6/11/2018 | | FAIL |
Daryl Spivey
|
|
|
2 in. minimum waste sizing under ground and Sink and pump shall be vented as required by ISPC.
|
Routing - PLAN CHECK | 6/7/2018 | | 6/8/2018 | | FAIL |
Julie Romig
|
|
|
|
Route to Impact Fee Review | 5/25/2018 | 5/28/2018 | 5/29/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 5/10/2018 | 5/10/2018 | 5/25/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 5/25/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 5/10/2018 | | 5/25/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - Erosion and Sediment | 5/10/2018 | | 5/16/2018 | | PASS |
Andy J. Long
|
|
|
No exterior disturbance listed. No ESC permit required per scope of work.
|
Routing - Addressing | 5/10/2018 | | 5/11/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLUMBING | 5/10/2018 | | 5/11/2018 | | FAIL |
Bill VanDegrift
|
|
|
Air admittance valves not approved for commercial use. 909.1 ISPC. 2 in. minimum sizing for underground waste and vent piping.
|
Routing - PLANNING | 5/10/2018 | | 5/10/2018 | | PASS |
Leon Letson
|
|
|
No Review Required
|
Routing - Design Review | 5/10/2018 | | 5/10/2018 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 5/10/2018 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/10/2018 | | 5/10/2018 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 5/4/2018 | | FAIL |
Michael Hanson
|
|
|
1. All sheet must be stamped and signed by a Idaho registered design professional.
2. Multiple sheets have "not for construction" stamp. Only submit final sheet sets stamped and signed.
|
Application received | | | 4/30/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 30 2018 10:37AM
|
Extend Review Timeline | | | 4/30/2018 | | DONE |
|
|
|
Should only be for 180 days not one year
|