Plan Reviewer's activity | | | 4/13/2020 | | DONE |
|
|
|
Drawings taken to Records
|
FIRE-Final Inspection | 11/21/2019 | 11/22/2019 | 11/22/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Dave Phone #: ###-####
|
FIRE-Final Inspection | 11/20/2019 | 11/21/2019 | 11/21/2019 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans or small documents on site. No inspection performed. David Phone #: ###-####
|
Meeting | | | 11/20/2019 | | DONE |
|
|
|
fax came in from david requesting the occupancy. called him informing him that he still needs to have the zoning, fire life and building inspections completed
|
Issue PAID IN FULL permit | | | 10/30/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/30/2019 | | DONE |
|
|
|
|
Telephone call | | | 10/25/2019 | | DONE |
|
|
|
sent an email to dave informing him the gc has not come in to sign for the permit and pick up the plans. permit is now showing to be 2 days past the date
|
Meeting | | | 9/27/2019 | | DONE |
|
|
|
Dave, with the church, brought paper work in and paid fees. informed him that the GC will need to come in to sign for the permit and pick up the approved plans
|
Plan assigned to (CJW) | 5/1/2018 | 5/1/2018 | 9/23/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 05/21/18 (L3 - 15 days) (paper - 1 sheet) Calvary Chapel (waiting for applicant to resolve Planning issues)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/23/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/23/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/23/2019 | | DONE |
|
|
|
MET MEMBER OF CHURCH PAID FOR PERMIT
Need
GC Form
Revised Value
MET
ACHD
|
Telephone call | | | 9/23/2019 | | DONE |
|
|
|
spoke with dave informing him that the permit is ready; told him what else is needed for issuance
|
Routing - PLANNING | 9/19/2019 | | 9/19/2019 | | PASS |
Brent Moore
|
|
|
Determined this was primarily an office use and not a church.
|
Plan Reviewer's activity | | | 8/16/2019 | | DONE |
Carl Westfall
|
|
|
The following Email was sent on 8-16-19.
Cathy,
Back on May 7, 2018, Andrea Tuning in Planning noted that a Conditional Use Permit was required for this church use in this zone. She noted that the applicant was contacted. Andrea is in transition to a new position so she is no longer your contact in Planning for this project.
I recommend that you contact Leon Letson in Planning at ###-#### to determine the next steps for getting Planning approval.
I approved the Building Code plan review. Once Planning is satisfied, we will be able to issue a permit. Call me if you have questions. Thanks.
Carl J. Westfall
Boise City IBC Plans Examiner
###-####
|
Routing - PLAN CHECK | 8/15/2019 | | 8/16/2019 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 8/15/2019 | | DONE |
|
|
|
Documents received by Email
|
Plan Reviewer's activity | | | 6/28/2019 | | DONE |
|
|
|
Sent an Email to the Architect asking for more information.
|
Extend Review Timeline | | | 4/12/2019 | | DONE |
|
|
|
1st extension approved. New exp. date is 4/26/19
|
Extend Review Timeline | | | 4/12/2019 | | DONE |
|
|
|
2nd extension approved. New exp. date is 10/23/19
|
Plan Reviewer's activity | | | 4/11/2019 | | DONE |
|
|
|
Got an E-mail from the Architect who plans on requesting two extensions.
|
Plan Reviewer's activity | | | 4/9/2019 | | DONE |
|
|
|
Telephoned the Architect and also sent an Email asking about the status of this project.
|
Telephone call | | | 1/7/2019 | | DONE |
|
|
|
Called the Architect and asked for a status report. Left a voice mail message.
|
Route to Impact Fee Review | 7/3/2018 | 7/6/2018 | 7/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan Reviewer's activity | | | 5/22/2018 | | DONE |
|
|
|
Emailed the architect asking for a status update
|
Routing - FIRE | 5/7/2018 | 5/7/2018 | 5/7/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case and plans
|
Routing - PLANNING | | | 5/7/2018 | | FAIL |
Andrea Tuning
|
|
|
A church use will require a Conditional Use Permit. Contacted the applicant.
|
1st review completed | | | 5/7/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/5/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/1/2018 | | 5/5/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - Addressing | 5/1/2018 | | 5/1/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/1/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/1/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/1/2018 | | PASS |
|
|
|
per CJW
|
Zoning Approval | 11/20/2019 | 11/20/2019 | | | PASS |
|
|
|
|
Application received | | 5/1/2018 | | | |
|
|
|
|