Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD18-01541
StatusFinaled
Name AURIC SOLAR
Site Address 2812 S HARMONY ST
Project Name176167 - Beale
Customer Number 
ePlanReviewYes
Description
Permit for a 14 panel, ground-mounted, grid-tied Photo-voltaic array with micro-inverters tying into a Westinghouse panel. There will be twelve 12" round footings; the front six 30" deep, the back six 39" deep per engineered manufacturer's specs. All work per plans, engineering, manufacturer’s specs, & local code. Separate electrical permit required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/16/20187/17/20187/17/2018APASS
DetailsJim Storey
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes
DOC - Permit Finaled7/17/20187/17/20187/17/2018PPASS
DetailsJim Storey
BLD-Framing/Rough-in7/10/20187/11/20187/11/2018PPASS
DetailsJim Storey
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes footting ok
BLD-Footing7/11/20187/11/20187/11/2018PPASS
DetailsJim Storey
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes
BLD-Framing/Rough-in6/22/20186/25/20186/25/2018PNR
DetailsJim Storey
Pls contact Brad (Foreman) @ ###-#### or Preston (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes
Issue PAID IN FULL permit  5/14/2018 DONE
(F) Reprint permit  5/14/2018 DONE
Inspection Record Card- Bld  5/14/2018 DONE
Plan assigned to (JAB) Josh5/1/20185/1/20185/11/2018 PASS
DetailsJosh Bogle
1st done - PV
Routing - PLAN CHECK5/11/2018 5/11/2018 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  5/11/2018 DONE
DetailsJosh Bogle
Permit Ready to Issue  5/11/2018 DONE
met
Routing - PLAN CHECK5/1/2018 5/2/2018 FAIL
DetailsJosh Bogle
1st review completed  5/2/2018 FAIL
DetailsJosh Bogle
Application received  5/1/2018 DONE
Application submitted via PDS Online on May 1 2018 2:59PM
Plans ACCEPTED BY PLAN TECH  5/1/2018 DONE
Intake Approval  5/1/2018 PASS
Recd Pcfee & Taken To Pln CK  5/1/2018 DONE
Routing - PLANNING5/1/2018 5/1/2018 PASS
DetailsColleen T Carroll