BLD-Final | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Beck//Zoning complete//bevel was created under nosing of stairs to meet ANSI requirements//per the plan modification to remove the ramp, the project appears to be complete per the scope//no isnpection card onsite to sign//
|
Zoning Approval | 7/6/2020 | 7/6/2020 | 7/6/2020 | | DONE |
Michaella Owens
|
|
|
|
BLD-Final | 6/30/2020 | 6/30/2020 | 6/30/2020 | P | NR |
Tell Riley
|
|
|
need to remove electrical requirement from permit, obtain zoning final approval//bevel or radius underside of projection at nosing of treads//
|
BLD-Final | 6/29/2020 | 6/30/2020 | 6/30/2020 | A | CANC |
Tell Riley
|
|
|
For access please call Gary @ ###-#### 30 min prior to arrival. Thanks! Phone #: ###-#### Inspection requested via web by Gary Beck//unable to make contact with Gary, called and left VM with no response//two other calls went straight to voicemail//
|
BLD-Final | 6/19/2020 | 6/19/2020 | 6/19/2020 | P | NR |
Tell Riley
|
|
|
For building access, please call Jon Jackson @ ###-#### thirty minutes prior to arrival. Thanks! Phone #: ###-#### Inspection requested via web by Gary Beck//need zoning approval prior to final//
|
FIRE-Final Inspection | 6/16/2020 | 6/17/2020 | 6/17/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
For building access please call Karl Miller 30 minutes prior to arrival @ ###-#### Phone #: ###-#### Inspection requested via web by Gary Beck
|
FIRE-Final Inspection | 6/4/2020 | 6/4/2020 | 6/4/2020 | P | FAIL |
Troy Cobbley
|
|
|
Need plans and small documents. For access, call Karl Miller @ ###-#### twenty minutes before arrival. Phone #: ###-#### Inspection requested via web by Gary Beck
|
CHANGE STATUS TO (ISS) | | | 4/23/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/8/2020 | | DONE |
|
|
|
Plan Mod Met
|
Plan assigned to (RMH) | 3/20/2020 | 3/20/2020 | 4/7/2020 | | PASS |
Ron Hill
|
|
|
plan mod The Masonry Center
|
Routing - Design Review | 3/25/2020 | | 4/7/2020 | | PASS |
KayCee Babb
|
|
|
|
Routing - PLAN CHECK | 3/25/2020 | | 4/7/2020 | | PASS |
Ron Hill
|
|
|
|
Routing - PLANNING | 4/6/2020 | | 4/7/2020 | | PASS |
KayCee Babb
|
|
|
|
Routing - PLAN CHECK | 4/6/2020 | | 4/7/2020 | | PASS |
Ron Hill
|
|
|
|
1st review completed | | | 4/7/2020 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2020 | | DONE |
|
|
|
|
Routing - Design Review | 4/7/2020 | | 4/7/2020 | | PASS |
Michaella Owens
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/6/2020 | | |
|
|
|
|
Routing - Design Review | 3/26/2020 | | 3/26/2020 | | FAIL |
KayCee Babb
|
|
|
Revised plans do not comply with plans approved through CZC18-00029. A new Zoning Certificate is required for further Design Review.
|
Plan Modification Accepted | | | 3/20/2020 | | DONE |
|
|
|
Mark Hirshi submitted a plan mod application to reduce scope of work
|
Print Occupancy Form | | | 8/28/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/28/2018 | | DONE |
|
|
|
|
Plan assigned to (RMH) | 6/7/2018 | 6/7/2018 | 7/18/2018 | | PASS |
Ron Hill
|
|
|
6/06 L2 Masonry Center Ramp ePlan**
|
Routing - PLAN CHECK | 5/24/2018 | | 7/18/2018 | | PASS |
Ron Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/18/2018 | | DONE |
|
|
|
NEED
GC
Rev Cert of Val
|
Routing - Design Review | 7/13/2018 | | 7/13/2018 | | PASS |
KayCee Babb
|
|
|
per CZC18-00029. Tile colors submitted and approved.
|
Route to Impact Fee Review | 6/8/2018 | 6/11/2018 | 6/11/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing Off Site - STRUCTURAL | 5/24/2018 | | 6/8/2018 | | FAIL |
Javier Guzman
|
|
|
ahj
|
1st review completed | | | 6/8/2018 | | FAIL |
|
|
|
|
Plan assigned to (JG) | 5/24/2018 | 5/24/2018 | 6/7/2018 | | DEFR |
Javier Guzman
|
|
|
6/06 L2 Masonry Center Ramp ePlan**
|
Intake Approval | | | 5/24/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 5/24/2018 | | 5/24/2018 | | FAIL |
KayCee Babb
|
|
|
Tile color needs to be submitted to Design Review Staff for review, per condition on CZC18-00029.
|
Intake Approval | | | 5/21/2018 | | FAIL |
Brian McGowan
|
|
|
Code Data is done for 2012- must be updated to the current codes (2015 IBC ect.).
The Engineer's stamp and signature are not legible on the Cover Sheet of the Engineering.
|
Application received | | | 5/2/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 2 2018 9:17AM
|