BLD-Blower Door Test Results | 12/3/2018 | 12/3/2018 | 12/3/2018 | P | PASS |
Tony Young
|
|
|
John Phone #: ###-####// 3.2 per contractor,, not posted yet
|
DOC - Permit Finaled | 12/3/2018 | 12/3/2018 | 12/3/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 11/30/2018 | 12/3/2018 | 12/3/2018 | A | PASS |
Tony Young
|
|
|
John Phone #: ###-####
|
BLD-Final | 11/29/2018 | 11/30/2018 | 11/30/2018 | A | NR |
Tony Young
|
|
|
John Phone #: ###-####--please call to get access code// needs bloweer door test results,, fire caulk a/c line by the furnace,, tempered glass in the window next to the patio door
|
BLD-Energy code compliance | 9/10/2018 | 9/11/2018 | 9/11/2018 | A | PASS |
Brandon Shaw
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 9/7/2018 | 9/10/2018 | 9/10/2018 | A | PASS |
Jim Sly
|
|
|
John Phone #: ###-#### FRAME AND ENERGY>>>>>OK.
|
BLD-Framing/Rough-in | 9/7/2018 | 9/7/2018 | 9/7/2018 | P | PASS |
Tony Young
|
|
|
Phone #: 208-6=###-####
|
BLD-Framing/Rough-in | 9/5/2018 | 9/5/2018 | 9/5/2018 | P | PART |
Tony Young
|
|
|
Bret Phone #: ###-####,, ok to insulate,, needs
|
BLD-Wall Bracing | 7/27/2018 | 7/27/2018 | 7/30/2018 | P | PASS |
Tony Young
|
|
|
John Phone #: ###-####
|
BLD-Wall Bracing | 7/26/2018 | 7/27/2018 | 7/27/2018 | A | PASS |
Tony Young
|
|
|
John Phone #: ###-####
|
BLD-Footing | 7/5/2018 | 7/5/2018 | 7/5/2018 | P | PASS |
Tony Young
|
|
|
Jose Phone #: ###-####,, ok after adding rebar and adding another side footing on the back of the garage on the edge
|
BLD-Footing | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | NR |
Tony Young
|
|
|
Jose--around 11 is best Phone #: ###-####
|
BLD-Footing | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | NR |
Tony Young
|
|
|
Jose--around 11 is best Phone #: ###-####,, re-digging hole
|
BLD-Footing | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | NR |
Tony Young
|
|
|
Jose--around 11 is best Phone #: ###-####
|
OVERRIDE | | | 6/19/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/19/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/19/2018 | | DONE |
|
|
|
|
Telephone call | | | 6/19/2018 | | DONE |
|
|
|
Called John to inform him the permit ready and what fees are due.
|
Issue PAID IN FULL permit | | | 6/19/2018 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 6/13/2018 | | 6/19/2018 | | DONE |
Michael Hanson
|
|
|
06/19 resub to change from 4 to 3 bedroom
|
Routing - PLAN CHECK | 6/13/2018 | | 6/19/2018 | | PASS |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 6/19/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/19/2018 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 6/13/2018 | | DONE |
|
|
|
permit in RDY status. Received resubs to change floor plan from 4 bedroom to 3 bedroom. Received two copies full size set of plans, put on Michael Hansen's desk
|
OVERRIDE | | | 6/6/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/6/2018 | | DONE |
|
|
|
|
Telephone call | | | 6/6/2018 | | DONE |
|
|
|
Spoke with John informing him that this permit is ready and the fee amount due for issuance
|
Plan assigned to (M_H) | 5/3/2018 | | 6/6/2018 | | DONE |
Michael Hanson
|
|
|
05/16 sfd L1 Paper. 1st review completed - Energy and wall bracing deficiencies. MDH
|
Routing - PLANNING | 6/6/2018 | | 6/6/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - PLAN CHECK | 6/6/2018 | | 6/6/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/6/2018 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 6/4/2018 | | DONE |
|
|
|
received two coipes of shear calcs and three copies of plan sheets 0.0, and two copies of plan sheets 1.0, 5.0; taken to Michael Hansen
|
Plan Reviewer's activity | | | 5/30/2018 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 5/30/2018 | | FAIL |
Michael Hanson
|
|
|
Energy and wall bracing deficiencies. MDH
|
Routing - PLAN CHECK | 5/8/2018 | | 5/30/2018 | | FAIL |
Michael Hanson
|
|
|
Energy and wall bracing deficiencies. MDH
|
Routing - MECHANICAL | 5/3/2018 | | 5/8/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Plan resubmittals received | | | 5/7/2018 | | DONE |
|
|
|
Resubmittals received 2 sheets of 7.0 and took to Mech plan reviewer and put with the drawings
|
Route to Impact Fee Review | 5/3/2018 | 5/6/2018 | 5/4/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 5/3/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/3/2018 | | PASS |
|
|
|
still needs to get us the building cross section but i told him i'd get the permit started around for plan review. He said he'd bring in 2 full sheets
|
Recd Pcfee & Taken To Pln CK | | | 5/3/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 5/3/2018 | | 5/3/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 5/3/2018 | | 5/3/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | | | 5/3/2018 | | PASS |
|
|
|
|
Application received | | 5/3/2018 | | | |
|
|
|
|