BLD-Final | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | DONE |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ken Litzinger
|
DOC - Permit Finaled | 12/13/2018 | 12/13/2018 | 12/13/2018 | P | PASS |
Tony Young
|
|
|
per plan
|
BLD-Final | 12/12/2018 | 12/12/2018 | 12/13/2018 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ken Litzinger,, needs historical 1st
|
Zoning Approval | 12/13/2018 | 12/13/2018 | 12/13/2018 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Energy code compliance | 9/23/2018 | 9/24/2018 | 9/24/2018 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Ken Litzinger ok to cover if its ok with mec
|
BLD-Framing/Rough-in | 9/19/2018 | 9/20/2018 | 9/20/2018 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ken Litzinger,,ok to isulate,, needs mech full pass prior to cover,, verify seal pack at energy
|
Telephone call | | | 8/27/2018 | | DONE |
|
|
|
per Tisha-needs pulled for ADU
|
BLD-Wall Bracing | 7/9/2018 | 7/10/2018 | 7/10/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ken Litzinger
|
BLD-Foundation | 6/5/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
Tony Young
|
|
|
Early afternoon if possible. Thanks Phone #: ###-#### Inspection requested via web by Ken Litzinger
|
BLD-Footing | 6/4/2018 | 6/5/2018 | 6/5/2018 | P | PASS |
Tony Young
|
|
|
Early afternoon if possible. Thanks Phone #: ###-#### Inspection requested via web by Ken Litzinger,, meets plan
|
Issue PAID IN FULL permit | | | 5/24/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/23/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 5/7/2018 | 5/7/2018 | 5/23/2018 | | PASS |
Josh Bogle
|
|
|
1st done - detached garage, fire-wall & structural issues
|
Routing - PLAN CHECK | 5/23/2018 | | 5/23/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/23/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 5/23/2018 | | DONE |
|
|
|
Need
RP
|
Plan Reviewer's activity | | | 5/18/2018 | | FAIL |
Josh Bogle
|
|
|
resubmit task not accpeted, no change to plans, called applicant
|
Routing - PLAN CHECK | 5/7/2018 | | 5/11/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 5/11/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 5/7/2018 | | 5/8/2018 | | PASS |
Ted Vanegas
|
|
|
|
Intake Approval | | | 5/7/2018 | | FAIL |
|
|
|
Show dimensions and distances to the property lines (setbacks) on site plan.
|
Plans ACCEPTED BY PLAN TECH | | | 5/7/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/7/2018 | | DONE |
|
|
|
no fee taken at intake, 406
|
Intake Approval | | | 5/7/2018 | | PASS |
|
|
|
|
Application received | | | 5/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 3 2018 3:20PM
|