Telephone call | | | 8/6/2019 | | DONE |
|
|
|
called to see when we could expect payment on the final values-talked to Jamie, she talked to Amber and they're not sure when it will be paid-they're waiting on the owners-told her that on or around the 20th of Aug there will be a hold put on the account until paid
|
Print Statement | | | 7/25/2019 | | DONE |
|
|
|
sent 3rd late notice
|
Print Statement | | | 6/18/2019 | | DONE |
|
|
|
sent 2nd late notice
|
Print Statement | | | 4/19/2019 | | DONE |
|
|
|
sent 1st late notice
|
Print Statement | | | 12/20/2018 | | DONE |
|
|
|
|
Second Notice | | 11/17/2018 | 12/14/2018 | | DONE |
|
|
|
mailed 12-17
|
First Notice | | 10/14/2018 | 11/7/2018 | | DONE |
|
|
|
mailed 11-12
|
Permanent Occupancy | | | 10/4/2018 | | DONE |
|
|
|
|
BLD-Final | 9/28/2018 | 9/28/2018 | 9/28/2018 | P | PASS |
Jim Storey
|
|
|
Dave Phone #: 208-960- final ok pending plm
|
FIRE-Final Inspection | 9/26/2018 | 9/27/2018 | 9/27/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.
Dave Phone #: ###-####
|
BLD-Footing | 9/13/2018 | 9/14/2018 | 9/17/2018 | A | PASS |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
Print Occupancy Form | | | 8/23/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/23/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 8/1/2018 | 8/1/2018 | 8/21/2018 | | DONE |
Julie Romig
|
|
|
08/21 - 2nd Rev - 1st Rev Comp - Plan Mod - Naked Fins
|
Routing Off Site - STRUCTURAL | 8/15/2018 | | 8/21/2018 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 8/21/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
(changed back to issued status once plan mod fees are paid)
|
BLD-Framing/Rough-in | 8/14/2018 | 8/15/2018 | 8/15/2018 | A | PART |
Jim Storey
|
|
|
Dave-plan mod but isn''t part of the review Phone #: ###-#### ok pending ofhers
|
Routing - Design Review | 8/15/2018 | | 8/15/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLAN CHECK | 8/3/2018 | | 8/9/2018 | | PASS |
Julie Romig
|
|
|
Plan Mod 1 - Pending structural and design review approval.
|
Routing Off Site - STRUCTURAL | 8/3/2018 | | 8/9/2018 | | FAIL |
Julie Romig
|
|
|
Plan Mod 1 - Corrections required per ePlanReview
|
Routing - Design Review | 8/3/2018 | | 8/3/2018 | | FAIL |
Katelyn Menuge
|
|
|
Please submit elevations approved by Design Review and a maintenance plan if utilizing wood siding.
|
Plan resubmittals received | | | 8/1/2018 | | DONE |
|
|
|
modify the existing structural. openings in west wall are revised to work with existing structural columns
|
Issue PAID IN FULL permit | | | 7/25/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/25/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 5/31/2018 | 5/31/2018 | 7/24/2018 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 2nd Rev Comp - L3 Naked Fins
|
Routing - PLANNING | 5/31/2018 | | 7/24/2018 | | PASS |
Susan Riggs
|
|
|
No review required per Susan Riggs in ePlanReview
|
Routing - PLAN CHECK | 7/24/2018 | | 7/24/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/24/2018 | | DONE |
|
|
|
NEED - all met
GC
Rev Cert of Val
|
Routing - FIRE | 7/18/2018 | 7/18/2018 | 7/19/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 7/18/2018 | | 7/19/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - Design Review | 7/18/2018 | | 7/18/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Route to Impact Fee Review | 7/12/2018 | 7/15/2018 | 7/13/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 7/12/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 5/31/2018 | | 7/12/2018 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview
|
Routing - FIRE | 5/31/2018 | 5/31/2018 | 7/5/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing PW Environmental | 5/31/2018 | | 6/15/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing Off Site - STRUCTURAL | 5/31/2018 | | 6/8/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 5/31/2018 | | 6/7/2018 | | PASS |
Troy James
|
|
|
No mechanical work shown on plans. Kitchen appliances noted do not require hood. Restaurant to restaurant does not require any changes to mechanical ventilation design.
|
Routing - Design Review | 5/31/2018 | | 6/6/2018 | | FAIL |
Katelyn Menuge
|
|
|
Show bike racks meeting Zoning Code design and placement requirements.
Show that vision triangles will be kept clear. Fencing and posts within vision triangles are limited to 36 feet in height. Vision triangles at driveways are measured 10 feet back and 20 feet out from the back of sidewalk.
|
Routing - Erosion and Sediment | 5/31/2018 | | 6/1/2018 | | PASS |
Michael Zawacki
|
|
|
TI. Minor changes to exterior, no ESC permit required based on site plan submitted.
|
Routing - Addressing | 5/31/2018 | | 5/31/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/31/2018 | | 5/31/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 5/31/2018 | | 5/31/2018 | | PASS |
Bill VanDegrift
|
|
|
May require additional backflow protection on installed equipment as required by ISPC.
|
Intake Approval | | | 5/31/2018 | | PASS |
|
|
|
|
Intake Approval | | | 5/17/2018 | | FAIL |
Brian McGowan
|
|
|
Openings are being widened at the exterior wall. Engineering is required.
No CDHD Review letter was provided.
|
Intake Approval | | | 5/8/2018 | | FAIL |
Brian McGowan
|
|
|
520 Application not signed
CDHD review not provided.
Building is not identified on Key Plan.
Adding exterior patio will require Landscaping design.
Relocating doors, widening windows, modifying the exterior will require Structural Plans signed and stamped by an Idaho licensed engineer..
Mechanical Plans signed and stamped by an Idaho Licensed engineer are required.
Plumbing Plans signed and stamped by an Idaho licensed engineer are required.
|
Application received | | | 5/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 7 2018 11:50AM
|