BLD-Final | 12/7/2018 | 12/7/2018 | 12/7/2018 | P | PASS |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
DOC - Permit Finaled | 12/7/2018 | 12/7/2018 | 12/7/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 12/7/2018 | 12/7/2018 | 12/7/2018 | P | DONE |
Jim Storey
|
|
|
Dave Phone #: ###-#### 4.0
|
BLD-Final | 12/5/2018 | 12/6/2018 | 12/6/2018 | P | CANC |
Jim Storey
|
|
|
David Phone #: ###-####
|
Case Summary (BLD) | | | 12/6/2018 | | DONE |
|
|
|
|
BLD-Energy code compliance | 9/10/2018 | 9/10/2018 | 9/10/2018 | P | PASS |
Brandon Shaw
|
|
|
Dave Phone #: ###-####
|
BLD-Framing/Rough-in | 8/23/2018 | 8/24/2018 | 8/24/2018 | A | PART |
Jim Storey
|
|
|
Dave Phone #: ###-#### missing all interior headers and truss bracing thru out roof/ nail hangers
|
BLD-Wall Bracing | 8/8/2018 | 8/8/2018 | 8/9/2018 | P | PASS |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
BLD-Wall Bracing | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | FAIL |
Jim Storey
|
|
|
Dave Phone #: ###-#### wsp not per plan back of building// steel colm is wood with no post to beam cap.
|
BLD-Foundation | 7/9/2018 | 7/10/2018 | 7/10/2018 | A | PASS |
Jim Storey
|
|
|
As late as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
BLD-Footing | 7/6/2018 | 7/9/2018 | 7/9/2018 | A | PASS |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
BLD-Footing | 7/5/2018 | 7/6/2018 | 7/6/2018 | A | FAIL |
Jim Storey
|
|
|
Wes--prefers as early as possible, plans are in a bag upfront in the footing Phone #: ###-#### north set back to close
|
BLD-Footing | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | NR |
Dave Hannah
|
|
|
As late as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
OVERRIDE | | | 6/14/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 5/29/2018 | 5/29/2018 | 6/14/2018 | | DONE |
Brian McGowan
|
|
|
1st review complete - 6-11 sfd L1 ePlan
|
Issue PAID IN FULL permit | | | 6/14/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/14/2018 | | 6/14/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/14/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/14/2018 | | DONE |
|
|
|
|
1st review completed | | | 6/8/2018 | | FAIL |
Brian McGowan
|
|
|
Wall bracing needs to updated to 2015 IRC
|
Routing - PLAN CHECK | 5/29/2018 | | 6/8/2018 | | FAIL |
Brian McGowan
|
|
|
Wall bracing needs to updated to 2015 IRC
|
Route to Impact Fee Review | 5/29/2018 | 6/1/2018 | 5/30/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 5/29/2018 | | 5/30/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/29/2018 | | 5/29/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 5/29/2018 | | 5/29/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/29/2018 | | 5/29/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/29/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/29/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/29/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/23/2018 | | FAIL |
|
|
|
I noticed notice that the drawings show 2009 IRC codes and 2012 energy codes. We are now complying with the 2015 IRC and Energy codes so they will need to be changed. Also the parcel has a SFD on it right now so you will need a demo permit for that in order to received the credit for impact fees or you can include the valuation for the demo on this permit.
|
Application received | | | 5/9/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 9 2018 12:28PM
|