Permit Information
Permit NumberBLD18-01674
StatusFinaled
Name CHAMISA BUILDING CO INC
Site Address 3221 N 24TH WAY
Project NameSevier Remodel
Customer Number 
ePlanReviewYes
Description
WUI - HILLSIDE - Permit for a remodel, to include: replacement of the roof, siding, windows, rebuilding the existing sun room, adding a new 2nd level balcony w/ glass rail, enlarging a clerestory dormer, and adding an entry trellis. All work per plans, engineering, local codes & ordinances. Separate electrical permit required. **JAB** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/2/201811/5/201811/5/2018APASS
DetailsTony Young
Matt Phone #: ###-####
DOC - Permit Finaled11/5/201811/5/201811/5/2018PPASS
DetailsTony Young
c of c issued
BLD-Energy code compliance8/27/20188/27/20188/27/2018PPASS
DetailsTony Young
Jack Phone #: ###-####
BLD-Energy code compliance8/22/20188/23/20188/23/2018ACANC
DetailsBrandon Shaw
Matt Phone #: ###-####
BLD-Framing/Rough-in8/16/20188/17/20188/17/2018APASS
DetailsJim Sly
Matt Phone #: ###-####
BLD-Footing7/10/20187/11/20187/11/2018APASS
DetailsTony Young
Phone #: ###-####
PubWorks Subgrade Approval7/9/20187/9/20187/9/2018 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
BLD-Footing7/3/20187/5/20187/5/2018PPEND
DetailsTony Young
still need to verify soils approval
BLD-Footing7/2/20187/3/20187/3/2018PPEND
DetailsTony Young
Tim Phone #: ###-####,, still needing soils approval
BLD-Footing7/2/20187/2/20187/2/2018PPEND
DetailsTony Young
Tim Phone #: ###-####,, ok pending soils report
BLD-Footing6/29/20187/2/20187/2/2018ANR
DetailsTony Young
Tim Phone #: ###-####
BLD-Footing6/29/20186/29/20186/29/2018PPEND
DetailsTony Young
Tim Phone #: ###-####
BLD-Footing6/28/20186/29/20186/29/2018APEND
DetailsTony Young
Tim Phone #: ###-####
BLD-Foundation6/27/20186/28/20186/28/2018PNR
DetailsTony Young
Tim Phone #: ###-####,, need soils report
Issue PAID IN FULL permit  6/13/2018 DONE
Plan assigned to (JAB) Josh5/11/20185/11/20186/8/2018 PASS
DetailsJosh Bogle
1st done - Hillside remodel - lacking some structural & WUI details
Routing - PLAN CHECK6/8/2018 6/8/2018 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  6/8/2018 DONE
DetailsJosh Bogle
ESC yes - Energy yes
Permit Ready to Issue  6/8/2018 DONE
NEED
GC Form
RP
Routing Walk-In (BLD)5/31/20185/31/20185/31/2018PPASS
DetailsJosh Bogle
applicant came in for a conversation
Routing - PLAN CHECK5/24/2018 5/24/2018 FAIL
DetailsJosh Bogle
Routing - PLAN CHECK5/11/2018 5/14/2018 FAIL
DetailsJosh Bogle
Routing PW Grading-Hillside5/14/2018 5/14/2018 PASS
DetailsMelissa Jannusch


A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####


Subgrade only
Routing - PUBLIC WORKS5/14/2018 5/14/2018 PASS
DetailsMorgan Webb
1st review completed  5/14/2018 FAIL
DetailsJosh Bogle
Application received  5/11/2018 DONE
Application submitted via PDS Online on May 11 2018 2:33PM
Plans ACCEPTED BY PLAN TECH  5/11/2018 DONE
Intake Approval  5/11/2018 PASS
Recd Pcfee & Taken To Pln CK  5/11/2018 DONE
Routing - PLANNING5/11/2018 5/11/2018 PASS
DetailsColleen T Carroll