BLD-Final | 9/13/2018 | 9/14/2018 | 9/17/2018 | P | PASS |
Dave Hannah
|
|
|
Jason Phone #: ###-####
|
FIRE-Final Inspection | 9/17/2018 | 9/17/2018 | 9/17/2018 | A | PASS |
Adele J Schaffeld-Griffin
|
|
|
Building verified rear door installed
|
DOC - Permit Finaled | | | 9/17/2018 | | DONE |
Dave Hannah
|
|
|
as per Dave H. final insp passed and ok to doc final
|
BLD-Final | 9/11/2018 | 9/12/2018 | 9/12/2018 | P | PEND |
Dave Hannah
|
|
|
Jason Phone #: ###-#### ok for temp occ need perm back door
|
FIRE-Final Inspection | 9/11/2018 | 9/12/2018 | 9/12/2018 | A | PART |
Jim Page
|
|
|
okay for temp, exit door needs to be installed. Jason Phone #: ###-####
|
FIRE-Conference | 8/10/2018 | 8/13/2018 | 8/13/2018 | P | DONE |
Jim Page
|
|
|
Fire conference complete.
Paul Phone #: ###-####
|
FIRE-Conference | 8/7/2018 | 8/7/2018 | 8/7/2018 | A | DONE |
Jim Page
|
|
|
During the rough-in inspection for newly installed overhead fire sprinkler piping it was noticed that the premise still has o-ring style heads throughout the building that need to be replaced (O-ring style heads must be replaced due to o-ring style sprinkler heads failing to operate correctly). O-ring style heads must be replaced before fire sprinkler final inspection and fire life safety inspection. After discussion with Ron Johnson with Boise Fire, final inspections will be failed on fire sprinkler and life safety if o-ring style heads are not replaced.
|
BLD-Framing/Rough-in | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | PASS |
Dave Hannah
|
|
|
Paul Phone #: ###-#### restrooms ok
|
Issue PAID IN FULL permit | | | 6/1/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/1/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 5/17/2018 | 5/17/2018 | 5/29/2018 | | PASS |
Javier Guzman
|
|
|
5/23 L1 First Presbyterian Church ePlan
|
Routing - PLAN CHECK | 5/17/2018 | | 5/29/2018 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 5/29/2018 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/29/2018 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE
|
Routing - FIRE | 5/17/2018 | 5/17/2018 | 5/18/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Intake Approval | | | 5/17/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 5/17/2018 | | 5/17/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/17/2018 | | 5/17/2018 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 5/14/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 14 2018 11:39AM
|