Permit Information
Permit NumberBLD18-01688
StatusFinaled
Name FIRST PRESBYTERIAN CHRUCH
Site Address 950 W STATE ST
Project NameFirst Presbyterian Church
Customer Number 
ePlanReviewYes
Description
(FIRST PRESBYTERIAN CHURCH – LOBBY AND RESTROOM REMODEL) Fire sprinklers used for building area increase. Permit is to remodel the existing lobby and restroom areas within the existing church building main level. Approval is contingent upon adhering to the approved plans on file. Work to include: removal of select interior nonbearing walls, removal of select door/door frames, removal of select suspended acoustic ceiling, removal of select plumbing fixtures, removal of select millwork, construction of interior non-bearing walls to create accessible restrooms and new accessible restroom accessories, select new door/door frames, select new plumbing fixtures, select new gypsum ceiling, select new light fixtures, select new millwork, a new interior lobby metal roof awning, electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the current IBC. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/13/20189/14/20189/17/2018PPASS
DetailsDave Hannah
Jason Phone #: ###-####
FIRE-Final Inspection9/17/20189/17/20189/17/2018APASS
DetailsAdele J Schaffeld-Griffin
Building verified rear door installed
DOC - Permit Finaled  9/17/2018 DONE
DetailsDave Hannah
as per Dave H. final insp passed and ok to doc final
BLD-Final9/11/20189/12/20189/12/2018PPEND
DetailsDave Hannah
Jason Phone #: ###-#### ok for temp occ need perm back door
FIRE-Final Inspection9/11/20189/12/20189/12/2018APART
DetailsJim Page
okay for temp, exit door needs to be installed. Jason Phone #: ###-####
FIRE-Conference8/10/20188/13/20188/13/2018PDONE
DetailsJim Page
Fire conference complete.

Paul Phone #: ###-####
FIRE-Conference8/7/20188/7/20188/7/2018ADONE
DetailsJim Page
During the rough-in inspection for newly installed overhead fire sprinkler piping it was noticed that the premise still has o-ring style heads throughout the building that need to be replaced (O-ring style heads must be replaced due to o-ring style sprinkler heads failing to operate correctly). O-ring style heads must be replaced before fire sprinkler final inspection and fire life safety inspection. After discussion with Ron Johnson with Boise Fire, final inspections will be failed on fire sprinkler and life safety if o-ring style heads are not replaced.
BLD-Framing/Rough-in8/3/20188/3/20188/3/2018PPASS
DetailsDave Hannah
Paul Phone #: ###-#### restrooms ok
Issue PAID IN FULL permit  6/1/2018 DONE
Inspection Record Card- Bld  6/1/2018 DONE
Plan assigned to (JG)5/17/20185/17/20185/29/2018 PASS
DetailsJavier Guzman
5/23 L1 First Presbyterian Church ePlan
Routing - PLAN CHECK5/17/2018 5/29/2018 PASS
DetailsJavier Guzman
1st review completed  5/29/2018 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  5/29/2018 DONE
Permit Ready to Issue  5/29/2018 DONE
NEED
GC FORM
REVISED VALUE
Routing - FIRE5/17/20185/17/20185/18/2018 PASS
DetailsErika Akin
Attached comments to case
Intake Approval  5/17/2018 PASS
DetailsJavier Guzman
Routing - Addressing5/17/2018 5/17/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS5/17/2018 5/17/2018 PASS
DetailsRachael Beierle
Application received  5/14/2018 DONE
Application submitted via PDS Online on May 14 2018 11:39AM