Information based on query as of Tuesday, June 25, 2024.
Permit Information
Permit NumberBLD18-01689
StatusFinaled
Name TIM AUSTIN CONSTRUCTION
Site Address 3820 N ERICK LN
Project Name 
Customer Number 
ePlanReviewNo
Description
Permit for the remodel to construct a garage addition. Work to include new foundation and footings, walls, engineered truss system and electrical. All work per plans, notes & local codes. Separate electrical permit required. ***RDP***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/9/20188/9/20188/9/2018PPASS
DetailsJim Sly
Please call ahead for access // Tim Phone #: ###-####
DOC - Permit Finaled8/9/20188/9/20188/9/2018PPASS
DetailsJim Sly
BLD-Framing/Rough-in7/10/20187/11/20187/11/2018APASS
DetailsJim Sly
Tim Phone #: ###-####
BLD-Wall Bracing6/21/20186/21/20186/21/2018PPASS
DetailsJim Sly
Shane Phone #: ###-####
BLD-Wall Bracing6/14/20186/15/20186/15/2018ACANC
DetailsJim Sly
Shane Phone #: ###-####
BLD-Foundation5/31/20186/1/20186/1/2018PPART
DetailsJim Sly
Dave-would like early afternoon Phone #: ###-####
Wall appears OK.
BLD-Footing5/30/20185/31/20185/31/2018APART
DetailsJim Sly
Dave Phone #: ###-####
No string lines pulled. Unable to determine property lines. Concrete Contactor notified......pour at own risk.
OVERRIDE  5/22/2018  
Telephone call  5/22/2018 DONE
Let voicemail for Chris to inform him the permit is ready what fees are due. If he as the homeowner if putting the permit in his name we will need a 302, or if Tim Austin Construction is going to have the permit in their name. (see application)
Issue PAID IN FULL permit  5/22/2018 DONE
Routing - Erosion and Sediment5/22/2018 5/22/2018 PASS
DetailsAndy J. Long
ESC general permit issued per scope of project. Parcel zoned hillside but no work occuring on or near sloped portion of lot. Homeowner RP
Permit Ready to Issue  5/22/2018 DONE
Need
if parcel owner is GC will need a 302.
Plan assigned to (RDP)5/14/20185/14/20185/21/2018 DONE
DetailsRob Patrick
5/14...Take-in at front counter routed to Hillside. Garage addition.
Routing - PLAN CHECK5/21/2018 5/21/2018 PASS
DetailsRob Patrick
Routing - PUBLIC WORKS5/14/2018 5/21/2018 PASS
DetailsMorgan Webb
Routing PW Grading-Hillside5/15/2018 5/21/2018 PASS
DetailsMelissa Jannusch
Subgrade inspection only
1st review completed  5/21/2018 DONE
DetailsRob Patrick
Inspection Record Card- Bld  5/21/2018 DONE
DetailsRob Patrick
Case Summary (BLD)  5/21/2018 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  5/21/2018 DONE
DetailsRob Patrick
Routing - Erosion and Sediment5/21/2018 5/21/2018 FAIL
DetailsMichael Zawacki
No ESC or waiver request provided.
Routing - Addressing5/15/2018 5/15/2018 PASS
DetailsLaura Hunter
Routing Walk-In (Zoning)5/14/20185/14/20185/14/2018APASS
DetailsColleen T Carroll
Routing Walk-In (BLD)5/14/20185/14/20185/14/2018PCANC
DetailsRob Patrick
Took in as level 2.
Application received 5/14/2018