BLD-Final | 2/21/2019 | 2/22/2019 | 2/22/2019 | A | DONE |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
DOC - Permit Finaled | 2/22/2019 | 2/22/2019 | 2/22/2019 | P | PASS |
Tony Young
|
|
|
|
Zoning Approval | 1/29/2019 | 1/29/2019 | 1/31/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH18-00148. Historic inspection complete.
|
BLD-Final | 10/15/2018 | 10/26/2018 | 10/26/2018 | P | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
BLD-Final | 10/12/2018 | 10/15/2018 | 10/15/2018 | A | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####,, needs historical and hand rail
|
BLD-Final | 10/11/2018 | 10/12/2018 | 10/12/2018 | A | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####, needs zoning and hand rail off the deck
|
BLD-Final | 10/9/2018 | 10/11/2018 | 10/11/2018 | A | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####,, needs historical
|
BLD-Energy code compliance | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
BLD-Framing/Rough-in | 8/3/2018 | 8/6/2018 | 8/6/2018 | A | PART |
Brandon Shaw
|
|
|
Need to foam seal OK to insulate
|
BLD-Foundation | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PASS |
Jim Storey
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 6/8/2018 | 6/11/2018 | 6/11/2018 | A | PASS |
Brandon Shaw
|
|
|
Ryan Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/8/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/24/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 5/15/2018 | 5/15/2018 | 5/24/2018 | | PASS |
Josh Bogle
|
|
|
1st done - paper - addition/remodel, missing details
|
Telephone call | | | 5/24/2018 | | DONE |
|
|
|
Spoke with Ryan to inform him the permit is ready, what fees are due and who will be the RP
|
Routing - PLAN CHECK | 5/24/2018 | | 5/24/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 5/24/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2018 | | DONE |
Josh Bogle
|
|
|
$5 min. copy fee
|
Permit Ready to Issue | | | 5/24/2018 | | DONE |
|
|
|
need
RP
|
Routing - PLAN CHECK | 5/22/2018 | | 5/23/2018 | | FAIL |
Josh Bogle
|
|
|
see e-mail 5/23
|
Plan resubmittals received | | | 5/22/2018 | | DONE |
|
|
|
3 copies of A0.0, A1.0 and A2, stamped and taken to plan reviewer.
|
Routing - PLAN CHECK | | | 5/16/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - Design Review | 5/15/2018 | | 5/16/2018 | | PASS |
KayCee Babb
|
|
|
Minor door and window changes updated in Historic application
|
1st review completed | | | 5/16/2018 | | FAIL |
Josh Bogle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/15/2018 | | DONE |
|
|
|
taken in for level 2 review. Customer did not want to do over counter.
|
Application received | | 5/15/2018 | | | |
|
|
|
|