Print Statement | | | 4/19/2019 | | DONE |
|
|
|
sent 1st late notice
|
Print Statement | | | 1/9/2019 | | DONE |
|
|
|
|
Meeting | | | 1/9/2019 | | DONE |
|
|
|
sent kay with horizon retail construction inc email checking on the over 50,000 value difference for electrical
|
First Notice | | 11/30/2018 | 12/13/2018 | | DONE |
|
|
|
mailed 12-14
|
PubWorks Occupancy Approval | 11/20/2018 | 11/20/2018 | 11/20/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 11/20/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/19/2018 | | DONE |
|
|
|
|
BLD-Final | 11/13/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker OK for Perm Occ.
|
FIRE-Final Inspection | 11/13/2018 | 11/15/2018 | 11/15/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractro agreed to provide ADA hardware on the pocket door and provide sticker at the main exit door with the keyed egress hardware.
Mark Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker
|
BLD-Ceiling Grid Inspection | 11/6/2018 | 11/8/2018 | 11/8/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mark Becker Inspection cancelled from web by: Mark Becker
|
BLD-Ceiling Grid Inspection | 10/31/2018 | 10/31/2018 | 10/31/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker. Draft stop ok. Needs MEP's sign off prior to installing tile and another grid inspction.
|
BLD-Wall cover | 10/12/2018 | 10/12/2018 | 10/12/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker. Draft stop has been installled, but has several gaps. Will verify completion at grid inspection.
|
BLD-Framing/Rough-in | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker. Interior steel studframed walls ok. No grid at this time. Pending electrical rough in inspection.
|
BLD-Framing/Rough-in | 9/18/2018 | 9/19/2018 | 9/19/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker
|
BLD-Conference | 9/19/2018 | 9/19/2018 | 9/19/2018 | A | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker
|
BLD-Framing/Rough-in | 9/18/2018 | 9/18/2018 | 9/18/2018 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mark Becker Inspection cancelled from web by: Mark Becker
|
Print Occupancy Form | | | 9/11/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/11/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 6/29/2018 | 6/29/2018 | 8/22/2018 | | DONE |
Julie Romig
|
|
|
08/27 - 2nd Rev - 1st Rev Comp - L3 Aspen Dental
|
Routing - PLAN CHECK | 8/22/2018 | | 8/22/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - PLUMBING | 8/22/2018 | | 8/22/2018 | | PASS |
Dan Ediger
|
|
|
RP for model trimmer
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2018 | | DONE |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 8/22/2018 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED VALUE
|
Route to Impact Fee Review | 8/9/2018 | 8/12/2018 | 8/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 6/29/2018 | | 8/9/2018 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 8/9/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 6/29/2018 | 6/29/2018 | 7/26/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLUMBING | 6/29/2018 | | 7/5/2018 | | PASS |
Bill VanDegrift
|
|
|
See red lines.
|
Routing - MECHANICAL | 6/29/2018 | | 7/3/2018 | | PASS |
Troy James
|
|
|
|
Routing PW Environmental | 6/29/2018 | | 7/3/2018 | | PASS |
Terry Alber
|
|
|
If Solmetex HG5 amalgam separator is not included with RAMVAC, then a City of Boise approved amalgam separator shall be installed (https://publicworks.cityofboise.org/services/sewer/pretreatment-program/approvedamalgamseparators/). Complete and submit an application for Coverage under the Dental Best Management Practice Program (https://publicworks.cityofboise.org/media/266489/dental-bmp-application.pdf) or contact talber@cityofboise.org for more information.
|
Routing PW Solid Waste | 6/29/2018 | | 7/3/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PUBLIC WORKS | 6/29/2018 | | 7/2/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 6/29/2018 | | 6/29/2018 | | PASS |
David Moser
|
|
|
SEE DRH18-00057
|
Routing - Addressing | 6/29/2018 | | 6/29/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Drainage | 6/29/2018 | | 6/29/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 6/29/2018 | | 6/29/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 6/29/2018 | | 6/29/2018 | | PASS |
DeAnn Brown
|
|
|
Sewer work/connection approved per BLD18-01380.
|
Intake Approval | | | 6/26/2018 | | PASS |
|
|
|
|
Intake Approval | | | 5/29/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Missing 502 checklist form completed and signed.
|
Application received | | | 5/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 16 2018 10:32AM
|