Print Statement | | | 7/26/2019 | | DONE |
|
|
|
|
Print Statement | | | 7/23/2019 | | DONE |
|
|
|
|
Print Statement | | | 7/23/2019 | | DONE |
|
|
|
|
Third Notice | | 6/12/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11 with first follow up
|
First Follow up | | | 7/10/2019 | | DONE |
|
|
|
|
Third Notice | | 5/11/2019 | 6/7/2019 | | DONE |
|
|
|
mailed 6-10
|
Third Notice | | 4/13/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
Second Notice | | 3/21/2019 | 4/8/2019 | | DONE |
|
|
|
mailed 4-11-19
|
First Notice | | 3/2/2019 | 3/11/2019 | | DONE |
|
|
|
mailed 3-12-19
|
Print Occupancy Form | | | 2/20/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/20/2019 | | DONE |
|
|
|
|
BLD-Final | 2/13/2019 | 2/14/2019 | 2/14/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Steen
|
FIRE-Final Inspection | 2/12/2019 | 2/13/2019 | 2/13/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by Mark Steen
|
BLD-Framing/Rough-in | 11/15/2018 | 11/15/2018 | 11/16/2018 | P | PASS |
Dave Hannah
|
|
|
Per Brandon, a courtesy inspection should also occur for Dave Hannah. Phone #: ###-#### Inspection requested via web by Mark Steen
|
BLD-Framing/Rough-in | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PART |
Brandon Shaw
|
|
|
Pending trades rough-in...
|
BLD-Foundation | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Brandon Shaw
|
|
|
Small canopy in alley.
|
BLD-Framing/Rough-in | 9/25/2018 | 9/26/2018 | 9/26/2018 | A | PASS |
Dave Hannah
|
|
|
Metal stud framing at restrooms and shower. Also note, we are preparing to retrofit existing wood framing at mezzanine deck. A quick familiarization of existing conditions may help us all as we upgrade beams and hardware connections. Thanks Phone #: ###-#### Inspection requested via web by Mark Steen ok to cover bath rooms
|
Issue PAID IN FULL permit | | | 7/24/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/24/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/18/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 5/24/2018 | 5/24/2018 | 7/18/2018 | | DONE |
Julie Romig
|
|
|
07/20 - 2nd Rev - 1st Rev Comp - L3 Prestige Water Sports
|
Routing - PLAN CHECK | 7/16/2018 | | 7/18/2018 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 7/16/2018 | | 7/18/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/18/2018 | | DONE |
Christina Prado
|
|
|
Need - All met 7/23/18
GC
Rev Cert of Val
RP
|
Route to Impact Fee Review | 7/9/2018 | 7/12/2018 | 7/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 5/24/2018 | | 7/9/2018 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 7/9/2018 | | FAIL |
Julie Romig
|
|
|
|
Plan Reviewer's activity | | | 6/22/2018 | | DONE |
Julie Romig
|
|
|
Emailed Structural corrections to architect, notified that building review is 2 weeks behind timeframe
|
Routing - FIRE | 5/24/2018 | 5/24/2018 | 6/21/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 5/24/2018 | | 6/8/2018 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview
|
Routing - MECHANICAL | 5/24/2018 | | 5/29/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - Erosion and Sediment | 5/24/2018 | | 5/25/2018 | | PASS |
Michael Zawacki
|
|
|
Waiver request emailed and approved
|
Routing - PLUMBING | 5/24/2018 | | 5/24/2018 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing - PLANNING | 5/24/2018 | | 5/24/2018 | | PASS |
David Moser
|
|
|
see CZC18-00057
|
Routing - Addressing | 5/24/2018 | | 5/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/24/2018 | | 5/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 5/24/2018 | | 5/24/2018 | | PASS |
KayCee Babb
|
|
|
Proposal meets all plans and conditions of CZC18-00057.
|
Intake Approval | | | 5/24/2018 | | PASS |
|
|
|
|
Application received | | | 5/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 16 2018 11:41AM
|