Permit Information
Permit NumberBLD18-01744
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 6177 E HOOTOWL DR
Project NameShoshone MC HN 85-1
Customer Number 
ePlanReviewYes
Description
W.U.I. Zone "A". Class A roof Required. Permit for the construction of a new 4,110 sq. ft., two story (first story 2,514 sq. ft., second story 1,596 sq. ft.) single family dwelling with 6 bedrooms, 4 bathrooms, approximately 610 sq. ft. of covered patio/porch and a 1,076 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. SP-01 zoning and setbacks per planning. ***RDP***

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/15/20191/16/20191/16/2019APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
DOC - Permit Finaled1/16/20191/16/20191/16/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results1/16/20191/16/20191/16/2019ADONE
DetailsBrandon Shaw
ACH50- 3.40
PubWorks Occupancy Approval1/9/20191/9/20191/9/2019 DONE
DetailsMelissa Jannusch
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.

BLD-Energy code compliance10/11/201810/12/201810/12/2018APASS
DetailsBrandon Shaw
See Documents for Special inspection for installation of anchor bolts...
BLD-Other10/2/201810/3/201810/3/2018APASS
DetailsBrandon Shaw
Rollo- sofit Phone #: ###-####
BLD-Framing/Rough-in10/2/201810/2/201810/2/2018PPART
DetailsJim Storey
Rollo Phone #: ###-#### pending enginering fix as specifed by engineer. ok to insulate.
BLD-Framing/Rough-in9/25/20189/26/20189/26/2018AFAIL
DetailsBrandon Shaw
Anchor bolts are all bent at the washer or in compression from walls being placed on bolt head, with cracking in foundation at each bolt.
Need Engineering approval...

No other framing issues...
BLD-Wall Bracing8/28/20188/28/20188/28/2018PPART
DetailsBrandon Shaw
Work in progress...
Straps and hold downs to be in place by framing rough
BLD-Foundation7/2/20187/2/20187/2/2018PPASS
DetailsBrandon Shaw
Work in progress
BLD-Footing6/27/20186/28/20186/28/2018APASS
DetailsBrandon Shaw
Work in progress
PubWorks Subgrade Approval6/28/20186/28/20186/28/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
BLD-Footing6/27/20186/27/20186/27/2018PCANC
DetailsBrandon Shaw
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell Inspection cancelled via mobile web on Wednesday, June 27, 2018.
Issue PAID IN FULL permit  6/18/2018 DONE
Inspection Record Card- Bld  6/18/2018 DONE
OVERRIDE  5/30/2018  
Plan assigned to (RDP)5/17/20185/17/20185/30/2018 DONE
Details
6/5 sfd L2 ePlan
Routing - PLAN CHECK5/17/2018 5/30/2018 PASS
DetailsRob Patrick
1st review completed  5/30/2018 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  5/30/2018 DONE
DetailsRob Patrick
Permit Ready to Issue  5/30/2018 DONE
Routing PW Grading-Hillside5/17/2018 5/23/2018 PASS
DetailsMelissa Jannusch

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

Routing - Erosion and Sediment5/17/2018 5/22/2018 PASS
DetailsMichael Zawacki
Harris Ranch North, foothills sub. Site prep inspection required.
Route to Impact Fee Review5/17/20185/20/20185/18/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - FIRE5/17/20185/17/20185/17/2018 PASS
DetailsTim Frost
Routing - MECHANICAL5/17/2018 5/17/2018 PASS
DetailsChad Schwendiman
Routing - PLANNING5/17/2018 5/17/2018 PASS
DetailsSue Cummings
Routing - Addressing5/17/2018 5/17/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS5/17/2018 5/17/2018 PASS
DetailsMorgan Webb
Intake Approval  5/17/2018 FAIL
Grading plan needs to be landscape.
Plans ACCEPTED BY PLAN TECH  5/17/2018 DONE
Recd Pcfee & Taken To Pln CK  5/17/2018 DONE
Intake Approval  5/17/2018 PASS
Application received  5/16/2018 DONE
Application submitted via PDS Online on May 16 2018 3:23PM