First Notice | | 12/6/2018 | 12/28/2018 | | DONE |
|
|
|
emailed in 12-27-18
|
Print Statement | | | 12/28/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 11/26/2018 | | DONE |
|
|
|
|
BLD-Final | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | PASS |
Mike Jordan
|
|
|
Larin Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 11/20/2018 | 11/20/2018 | 11/20/2018 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final life fire safety inspection complete.
|
FIRE-Final Inspection | 11/19/2018 | 11/19/2018 | 11/19/2018 | P | FAIL |
Jim Page
|
|
|
Fire sprinkler heads by island/sink in breakroom ltchen area are less tha 6 feet abart, a minimum of 6 feet betwwen heads is required by code. Escutcheons need to be installed on the heads in the entry way to include cover of piping and holes for the fire sprinkler heads.
Larren Phone #: ###-####
|
FIRE-Final Inspection | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | NR |
Jim Page
|
|
|
Tenant space is not ready for life fire safety inspection.
Lauren Phone #: ###-####
|
Print Occupancy Form | | | 9/20/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Dave Hannah
|
|
|
Lauren Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/3/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/3/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 5/24/2018 | 5/24/2018 | 7/19/2018 | | DONE |
Julie Romig
|
|
|
07/23 - 2nd Rev - 1st Rev Comp - L2 Kittelson & Associates, Inc.
|
Routing - PLAN CHECK | 7/17/2018 | | 7/19/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/19/2018 | | DONE |
|
|
|
ALL MET
NEED
GC FORM
REVISED VALUE
|
Route to Impact Fee Review | 6/6/2018 | 6/9/2018 | 6/7/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 6/6/2018 | 6/6/2018 | 6/6/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 6/6/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 5/24/2018 | | 6/6/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 5/24/2018 | | 5/29/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLUMBING | 5/24/2018 | | 5/25/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 5/24/2018 | | 5/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/24/2018 | | 5/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 5/24/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 5/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 17 2018 9:01AM
|