Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD18-01755
StatusFinaled
Name PROCRAFT CONSTRUCTION LLC
Site Address 3635 S WEATHERED AVE
Project NameWeartherwood addition
Customer Number 
ePlanReviewYes
Description
Permit for a 518sq', two-level, addition, that includes: adding a main level bedroom, adding a 2nd level loft that is open to below, and remodeling to add a shower to an existing half-bath.. All work per plans, engineering, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/5/201811/6/201811/6/2018PPASS
DetailsJim Storey
Call before heading to site Phone #: ###-#### Inspection requested via web by Curtis Bodenbender
DOC - Permit Finaled11/6/201811/6/201811/6/2018PPASS
DetailsJim Storey
BLD-Wall cover9/12/20189/13/20189/13/2018APASS
DetailsDave Hannah
Phone #: 2084120436 >> Inspection requested via mobile web by Curtis
BLD-Energy code compliance9/3/20189/4/20189/4/2018APASS
DetailsJim Storey
Phone #: 2084120436 >> Inspection requested via mobile web by Curtis
BLD-Energy code compliance8/28/20188/29/20188/29/2018PPART
DetailsJim Storey
Phone #: 208410436 >> Inspection requested via mobile web by Curtis air seal only
BLD-Framing/Rough-in8/28/20188/29/20188/29/2018PPASS
DetailsJim Storey
Phone #: 208410436 >> Inspection requested via mobile web by Curtis
BLD-Wall Bracing8/23/20188/24/20188/24/2018ANR
DetailsJim Storey
Needing a sheer wall inspection. Phone #: ###-#### Inspection requested via web by Curtis Bodenbender
BLD-Foundation7/17/20187/17/20187/17/2018PPASS
DetailsJim Storey
Concrete at 2pm- Brandon Phone #: ###-#### mono placement ft and wall ok rebar ok
Issue PAID IN FULL permit  7/9/2018 DONE
(F) Reprint permit  7/9/2018 DONE
OVERRIDE  7/5/2018  
Plan assigned to (JAB) Josh5/23/20185/23/20187/5/2018 PASS
DetailsJosh Bogle
1st done - addition, lacking several details
Routing - PLAN CHECK7/5/2018 7/5/2018 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  7/5/2018 DONE
DetailsJosh Bogle
ESC yes - Energy Yes - 2hrs (five Plan Checks total)
Telephone call  7/5/2018 DONE
Left voicemail and emailed Curtis to confirm the acres disturbed is correct and if not to let us know what the correct amount is. Gave Rita's email incase the acres disturbed is incorrect.
Permit Ready to Issue  7/5/2018 DONE
Need
RP

(see telephone call activity)
Routing - PLAN CHECK6/29/2018 6/29/2018 FAIL
DetailsJosh Bogle
footings are based on 2,000psf
Routing - PLAN CHECK6/22/2018 6/22/2018 FAIL
DetailsJosh Bogle
Routing Walk-In (BLD)6/7/20186/7/20186/7/2018PFAIL
DetailsJosh Bogle
Routing - PLAN CHECK6/7/2018 6/7/2018 FAIL
DetailsJosh Bogle
Routing - PLAN CHECK5/23/2018 5/30/2018 FAIL
DetailsJosh Bogle
lacking several details
1st review completed  5/30/2018 DONE
DetailsJosh Bogle
Routing - PLANNING5/23/2018 5/24/2018 PASS
DetailsSue Cummings
Plans ACCEPTED BY PLAN TECH  5/23/2018 DONE
Intake Approval  5/23/2018 PASS
Recd Pcfee & Taken To Pln CK  5/23/2018 DONE
Intake Approval  5/22/2018 FAIL
Need to provide all structural details (framing, sheathing, etc.) and stair section. See checklist items
Intake Approval  5/21/2018 FAIL
1.Please upload plans in the correct orientation (Landscape vs. Horizontal)
2. On Rear Elevations, Front Elevations and Elevations B2.0, can't read the details.
Application received  5/17/2018 DONE
Application submitted via PDS Online on May 17 2018 2:59PM