First Notice | | 7/24/2020 | 8/10/2020 | | DONE |
|
|
|
mailed 8-14-2020
|
Print Occupancy Form | | | 7/14/2020 | | DONE |
|
|
|
|
Permanent Occupancy | | | 7/14/2020 | | DONE |
|
|
|
|
BLD-Final | 10/23/2019 | 10/23/2019 | 10/23/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
CHANGE STATUS TO (ISS) | | | 5/29/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/29/2019 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 4/8/2019 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Called Architect Left message for Chad either applicant or contractor needs to pay for permit.
|
Plan assigned to (CJW) | 2/28/2019 | 2/28/2019 | 3/4/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod - St. Al's (plan intake approved)
|
Routing - PLAN CHECK | 3/1/2019 | | 3/4/2019 | | PASS |
Carl Westfall
|
|
|
IBC plan review approved
|
Plan Reviewer's activity | | | 3/4/2019 | | PASS |
|
|
|
Plan mod approved
|
Permit Ready to Issue | | | 3/4/2019 | | DONE |
|
|
|
PLAN MOD
|
Routing - PLAN CHECK | 2/28/2019 | | 3/1/2019 | | PASS |
Carl Westfall
|
|
|
Plan intake review approved
|
Plan Modification Accepted | | | 2/28/2019 | | DONE |
|
|
|
Addition of wall and door to separate waiting area from clinic space. Eplan work flow started.
(willl need revised value per plan mod app states it will affect value)
|
BLD-Final | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | PART |
Mike Jordan
|
|
|
As early as possible - Please call Ami. Phone #: ###-#### Inspection requested via web by Ami Ostrow. OK for temp occ. Wating for new doors in the 2hr. exit passageway.
|
BLD-Conference | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | DONE |
Mike Jordan
|
|
|
Call Darius, please. Phone #: ###-#### Inspection requested via web by Ami Ostrow
|
BLD-Conference | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | DEFR |
Jim Storey
|
|
|
Call Darius, please. Phone #: ###-#### Inspection requested via web by Ami Ostrow out of time
|
BLD-Conference | 1/23/2019 | 1/23/2019 | 1/23/2019 | P | DONE |
Mike Jordan
|
|
|
Please call Darius. Phone #: ###-#### Inspection requested via web by Ami Ostrow
|
FIRE-Final Inspection | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Ceiling Grid Inspection | 1/10/2019 | 1/10/2019 | 1/10/2019 | A | PASS |
Mike Jordan
|
|
|
As early as possible, please. Call Darius when on site. Thank you! Phone #: ###-#### Inspection requested via web by Ami Ostrow
|
BLD-Final | 1/7/2019 | 1/8/2019 | 1/8/2019 | P | PART |
Mike Jordan
|
|
|
Partial for conference room. Please call Darius Phone #: ###-#### Inspection requested via web by Ami Ostrow. Conferance room only ok to occupy.
|
FIRE-Final Inspection | 1/7/2019 | 1/8/2019 | 1/8/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety for Conference Room only is passed.
Partial for conference room. Please call Darius Phone #: ###-#### Inspection requested via web by Ami Ostrow
|
BLD-Ceiling Grid Inspection | 1/2/2019 | 1/2/2019 | 1/2/2019 | A | PASS |
Mike Jordan
|
|
|
Early if possible. Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Framing/Rough-in | 12/13/2018 | 12/14/2018 | 12/13/2018 | A | PASS |
Mike Jordan
|
|
|
Please come as early as possible - call Darius. Phone #: ###-#### Inspection requested via web by Ami Ostrow
|
BLD-Ceiling Grid Inspection | 12/4/2018 | 12/5/2018 | 12/5/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton. Storage room hardlid and mag room.
|
BLD-Ceiling Grid Inspection | 11/30/2018 | 12/3/2018 | 11/30/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Darius Saxton Inspection cancelled from web by: Darius Saxton
|
FIRE-Conference | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | DONE |
Troy Cobbley
|
|
|
We spoke about doing phase sign offs for this area of work. Call Darius when on site, please Phone #: ###-#### Inspection requested via web by Ami Ostrow
|
BLD-Framing/Rough-in | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Mike Jordan
|
|
|
Please call Darius when you get to the hospital. Phone #: ###-#### Inspection requested via web by Ami Tracy
|
BLD-Framing/Rough-in | 10/31/2018 | 10/31/2018 | 10/31/2018 | P | PASS |
Mike Jordan
|
|
|
Partial to cover - please call Darius. Phone #: ###-#### Inspection requested via web by Ami Tracy
|
BLD-Conference | 10/5/2018 | 10/8/2018 | 10/8/2018 | A | PART |
Mike Jordan
|
|
|
Call Darius, please. Phone #: ###-#### Inspection requested via web by Ami Tracy. Interior steel stud framed wall for New MRI room. Ok to one side only for install of shielding.
|
Issue PAID IN FULL permit | | | 8/21/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/21/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/8/2018 | | DONE |
|
|
|
Need - all met
GC Form
Revised Cert of Value
|
Plan assigned to (CJW) | 6/16/2018 | 6/16/2018 | 8/7/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) 07/03/18 (L3 - 15 days) (ePlan - 43 sheets) SARMC MRI
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/2/2018 | | 8/7/2018 | | PASS |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - PLUMBING | 8/2/2018 | | 8/7/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Design Review | 8/2/2018 | | 8/3/2018 | | PASS |
Andrea Tuning
|
|
|
|
Plan resubmittals received | | | 8/2/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/2/2018 | | 8/2/2018 | | PASS |
Carl Westfall
|
|
|
Pending approval by Structural
|
Route to Impact Fee Review | 7/21/2018 | 7/24/2018 | 7/23/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 6/16/2018 | | 7/21/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
1st review completed | | | 7/21/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 7/21/2018 | | DONE |
|
|
|
|
Routing - FIRE | 6/16/2018 | 6/16/2018 | 7/13/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 6/16/2018 | | 6/26/2018 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - MECHANICAL | 6/16/2018 | | 6/25/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing PW Environmental | 6/18/2018 | | 6/19/2018 | | PASS |
Terry Alber
|
|
|
No issues.
|
Routing - PLUMBING | 6/16/2018 | | 6/18/2018 | | FAIL |
Bill VanDegrift
|
|
|
H-1 and H-2 both require RPBP's and need to show location of drains and point of drain connection to waste.
|
Routing - Addressing | 6/16/2018 | | 6/18/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/16/2018 | | 6/18/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 6/16/2018 | | 6/18/2018 | | FAIL |
Andrea Tuning
|
|
|
Requires Design Review approval prior to a building permit.
|
Intake Approval | | | 6/13/2018 | | PASS |
Carl Westfall
|
|
|
SARMC MRI L-3
|
Plan Reviewer's activity | | | 6/11/2018 | | PASS |
Julie Romig
|
|
|
Plan intake review approved
|
Intake Approval | | | 6/8/2018 | | |
Julie Romig
|
|
|
Need completed Form 310
|
Intake Approval | | | 6/7/2018 | | FAIL |
Julie Romig
|
|
|
Need completed Form 310
|
Intake Approval | | | 6/7/2018 | | |
Julie Romig
|
|
|
Need completed Form 310
|
Intake Approval | | | 6/4/2018 | | FAIL |
Julie Romig
|
|
|
1. Completed 520 Checklist.
2. Structural calculations for MRI attachments, lift attachment, roof top equipment, new openings, etc.
3. Signed structural drawings.
4. Form 310 for required special inspections.
5. Identify the location of existing fire rated assemblies (including smoke partitions/barriers).
6. ESC Waiver Letter
7. Any other documentation as required by the 520 Checklist.
|
Application received | | | 5/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 21 2018 7:31AM
|
Second Notice | | 8/20/2020 | | | |
|
|
|
|