Print Statement | | | 11/20/2018 | | DONE |
|
|
|
|
Second Notice | | 10/22/2018 | 11/13/2018 | | DONE |
|
|
|
|
First Notice | | 9/27/2018 | 10/12/2018 | | DONE |
|
|
|
mailed 10-15-18
|
BLD-Final | 9/16/2018 | 9/17/2018 | 9/17/2018 | A | PASS |
Dave Hannah
|
|
|
Building final Business Interiors. Super working on exterior make sure to contact number above upon arrival. Phone #: ###-#### Inspection requested via web by Devan Hardwick
|
Permanent Occupancy | | | 9/17/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/13/2018 | 9/14/2018 | 9/14/2018 | A | PASS |
Mike Jordan
|
|
|
Re-Inspection of door hardware on sliding glass door and swing door to ensure no locking mechanisms. Please contact Devan Hardwick prior to arrival at number provided. Phone #: ###-#### Inspection requested via web by Devan Hardwick. All issues resolved. Ok for final.
|
FIRE-Final Inspection | 9/12/2018 | 9/13/2018 | 9/13/2018 | P | FAIL |
Mike Jordan
|
|
|
Final Inspection for fire/life/safety SEE DESCRIPTION BY JAVIER GUZMAN: BUILDING IS INTENDED NON FIRE-SPRINKLERED. MINOR CHANGES MADE, PROJECT FLOOR IS OPEN PLENUM, SMOKE DETECTORS UPDATED, OTHERWISE SYSTEM REMAINS THE SAME. Please contact Devan Hardwick prior to arrival for parking. Phone #: ###-#### Inspection requested via web by Devan Hardwick. Remove the thumb turn and key locking hardware from the glass sliding doors upstairs. Remove the ke locking hardware or provide single action lever hardware from the side hung glass door. Noted that new smoke detectors installed are of the same model. No fire alarm permit will be required.
|
BLD-Ceiling Grid Inspection | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | DONE |
Dave Hannah
|
|
|
Devin-above grid Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PASS |
Dave Hannah
|
|
|
Devin Phone #: ###-####
|
Fees Due Hold | 6/26/2018 | | 6/28/2018 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | PASS |
Jim Sly
|
|
|
Devin Phone #: ###-####
|
Permit Ready to Issue | | | 6/18/2018 | | DONE |
|
|
|
NEED- all met
GC FORM- met
REVISED VALUE
|
Issue PAID IN FULL permit | | | 6/18/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/18/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 5/24/2018 | 5/24/2018 | 6/16/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 6/06 L2 Business Interiors of Idaho TI ePlan
|
Routing - PLAN CHECK | 6/13/2018 | | 6/16/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/16/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/11/2018 | 6/14/2018 | 6/11/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 5/24/2018 | | 6/11/2018 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 6/11/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 5/24/2018 | | 6/4/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 5/24/2018 | | 5/24/2018 | | PASS |
Doug Chausow
|
|
|
Floor 2
|
Routing - PUBLIC WORKS | 5/24/2018 | | 5/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 5/24/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 5/23/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following: 1. Missing wall bracing information 2. Missing stamp and signature on all plans. This is required on the interior design plans as they have code compliance related information. 3. Missing stamped signed plumbing plans
|
Application received | | | 5/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 22 2018 2:15PM
|