Permit Information
Permit NumberBLD18-01830
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 5599 E HOOTOWL DR
Project NameCottonwood Lakehouse
Customer Number 
ePlanReviewYes
Description
***FIRE SPRINKLER SYSTEM VOLUNTARILY INSTALLED***Prescriptive component energy approach*** Permit for the construction of a new 3,089 sq. ft., one story single family dwelling with 3 bedrooms, 3 and a half bathrooms, approximately 616 sq. ft. of covered patio/porch and a 927 sq. ft. attached garage per the approved plans and any notations. SP-01 zoning and setbacks per planning. MDH


A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.


Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/15/20191/16/20191/16/2019APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
DOC - Permit Finaled1/16/20191/16/20191/16/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results1/16/20191/16/20191/16/2019ADONE
DetailsBrandon Shaw
ACH50- 2.05
PubWorks Occupancy Approval1/15/20191/15/20191/15/2019 DONE
DetailsMelissa Jannusch
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Final1/9/20191/9/20191/9/2019PNR
DetailsBrandon Shaw
Sorry Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Final1/8/20191/9/20191/9/2019ACANC
DetailsBrandon Shaw
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
BLD-Final1/4/20191/4/20191/4/2019PFAIL
DetailsBrandon Shaw
Need all trade permits finalled...
Need PW approval...
BLD-Other10/4/201810/5/201810/5/2018PPASS
DetailsBrandon Shaw
sofit // Rolo Phone #: ###-####
BLD-Energy code compliance10/2/201810/3/201810/3/2018APASS
DetailsBrandon Shaw
rolo Phone #: ###-####
BLD-Framing/Rough-in10/1/201810/1/201810/1/2018PPEND
DetailsBrandon Shaw
Pending fire sprinkler approval
BLD-Wall Bracing9/12/20189/12/20189/13/2018PFAIL
DetailsBrandon Shaw
Anchor bolts to be secured and fastened with washers and nuts...
Anchor bolts to be no more than 12" from ends of sill plate...
Verify 3"x3" nailing pattenfor PHG per detail...
Hold downs to be fastened per manufactures installation instructions...
BLD-Foundation7/24/20187/24/20187/24/2018PPASS
DetailsBrandon Shaw
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
BLD-Footing7/23/20187/23/20187/23/2018PCANC
DetailsBrandon Shaw
Dion Phone #: ###-####
BLD-Footing7/19/20187/20/20187/20/2018APASS
DetailsDave Hannah
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
PubWorks Subgrade Approval7/20/20187/20/20187/20/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

BLD-Footing7/18/20187/19/20187/19/2018ANR
DetailsMike Jordan
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell. Needs geotech report to public works.
Inspection Record Card- Bld  7/3/2018 DONE
Issue PAID IN FULL permit  7/3/2018 DONE
OVERRIDE  6/8/2018  
Permit Ready to Issue  6/8/2018 DONE
met
Plan assigned to (M_H)5/23/2018 6/7/2018 DONE
DetailsMichael Hanson
06/11 sfd L2 ePlan. 1st review completed - Retaining wall calc correction required. MDH
Routing - PLAN CHECK5/23/2018 6/7/2018 FAIL
DetailsMichael Hanson
Retaining wall calc correction required. MDH
Plan Reviewer's activity  6/7/2018 DONE
DetailsMichael Hanson
1st review completed  6/7/2018 FAIL
DetailsMichael Hanson
Retaining wall calc correction required. MDH
Routing - PLAN CHECK6/7/2018 6/7/2018 PASS
DetailsMichael Hanson
PLANS/APPL TAKEN TO FRONT DESK  6/7/2018 DONE
DetailsMichael Hanson
Routing PW Grading-Hillside5/24/2018 6/1/2018 PASS
DetailsMelissa Jannusch



A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.


Routing - FIRE5/23/20185/23/20185/31/2018 PASS
DetailsTim Frost
6/11 New R3 SFH L2
Route to Impact Fee Review5/23/20185/26/20185/24/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - Addressing5/23/2018 5/24/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS5/23/2018 5/24/2018 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment5/23/2018 5/24/2018 PASS
DetailsMichael Zawacki
Harris North foothills home. Site prep inspection required.
Routing - MECHANICAL5/23/2018 5/24/2018 PASS
DetailsTroy James
Application received  5/23/2018 DONE
Application submitted via PDS Online on May 23 2018 9:32AM
Plans ACCEPTED BY PLAN TECH  5/23/2018 DONE
Recd Pcfee & Taken To Pln CK  5/23/2018 DONE
Intake Approval  5/23/2018 PASS
Routing - PLANNING5/23/2018 5/23/2018 PASS
DetailsSue Cummings