BLD-Final | 1/15/2019 | 1/16/2019 | 1/16/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 1/16/2019 | 1/16/2019 | 1/16/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 1/16/2019 | 1/16/2019 | 1/16/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 2.05
|
PubWorks Occupancy Approval | 1/15/2019 | 1/15/2019 | 1/15/2019 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 1/9/2019 | 1/9/2019 | 1/9/2019 | P | NR |
Brandon Shaw
|
|
|
Sorry Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Final | 1/8/2019 | 1/9/2019 | 1/9/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
|
BLD-Final | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | FAIL |
Brandon Shaw
|
|
|
Need all trade permits finalled... Need PW approval...
|
BLD-Other | 10/4/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Brandon Shaw
|
|
|
sofit // Rolo Phone #: ###-####
|
BLD-Energy code compliance | 10/2/2018 | 10/3/2018 | 10/3/2018 | A | PASS |
Brandon Shaw
|
|
|
rolo Phone #: ###-####
|
BLD-Framing/Rough-in | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PEND |
Brandon Shaw
|
|
|
Pending fire sprinkler approval
|
BLD-Wall Bracing | 9/12/2018 | 9/12/2018 | 9/13/2018 | P | FAIL |
Brandon Shaw
|
|
|
Anchor bolts to be secured and fastened with washers and nuts... Anchor bolts to be no more than 12" from ends of sill plate... Verify 3"x3" nailing pattenfor PHG per detail... Hold downs to be fastened per manufactures installation instructions...
|
BLD-Foundation | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | PASS |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 7/23/2018 | 7/23/2018 | 7/23/2018 | P | CANC |
Brandon Shaw
|
|
|
Dion Phone #: ###-####
|
BLD-Footing | 7/19/2018 | 7/20/2018 | 7/20/2018 | A | PASS |
Dave Hannah
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
PubWorks Subgrade Approval | 7/20/2018 | 7/20/2018 | 7/20/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 7/18/2018 | 7/19/2018 | 7/19/2018 | A | NR |
Mike Jordan
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell. Needs geotech report to public works.
|
Inspection Record Card- Bld | | | 7/3/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/3/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 6/8/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 6/8/2018 | | DONE |
|
|
|
met
|
Plan assigned to (M_H) | 5/23/2018 | | 6/7/2018 | | DONE |
Michael Hanson
|
|
|
06/11 sfd L2 ePlan. 1st review completed - Retaining wall calc correction required. MDH
|
Routing - PLAN CHECK | 5/23/2018 | | 6/7/2018 | | FAIL |
Michael Hanson
|
|
|
Retaining wall calc correction required. MDH
|
Plan Reviewer's activity | | | 6/7/2018 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 6/7/2018 | | FAIL |
Michael Hanson
|
|
|
Retaining wall calc correction required. MDH
|
Routing - PLAN CHECK | 6/7/2018 | | 6/7/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2018 | | DONE |
Michael Hanson
|
|
|
|
Routing PW Grading-Hillside | 5/24/2018 | | 6/1/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
|
Routing - FIRE | 5/23/2018 | 5/23/2018 | 5/31/2018 | | PASS |
Tim Frost
|
|
|
6/11 New R3 SFH L2
|
Route to Impact Fee Review | 5/23/2018 | 5/26/2018 | 5/24/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 5/23/2018 | | 5/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/23/2018 | | 5/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 5/23/2018 | | 5/24/2018 | | PASS |
Michael Zawacki
|
|
|
Harris North foothills home. Site prep inspection required.
|
Routing - MECHANICAL | 5/23/2018 | | 5/24/2018 | | PASS |
Troy James
|
|
|
|
Application received | | | 5/23/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 23 2018 9:32AM
|
Plans ACCEPTED BY PLAN TECH | | | 5/23/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/23/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/23/2018 | | PASS |
|
|
|
|
Routing - PLANNING | 5/23/2018 | | 5/23/2018 | | PASS |
Sue Cummings
|
|
|
|