BLD-Final | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PASS |
Dave Hannah
|
|
|
Kerry Phone #: ###-####
|
DOC - Permit Finaled | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 2/7/2019 | 2/8/2019 | 2/8/2019 | A | FAIL |
Jim Storey
|
|
|
call for access // Cerry Phone #: ###-#### no roof penarations with in 4 ft of ridge// need vents of roof 1718/ house and garage.
|
BLD-Energy code compliance | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Jim Storey
|
|
|
Terry Phone #: ###-####
|
BLD-Framing/Rough-in | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | PASS |
Jim Storey
|
|
|
Kerry Phone #: ###-#### no vents in soffit of garage
|
BLD-Framing/Rough-in | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | FAIL |
Jim Storey
|
|
|
Vinny Phone #: ###-#### penatrate fire wall have arch and planrevirwer resolve for compliance/ hold downs need nuts/ need ft before slabs/ eave gypat garage/need hvac aprovals.
|
BLD-Energy code compliance | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | NR |
Jim Storey
|
|
|
Vinny Phone #: ###-####
|
BLD-Other | 10/2/2018 | 10/3/2018 | 10/3/2018 | A | PASS |
Jim Storey
|
|
|
garge-fire wall-vinnie Phone #: ###-####
|
BLD-Wall Bracing | 9/26/2018 | 9/27/2018 | 9/27/2018 | A | PASS |
Jim Storey
|
|
|
HOUSE ONLY Vinnie Phone #: ###-####
|
BLD-Other | 9/19/2018 | 9/20/2018 | 9/20/2018 | A | DONE |
Brandon Shaw
|
|
|
fire wall- Need fire wall revision/details submitted and attached to approved set of plans... Mud and tape top seam, at top plate and continue sheat rock to under layment of roof, with seams off set 16" horizontally and vertically...
|
BLD-Footing | 8/28/2018 | 8/28/2018 | 8/28/2018 | P | PASS |
Jim Storey
|
|
|
Derek Phone #: ###-####
|
BLD-Footing | 8/24/2018 | 8/27/2018 | 8/27/2018 | P | NR |
Brandon Shaw
|
|
|
Derek Phone #: ###-####
|
BLD-Footing | 8/22/2018 | 8/22/2018 | 8/22/2018 | P | NR |
Jim Storey
|
|
|
Pat Phone #: ###-#### lot flooded need compaction report
|
BLD-Footing | 8/17/2018 | 8/20/2018 | 8/20/2018 | A | NR |
Jim Storey
|
|
|
Derick Phone #: ###-#### site flooded
|
BLD-Footing | 8/6/2018 | 8/7/2018 | 8/7/2018 | A | NR |
Jim Sly
|
|
|
Mercedes Phone #: ###-####
|
BLD-Footing | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | CANC |
Jim Storey
|
|
|
Mercedes Phone #: ###-#### cancelled per Mercedes 08-06-2018 KFW told him to call inspector
|
1st review completed | | | 8/6/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/26/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/25/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/25/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/20/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 5/24/2018 | 5/24/2018 | 7/20/2018 | | DONE |
Brian McGowan
|
|
|
1st review complete. 6-12 sfd L2 Townhome ePlan
|
Routing - PLAN CHECK | 7/20/2018 | | 7/20/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/20/2018 | | DONE |
|
|
|
met-do not issue without BLD18-01660
|
Routing - PLANNING | 5/24/2018 | | 6/1/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH18-00012
|
Route to Impact Fee Review | 5/24/2018 | 5/27/2018 | 5/29/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 5/24/2018 | | 5/25/2018 | | PASS |
Troy James
|
|
|
|
VOIDED CHANGE STATUS | | | 5/24/2018 | | DONE |
|
|
|
duplicate
|
CHANGE STATUS TO (REV) | | | 5/24/2018 | | DONE |
|
|
|
voided BLD18-01671 because the fees were paid to this permit and not to it. We voided BLD18-01671.
|
Plans ACCEPTED BY PLAN TECH | | | 5/24/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/24/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/24/2018 | | DONE |
|
|
|
|
Routing - Addressing | 5/24/2018 | | 5/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/24/2018 | | 5/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 5/23/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 23 2018 10:40PM
|