BLD-Final | 1/28/2019 | 1/29/2019 | 1/29/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 1/29/2019 | 1/29/2019 | 1/29/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 1/29/2019 | 1/29/2019 | 1/29/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.8
|
PubWorks Occupancy Approval | 1/29/2019 | 1/29/2019 | 1/29/2019 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | NR |
Brandon Shaw
|
|
|
Need PW approval...
|
CHANGE STATUS TO (ISS) | | | 1/25/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/25/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 11/21/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 11/19/2018 | 11/19/2018 | 11/21/2018 | | DONE |
Brian McGowan
|
|
|
replace 3 windows in great room with slider
|
Routing - PLAN CHECK | 11/20/2018 | | 11/21/2018 | | PASS |
Brian McGowan
|
|
|
MINIMAL TIME FOR REVIEW - 1/2 HOUR
|
Permit Ready to Issue | | | 11/21/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT RE ISSUE
|
CHANGE STATUS TO (REV) | | | 11/19/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 11/19/2018 | | DONE |
Christina Prado
|
|
|
Plan Mod - remove 3 windows from great room to replace with large slider
|
BLD-Energy code compliance | 10/24/2018 | 10/25/2018 | 10/25/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to cover
|
BLD-Framing/Rough-in | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Dave Hannah
|
|
|
Rolo Phone #: ###-####
|
BLD-Other | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | PART |
Tony Young
|
|
|
Rollo-soffit Phone #: ###-####,, work in progress,, ok
|
BLD-Framing/Rough-in | 10/17/2018 | 10/18/2018 | 10/18/2018 | P | CANC |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
BLD-Wall Bracing | 9/25/2018 | 9/25/2018 | 9/25/2018 | P | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
BLD-Foundation | 8/3/2018 | 8/3/2018 | 8/3/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 7/31/2018 | 8/1/2018 | 8/1/2018 | P | PASS |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
PubWorks Subgrade Approval | 8/1/2018 | 8/1/2018 | 8/1/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 7/31/2018 | 7/31/2018 | 7/31/2018 | P | NR |
Brandon Shaw
|
|
|
Need subgrage approval
|
Issue PAID IN FULL permit | | | 7/20/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/20/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/20/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 6/28/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 5/24/2018 | 5/24/2018 | 6/28/2018 | | DONE |
Brian McGowan
|
|
|
6-12 sfd L2 ePlan
|
Routing - PLAN CHECK | 5/24/2018 | | 6/28/2018 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 6/28/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/28/2018 | | DONE |
|
|
|
met
|
Routing PW Grading-Hillside | 5/25/2018 | | 6/1/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
|
Routing - FIRE | 5/24/2018 | 5/24/2018 | 5/31/2018 | | PASS |
Tim Frost
|
|
|
6/13 New SFH R3 ePlan
|
Route to Impact Fee Review | 5/24/2018 | 5/27/2018 | 5/29/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Erosion and Sediment | 5/24/2018 | | 5/29/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Site preparation inspection is REQUIRED.
|
Routing - Addressing | 5/24/2018 | | 5/25/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/24/2018 | | 5/25/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 5/24/2018 | | 5/25/2018 | | PASS |
Troy James
|
|
|
|
Application received | | | 5/24/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 24 2018 3:20PM
|
Plans ACCEPTED BY PLAN TECH | | | 5/24/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/24/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/24/2018 | | PASS |
|
|
|
|
Routing - PLANNING | 5/24/2018 | | 5/24/2018 | | PASS |
Sue Cummings
|
|
|
|