BLD-Final | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PASS |
Tony Young
|
|
|
Final can be done at anytime you are in the area. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
DOC - Permit Finaled | 8/31/2018 | 8/31/2018 | 8/31/2018 | P | PASS |
Tony Young
|
|
|
|
PubWorks Subgrade Approval | 8/6/2018 | 8/6/2018 | 8/6/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 7/24/2018 | 7/25/2018 | 7/25/2018 | P | PEND |
Tony Young
|
|
|
Phone #: 2085736921 >> Inspection requested via mobile web by Jimmy,, ok pending soils approval
|
BLD-Footing | 7/23/2018 | 7/24/2018 | 7/25/2018 | P | PEND |
Tony Young
|
|
|
Phone #: 2085736921 >> Inspection requested via mobile web by Jimmy
|
BLD-Footing | 7/23/2018 | 7/23/2018 | 7/24/2018 | P | NR |
Tony Young
|
|
|
Phone #: 2085736921 >> Inspection requested via mobile web by Jimmy,, still needs soils approval
|
BLD-Footing | 7/20/2018 | 7/23/2018 | 7/23/2018 | A | NR |
Tony Young
|
|
|
Phone #: 2085736921 >> Inspection requested via mobile web by Jimmy,, needs soils approval
|
Issue PAID IN FULL permit | | | 7/5/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/5/2018 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 7/3/2018 | 7/3/2018 | 7/3/2018 | A | PASS |
Sue Cummings
|
|
|
Open Air structure under 250 s.f. and less than 15 ft tall
|
Plan assigned to (JAB) Josh | 5/31/2018 | 5/31/2018 | 7/3/2018 | | PASS |
Josh Bogle
|
|
|
1st done - Hillside patio cover
|
Routing - PLAN CHECK | 7/3/2018 | | 7/3/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2018 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 7/3/2018 | | DONE |
|
|
|
|
1st review completed | | | 6/7/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/31/2018 | | 6/7/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - Erosion and Sediment | 5/31/2018 | | 6/4/2018 | | PASS |
Andy J. Long
|
|
|
No ESC permit required. Minimal excavation and disturbance.
|
Routing PW Grading-Hillside | 5/31/2018 | | 6/1/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
|
Routing PW Drainage | 5/31/2018 | | 5/31/2018 | | PASS |
Brian Murphy
|
|
|
NO REVIEW NEEDED
|
Routing - PUBLIC WORKS | 5/31/2018 | | 5/31/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/31/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/31/2018 | | DONE |
|
|
|
no fee taken at intake, 406
|
Intake Approval | | | 5/31/2018 | | PASS |
|
|
|
|
Application received | | | 5/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 27 2018 11:20AM
|
Routing - PLANNING | 5/31/2018 | | | | FAIL |
|
|
|
While the site plan indicates a 40 foot setback, the original permit for the house (site plan drawn to scale by an architect) shows the house is currently 35 feet from rear property line. Any addition more than 5 feet is in the setback and the fire defensible space.
|