BLD-Aging Inspection | 2/13/2019 | 2/13/2019 | 2/21/2019 | | PEND |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Dave Hannah
|
|
|
Please call ahead for access - Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 9/19/2018 | 9/19/2018 | 9/19/2018 | P | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 9/13/2018 | 9/14/2018 | 9/14/2018 | A | NR |
Dave Hannah
|
|
|
Chris Phone #: ###-#### needs air seal and strape top plates ok to spray foam
|
Plan assigned to (BJM) | 6/8/2018 | 6/8/2018 | 6/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/26/2018 | | 6/26/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 6/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 6/26/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/26/2018 | | DONE |
|
|
|
|
Telephone call | | | 6/26/2018 | | DONE |
|
|
|
Left a message for Chris informing permit is ready and fee amount due for issuance
|
Issue PAID IN FULL permit | | | 6/26/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/12/2018 | | DONE |
|
|
|
received two copies of plan sheet A-1; taken to Brian McGowan
|
Routing - PLANNING | 6/12/2018 | | 6/12/2018 | | PASS |
Sue Cummings
|
|
|
Adding a covered front porch.
|
Plan resubmittals received | | | 6/11/2018 | | DONE |
|
|
|
Resubmittals received 2 sets of sheets A-5, A-10 & A-11-took to Brian McGowan
|
1st review completed | | | 6/8/2018 | | FAIL |
Brian McGowan
|
|
|
No information provided on Basement or how the stairs will be modified to work for the Basement.
|
Routing - PLAN CHECK | 6/8/2018 | | 6/8/2018 | | FAIL |
Brian McGowan
|
|
|
No information provided on Basement or how the stairs will be modified to work for the Basement.
|
Plan resubmittals received | | | 6/1/2018 | | DONE |
|
|
|
received application, engineering calcs and plan sheets A-1, A-2, A-3, A-4, A-5, A-6, A-7, A-8, A-9, A-10; taken to BGM
|
Plan resubmittals received | | | 5/31/2018 | | DONE |
|
|
|
One copy of Beam Summary Report, two copies of sheets A-1, A-2, A-3, A-4, A-5, A-6, A-7A-8, A-9, and A-10. Taken to Brian Mc
|
Routing Walk-In (Zoning) | 5/29/2018 | 5/29/2018 | 5/29/2018 | A | PASS |
Nicolette Womack
|
|
|
|
Routing Walk-In (BLD) | 5/29/2018 | 5/29/2018 | 5/29/2018 | A | FAIL |
Brian McGowan
|
|
|
Needs more details on existing framing and proposed new construction details.
|
1st review completed | | | 5/29/2018 | | FAIL |
Brian McGowan
|
|
|
Needs more details on existing framing and proposed new construction details.
|
Routing - PLAN CHECK | 5/29/2018 | | 5/29/2018 | | FAIL |
Brian McGowan
|
|
|
Needs more details on existing framing and proposed new construction details.
|
Application received | | 5/29/2018 | | | |
|
|
|
|