BLD-Final | 10/19/2018 | 10/22/2018 | 10/22/2018 | A | DONE |
Mike Jordan
|
|
|
This is the final bldg inspection for East Gate (Message Center) Call Aaron for Questions Phone #: ###-#### Inspection requested via web by Dana Vance
|
DOC - Permit Finaled | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Mike Jordan
|
|
|
|
Permit Ready to Issue | | | 6/7/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/7/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/6/2018 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 6/6/2018 | | FAIL |
Michael Hanson
|
|
|
In field welding requires 310 form. MDH
|
Routing - PLAN CHECK | 6/6/2018 | | 6/6/2018 | | FAIL |
Michael Hanson
|
|
|
In field welding requires 310 form. MDH
|
Routing - PLAN CHECK | 6/6/2018 | | 6/6/2018 | | PASS |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 6/6/2018 | | 6/6/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2018 | | DONE |
Michael Hanson
|
|
|
|
Application received | | | 5/29/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 29 2018 10:19PM
|
First Notice | 10/22/2018 | 10/22/2018 | | | |
Mike Jordan
|
|
|
|