Letter of compliance/Occupancy | | | 5/13/2019 | | DONE |
|
|
|
|
BLD-Final | 5/9/2019 | 5/10/2019 | 5/10/2019 | P | PASS |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
DOC - Permit Finaled | 5/10/2019 | 5/10/2019 | 5/10/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 5/9/2019 | 5/10/2019 | 5/10/2019 | P | DONE |
Tony Young
|
|
|
Jeff Phone #: ###-####/// 5.02
|
BLD-Framing/Rough-in | 5/8/2019 | 5/9/2019 | 5/10/2019 | P | PASS |
Tony Young
|
|
|
Jeff Phone #: ###-####,, wanted a final
|
BLD-Final | 5/2/2019 | 5/6/2019 | 5/6/2019 | P | FAIL |
Brandon Shaw
|
|
|
No address posted... Need to post Blower door test...
|
BLD-Final | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | FAIL |
Tony Young
|
|
|
Jeff Phone #: ###-####,, no address posted,, no answer on phone,, not able to leave a voice mail due to being full,, needs plumbing final also,, door locked
|
BLD-Wall cover | 12/13/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Energy code compliance | 12/13/2018 | 12/13/2018 | 12/13/2018 | P | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, ok,, just needs to fix f/p flue
|
BLD-Framing/Rough-in | 12/13/2018 | 12/13/2018 | 12/13/2018 | P | PASS |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | PASS |
Tony Young
|
|
|
Jeff Phone #: ###-####,, ok to insulate
|
BLD-Framing/Rough-in | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | NR |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | NR |
Tony Young
|
|
|
Jeff Phone #: ###-####// c/n posted,, brace trusses per engineering,, doing other modifications
|
BLD-Framing/Rough-in | 12/6/2018 | 12/6/2018 | 12/6/2018 | P | FAIL |
Tony Young
|
|
|
Jeff Phone #: ###-####,, c/n posted,, trades, sill bolts, nailing headers, fire blocking,, do not insulate
|
Plan Modification Accepted | | | 11/16/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 11/16/2018 | | 11/16/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 10/15/2018 | 10/15/2018 | 10/15/2018 | P | PASS |
Brandon Shaw
|
|
|
Johnny Phone #: ###-####
|
BLD-Foundation | 8/13/2018 | 8/13/2018 | 8/13/2018 | P | PART |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 8/10/2018 | 8/10/2018 | 8/10/2018 | P | PART |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Conference | 8/10/2018 | 8/10/2018 | 8/10/2018 | P | CANC |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron Inspection cancelled via mobile web on Friday, August 10, 2018.
|
Place hold on job | 7/6/2018 | | 7/11/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
waiting for signed permit back
|
Telephone call | | | 7/11/2018 | | DONE |
|
|
|
Left voicemail for Cody to check the email. Sent two emails since 7/5/18 for the permit to be signed and emailed back.
|
Issue PAID IN FULL permit | | | 7/5/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/5/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/3/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 5/30/2018 | 5/30/2018 | 7/3/2018 | | DONE |
Rob Patrick
|
|
|
6/12 sfd L1 ePlan...6/28: Failed Braced Wall data req'd
|
Routing - PLAN CHECK | 7/3/2018 | | 7/3/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 7/3/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 6/28/2018 | | 6/28/2018 | | PASS |
Sue Cummings
|
|
|
Moved (or reduced) house to comply with front yard easement. O.K. now.
|
Routing - PLAN CHECK | 6/28/2018 | | 6/28/2018 | | FAIL |
Rob Patrick
|
|
|
Braced Wall table required
|
1st review completed | | | 6/1/2018 | | FAIL |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 5/30/2018 | | 6/1/2018 | | FAIL |
Rob Patrick
|
|
|
Failed due to Planning comments
|
Routing - MECHANICAL | 5/30/2018 | | 6/1/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 5/30/2018 | 6/2/2018 | 5/31/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Application received | | | 5/30/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 30 2018 8:25AM
|
Intake Approval | | | 5/30/2018 | | FAIL |
|
|
|
1.Please upload the plans with the drawing file names showing the first characters of the sheet name, followed by the sheet number. (example A.1 Site Plan or Framing A.4) For clarity all plans have been deleted from the drawings folder.
2.Please upload the REScheck or provide the table for prescriptive methods shown on plans.
(prescreen done, plans were deleted. New quick prescreen needed after plans uploaded again)
|
Plans ACCEPTED BY PLAN TECH | | | 5/30/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/30/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/30/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 5/30/2018 | | 5/30/2018 | | FAIL |
Sue Cummings
|
|
|
There is a 16 foot sidewalk and publick utilities easement along the front property line
|
Routing - Addressing | 5/30/2018 | | 5/30/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/30/2018 | | 5/30/2018 | | PASS |
Rachael Beierle
|
|
|
|