BLD-Final | 11/14/2018 | 11/19/2018 | 11/19/2018 | P | NR |
Jim Sly
|
|
|
Inspection requested via web by John Nock No phone # given.....to notify contractor. Need Plumbing and Mechanical finals.
|
BLD-Wall cover | 8/14/2018 | 8/14/2018 | 8/14/2018 | P | PASS |
Jim Sly
|
|
|
Drywall Phone #: ###-#### Inspection requested via web by John Nock
|
BLD-Energy code compliance | 8/2/2018 | 8/3/2018 | 8/3/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by John Nock
|
BLD-Conference | 7/30/2018 | 7/31/2018 | 7/31/2018 | P | CANC |
Jim Sly
|
|
|
Joist hangers. Phone #: ###-#### >> Inspection requested via web by John Nock Inspection cancelled from web by: John Nock Inspection cancelled from web by: John Nock
|
BLD-Framing/Rough-in | 7/30/2018 | 7/30/2018 | 7/30/2018 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by John Nock
|
BLD-Conference | 7/11/2018 | 7/11/2018 | 7/11/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by John Nock
|
BLD-Footing | 6/19/2018 | 6/20/2018 | 6/20/2018 | A | PASS |
Jim Sly
|
|
|
Footers and foundation framed Phone #: ###-#### Inspection requested via web by John Nock
|
BLD-Footing | 6/13/2018 | 6/18/2018 | 6/17/2018 | A | CANC |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by John Nock Inspection cancelled from web by: John Nock
|
OVERRIDE | | | 6/7/2018 | | |
|
|
|
|
Routing Walk-In (BLD) | 6/7/2018 | 6/7/2018 | 6/7/2018 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 6/7/2018 | | 6/7/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 6/7/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 6/7/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 6/7/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 6/7/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/7/2018 | | |
|
|
|
|
Routing Walk-In (Zoning) | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PASS |
Josh Bogle
|
|
|
lacked some details - point loads are a particular concern
|
Routing - PLAN CHECK | 5/30/2018 | | 5/30/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 5/30/2018 | | FAIL |
Josh Bogle
|
|
|
|
BLD-Wall cover | 8/23/2018 | 8/14/2018 | | P | |
Jim Sly
|
|
|
Drywall Phone #: ###-#### >> Inspection requested via web by John Nock
|
Application received | | 5/30/2018 | | | |
|
|
|
|