Print Statement | | | 2/19/2019 | | DONE |
|
|
|
|
First Notice | | 1/21/2019 | 2/7/2019 | | DONE |
|
|
|
mailed 2-11-19
|
Print Occupancy Form | | | 1/11/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/11/2019 | | DONE |
|
|
|
|
BLD-Final | 1/8/2019 | 1/8/2019 | 1/8/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jason Ginn
|
FIRE-Final Inspection | 1/8/2019 | 1/8/2019 | 1/8/2019 | A | PASS |
Jim Page
|
|
|
Troubles on fire panel have been repaired, final life fire safety inspection complete.
Phone #: ###-#### Inspection requested via web by Jason Ginn
|
BLD-Final | 12/20/2018 | 12/21/2018 | 12/21/2018 | P | PEND |
Dave Hannah
|
|
|
Please call Jason 45 minutes prior to arriving on site for inspection. My phone number is ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Jason Ginn ok for temp occ ok for perm occ after fire final perm
|
FIRE-Final Inspection | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PART |
Jim Page
|
|
|
Fire sprinkler inspection for area of work complete, fire alarm inspection for area of work complete, fire extinguishers are placed with current inspection tags in area of work. Fire alarm panel for building had troubles at time of inspection, troubles need to be repaired and fire panel needs to show normal before life fire safety can be finaled, all other items for life fire safety inspection is complete.
Phone #: ###-#### Inspection requested via web by Jason Ginn
|
FIRE-Alarm Testing | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | CANC |
Jim Page
|
|
|
Phone #: ###-#### Inspection requested via web by Jason Ginn
|
BLD-Ceiling Grid Inspection | 12/13/2018 | 12/13/2018 | 12/13/2018 | P | PASS |
Dave Hannah
|
|
|
This project is being completed during the night. Please call Jason Ginn 30 to 45 minutes ahead of the inspection so I can meet you onsite. My phone number is ###-####. Thanks, Phone #: ###-#### Inspection requested via web by Jason Ginn
|
BLD-Framing/Rough-in | 11/2/2018 | 11/2/2018 | 11/5/2018 | P | PART |
Dave Hannah
|
|
|
Requesting a partial framing inspection to hang GWB on one side of corridor wall. Please call Jason 1 hour before arriving onsite as this work is being performed at night and no construction personnel are onsite during the day. I will have to meet you there for the inspection. If Jason cannot be reached please contact Jake Salinas at ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Jason Ginn ok to one side corradors
|
Print Occupancy Form | | | 7/20/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/20/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/20/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 6/7/2018 | 6/7/2018 | 7/19/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 6/20 L2 MICROSOFT BOISE ePlan
|
Routing - PLAN CHECK | 7/16/2018 | | 7/19/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/19/2018 | | DONE |
|
|
|
MET
Need
GC Form
Revised Cert of Value
|
Routing - PLAN CHECK | 7/10/2018 | | 7/10/2018 | | FAIL |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 6/25/2018 | 6/28/2018 | 6/25/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 6/21/2018 | 6/21/2018 | 6/25/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 6/25/2018 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 6/7/2018 | | 6/21/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 6/7/2018 | | 6/12/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 6/7/2018 | | 6/8/2018 | | PASS |
Laura Hunter
|
|
|
Assigned Ste 600
|
Routing - PUBLIC WORKS | 6/7/2018 | | 6/8/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 6/7/2018 | | 6/8/2018 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 6/7/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 6/6/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Missing signature on architectural sheets
2. Provide wall bracing detail. (How are new interior walls secured)
|
Application received | | | 5/30/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 30 2018 6:12PM
|