Third Notice | | 11/11/2018 | 11/13/2018 | | DONE |
|
|
|
This permit finaled on the web by Travis Myers
|
Second Notice | | 10/21/2018 | 11/6/2018 | | DONE |
|
|
|
mailed 11-12
|
First Notice | 9/10/2018 | 9/10/2018 | 10/11/2018 | | DONE |
Mike Jordan
|
|
|
mailed 10-12-18
|
BLD-Final | 9/10/2018 | 9/10/2018 | 9/10/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Myers
|
DOC - Permit Finaled | 9/10/2018 | 9/10/2018 | 9/10/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Conference | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | DONE |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | PASS |
Jim Page
|
|
|
Hydrostatic test was perfromed on fire sprinkler system to verify integrity of fire sprinkler piping, hydro passed, final life fire safety inspection for scope of work complete.
Phone #: ###-#### Inspection requested via web by Travis Myers
|
FIRE-Final Inspection | 8/15/2018 | 8/16/2018 | 8/16/2018 | A | CANC |
Troy Cobbley
|
|
|
Fire/Life/Safety Final Phone #: ###-#### Inspection requested via web by Travis Myers
|
BLD-Final | 8/14/2018 | 8/15/2018 | 8/15/2018 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Myers. Needs fire/life/safety final first.
|
BLD-Framing/Rough-in | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Floor joist replacement ok. ok to cover. Also inspected exterior wall elements. All damaged siding has been removed. Framing elements at exterior wall showed no fire damaged.
|
Inspection Record Card- Bld | | | 6/20/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/20/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 6/7/2018 | 6/7/2018 | 6/13/2018 | | PASS |
Javier Guzman
|
|
|
L1 Fire damage ePlan
|
Routing - PLAN CHECK | 6/7/2018 | | 6/13/2018 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 6/13/2018 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/13/2018 | | DONE |
Christina Prado
|
|
|
Need:- all met
GC Form
Revised Cert of Value
**Not sure if Custom Cleanup is GC, not in our system. No new cert of value needed if they are GC**
|
Intake Approval | | | 6/7/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 6/4/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Provide all information listed in the 518 checklist "Plans Provided" section on a separate cover sheet minimum size 18"x24".
I've redlined the required items on the 518 checklist.
|
Application received | | | 5/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 31 2018 2:02PM
|