Second Notice | | 2/16/2019 | 3/11/2019 | | DONE |
|
|
|
mailed 3-12-19
|
Print Statement | | | 3/11/2019 | | DONE |
|
|
|
|
First Notice | | 1/12/2019 | 2/6/2019 | | DONE |
|
|
|
mailed 2-11-19
|
Print Occupancy Form | | | 1/3/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/2/2019 | | DONE |
|
|
|
|
BLD-Final | 12/31/2018 | 12/31/2018 | 12/31/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 12/28/2018 | 12/28/2018 | 12/31/2018 | P | PASS |
Dave Hannah
|
|
|
Clinton Phone #: ###-####
|
Temporary Occupancy | 11/21/2018 | 2/19/2019 | 11/21/2018 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PEND |
Dave Hannah
|
|
|
Clinton Phone #: ###-#### ok for temp occ needs to add handrail on aprt and returns on handrails on front steps and ramp
|
FIRE-Final Inspection | 11/19/2018 | 11/19/2018 | 11/19/2018 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final life fire safety inspection complete.
Clinton Phone #: ###-####
|
FIRE-Final Inspection | 11/15/2018 | 11/16/2018 | 11/16/2018 | A | FAIL |
Jim Page
|
|
|
Thumbturn deadbolt on ramp door needs to be changed to a double-key deadbolt with signage placed at door reading "Door to remain unlocked while building is occupied. Install code compliant door hardware on the two interior doors in common space on northside of building.
Clinton Phone #: ###-####
|
Zoning Approval | 11/14/2018 | 11/14/2018 | 11/14/2018 | | PASS |
David Moser
|
|
|
|
BLD-Framing/Rough-in | 9/21/2018 | 9/21/2018 | 9/21/2018 | P | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 9/10/2018 | 9/11/2018 | 9/11/2018 | A | PART |
Dave Hannah
|
|
|
interior framing - Chris Phone #: ###-#### ok to cover one side of four int walls
|
BLD-Framing/Rough-in | 9/5/2018 | 9/5/2018 | 9/5/2018 | P | NR |
Tony Young
|
|
|
Chris Phone #: ###-####,, needs trades 1st
|
BLD-Footing | 8/24/2018 | 8/24/2018 | 8/24/2018 | P | PASS |
Dave Hannah
|
|
|
rebar // Chris Phone #: ###-#### ftg in crawl space ok
|
BLD-Conference | 8/17/2018 | 8/20/2018 | 8/20/2018 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, general ?s on frame, firewalls, and ADA ramp vs. property line
|
Case Summary (BLD) | | | 8/8/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/11/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/11/2018 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 6/4/2018 | 6/4/2018 | 7/3/2018 | | PASS |
Carl Westfall
|
|
|
* (1st done) (June 22 - 15 days) (7 sheets) Boise Buddhist Community Center L-3
|
Routing - PLANNING | 7/2/2018 | | 7/3/2018 | | PASS |
David Moser
|
|
|
OK as per CUP17-00069 and CVA17-00063
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/3/2018 | | DONE |
|
|
|
all met-NEED
GC-met
ACHD-met
Rev Cert of val-met
|
Routing - PLAN CHECK | 6/28/2018 | | 7/2/2018 | | PASS |
Carl Westfall
|
|
|
|
Route to Impact Fee Review | 6/27/2018 | 6/30/2018 | 6/28/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals received | | | 6/28/2018 | | |
|
|
|
|
Routing - FIRE | 6/4/2018 | 6/4/2018 | 6/27/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 6/27/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 6/27/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/4/2018 | | 6/27/2018 | | PASS |
Carl Westfall
|
|
|
Completed the 1st review
|
Routing - MECHANICAL | 6/4/2018 | | 6/8/2018 | | PASS |
Troy James
|
|
|
Mechanical ventilation per openable windows and doors.
|
Routing - PLANNING | 6/4/2018 | | 6/4/2018 | | FAIL |
David Moser
|
|
|
Need to show three bike parking spaces on site as per CUP17-00069 and fence and property line location do not match the revised site plan from CUP17-00069. Was the fence line moved?
|
Routing - Addressing | 6/4/2018 | | 6/4/2018 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/4/2018 | | 6/4/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 6/4/2018 | | 6/4/2018 | | PASS |
KayCee Babb
|
|
|
|
Intake Approval | | | 6/4/2018 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/4/2018 | | DONE |
Carl D Madsen
|
|
|
Cathy, please verify and provide documentation whether any ACHD fees are due as this is a change in occupancy for this portion of the building. If fees are due they may be paid at the time the permit is issued or in advance to ACHD. If no fees are due or if fees have already been paid please provide documentation. N building permits can be issued prior to the payment of any fees that are due.
|
Application received | | | 6/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2018 7:58AM
|