First Notice | 10/22/2018 | 10/22/2018 | 11/6/2018 | | DONE |
Jim Sly
|
|
|
mailed 11-12
|
Print Occupancy Form | | | 10/24/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/24/2018 | | DONE |
|
|
|
|
BLD-Final | 10/19/2018 | 10/22/2018 | 10/22/2018 | A | PASS |
Jim Sly
|
|
|
###-####-Aaron
|
DOC - Permit Finaled | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 10/16/2018 | 10/17/2018 | 10/17/2018 | A | PASS |
Jim Page
|
|
|
Previously noted deficiencies on the fire sprinkler system have been corrected, final life fire safety inspection for area of work complete.
Aaron Phone #: ###-####
|
FIRE-Final Inspection | 10/5/2018 | 10/5/2018 | 10/5/2018 | A | FAIL |
Jim Page
|
|
|
Provide fire sprinkler in the closet between the restrooms. Provide fire sprinkler that is missing in vault, provide fire sprinkler under overhead door.
|
FIRE-Final Inspection | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | NR |
Jim Page
|
|
|
Spoke with Boise Fire Department about some noted issues in the fire sprinklered are that was outside the scope of work of the fire sprinkler contractor. A conference will be scheduled to verify discussed locations. Life safety is not passed at this time.
Aaron Phone #: ###-####
|
BLD-Final | 10/3/2018 | 10/4/2018 | 10/4/2018 | P | NR |
Jim Sly
|
|
|
Aaron Phone #: ###-#### Need Electrical and Fire final inspection.
|
BLD-Ceiling Grid Inspection | 9/26/2018 | 9/27/2018 | 9/27/2018 | P | PASS |
Jim Storey
|
|
|
Ken Phone #: ###-####
|
BLD-Framing/Rough-in | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Dave Hannah
|
|
|
Kem Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/16/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/16/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/6/2018 | | DONE |
|
|
|
Need
GC Form
Revised Cert of Value
|
Routing - FIRE | 7/2/2018 | 7/2/2018 | 7/5/2018 | | PASS |
Erika Akin
|
|
|
|
Plan assigned to (JG) | 6/7/2018 | 6/7/2018 | 7/5/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 6/13 L1 Amity Place ePlan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/29/2018 | | 7/5/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 6/29/2018 | | 7/3/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 6/21/2018 | 6/24/2018 | 6/25/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 6/7/2018 | 6/7/2018 | 6/21/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 6/21/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 6/7/2018 | | 6/19/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 6/7/2018 | | 6/11/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - MECHANICAL | 6/7/2018 | | 6/8/2018 | | PASS |
Troy James
|
|
|
See plans for redlines
|
Routing - Addressing | 6/7/2018 | | 6/8/2018 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/7/2018 | | 6/7/2018 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 6/7/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 6/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2018 9:54AM
|