Third Notice | | 1/12/2019 | 1/17/2019 | | DONE |
|
|
|
This permit finaled on the web by Ryan Allen
|
Third Notice | | 12/18/2018 | 1/7/2019 | | DONE |
|
|
|
mailed 1-11-19
|
Second Notice | | 11/16/2018 | 12/13/2018 | | DONE |
|
|
|
mailed 12-14
|
First Notice | | 10/25/2018 | 11/6/2018 | | DONE |
|
|
|
mailed 11-12
|
Permanent Occupancy | | | 10/15/2018 | | DONE |
|
|
|
|
BLD-Final | 10/11/2018 | 10/12/2018 | 10/12/2018 | P | PASS |
Tony Young
|
|
|
Phone number is for Kris. Business owner. He should be on site but please call when on your way. Thanks Phone #: ###-#### Inspection requested via web by Ryan Allen
|
FIRE-Final Inspection | 10/11/2018 | 10/12/2018 | 10/12/2018 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, hood suppression system inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
Phone number is for Kris. He will be on site and available if you need anything. Thanks. My phone number is 208 713 2042 if needed Phone #: ###-#### Inspection requested via web by Ryan Allen
|
BLD-Framing/Rough-in | 9/23/2018 | 9/24/2018 | 9/24/2018 | A | PASS |
Brandon Shaw
|
|
|
Seal/fire caulk penetreations at fire wall...
OK to cover
|
Issue PAID IN FULL permit | | | 7/13/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/13/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 7/4/2018 | 7/7/2018 | 7/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 7/5/2018 | | DONE |
|
|
|
Need:
GC
Revised Value
|
CHANGE STATUS TO (PND) | | | 7/5/2018 | | DONE |
|
|
|
pending impact fee routing for change of use
|
Permit Ready to Issue | | | 7/5/2018 | | |
|
|
|
MET
Need:
GC
Revised Value
|
Plan assigned to (CDM) | 6/7/2018 | 6/7/2018 | 7/4/2018 | | PASS |
Carl D Madsen
|
|
|
Cafficina bakery L-3 Due 7/4
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/4/2018 | | DONE |
|
|
|
|
Routing - FIRE | 6/7/2018 | 6/7/2018 | 7/2/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 7/2/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/23/2018 | | 6/23/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - C.D.H | 6/7/2018 | | 6/23/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Addressing | 6/7/2018 | | 6/11/2018 | | PASS |
Doug Chausow
|
|
|
Corrected address is 4754 W State St
|
Routing - PUBLIC WORKS | 6/7/2018 | | 6/11/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLUMBING | 6/11/2018 | | 6/11/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing PW Environmental | 6/8/2018 | | 6/8/2018 | | PASS |
Rick Christenson
|
|
|
Grease interceptor shown OK. Any floor drains in kitchen or scullery, as well as dishwasher, should attach to grease line.
|
Routing - MECHANICAL | 6/8/2018 | | 6/8/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/7/2018 | | 6/8/2018 | | PASS |
David Moser
|
|
|
Kitchen area for coffee shop - allowed in C-2 zone
|
Plan Reviewer's activity | | | 6/7/2018 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 6/7/2018 | | PASS |
|
|
|
|
Application received | | | 6/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2018 3:47PM
|