BLD-Final | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Brandon Shaw
|
|
|
Alan (engineer has inspected and signed off on walls) Phone #: ###-####
|
DOC - Permit Finaled | 6/28/2018 | 6/28/2018 | 6/28/2018 | P | PASS |
Brandon Shaw
|
|
|
|
OVERRIDE | | | 6/11/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 6/4/2018 | 6/4/2018 | 6/11/2018 | | PASS |
Josh Bogle
|
|
|
due 6/8 - boulder retaining wall
|
Routing - PLAN CHECK | | | 6/11/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing - Erosion and Sediment | | | 6/11/2018 | | PASS |
Michael Zawacki
|
|
|
Waiver approved
|
Issue PAID IN FULL permit | | | 6/11/2018 | | DONE |
|
|
|
|
1st review completed | | | 6/11/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 6/11/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 6/11/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2018 | | DONE |
Josh Bogle
|
|
|
|
Telephone call | | | 6/11/2018 | | DONE |
|
|
|
called Alan to let know the permit is rady and how much is owed-let him know the RP is about to expire-left message on his phone
|
Permit Ready to Issue | | | 6/11/2018 | | DONE |
|
|
|
met but let Alan know his RP will expire this month on 6/22-left message on his cell
|
Routing - PLANNING | 6/7/2018 | | 6/8/2018 | | PASS |
Nicolette Womack
|
|
|
Only retaining walls
|
Routing PW Grading-Hillside | 6/4/2018 | | 6/7/2018 | | PASS |
Melissa Jannusch
|
|
|
|
Routing - PUBLIC WORKS | 6/7/2018 | | 6/7/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 6/4/2018 | | 6/4/2018 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/4/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/4/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/4/2018 | | DONE |
|
|
|
|
Application received | | 6/4/2018 | | | |
|
|
|
|