BLD-Final | 11/29/2018 | 11/30/2018 | 11/30/2018 | P | PASS |
Brandon Shaw
|
|
|
as early as possible // sean Phone #: ###-####
|
DOC - Permit Finaled | 11/30/2018 | 11/30/2018 | 11/30/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 11/30/2018 | 11/30/2018 | 11/30/2018 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.62
|
BLD-Final | 11/28/2018 | 11/29/2018 | 11/29/2018 | A | FAIL |
Mike Jordan
|
|
|
Call for access- Shawn Phone #: ###-####. Provide tempered glazing in bathroom upstairs. Provide smoke and smoke/carbon detectors in den downstairs.(This room has a closet and egress window and shows s/c detectors on approved plan.) Provide landings at door in master bedroom and landing/step in door to garage.
|
BLD-Energy code compliance | 9/17/2018 | 9/18/2018 | 9/18/2018 | A | PASS |
Jim Sly
|
|
|
Shawn Phone #: ###-####
|
BLD-Framing/Rough-in | 9/13/2018 | 9/13/2018 | 9/13/2018 | P | PASS |
Jim Sly
|
|
|
Shawn Phone #: ###-####
|
BLD-Wall Bracing | 8/31/2018 | 9/4/2018 | 9/4/2018 | A | PASS |
Jim Sly
|
|
|
Sean Phone #: ###-####
|
Plan Modification Accepted | | | 8/31/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 8/31/2018 | | 8/31/2018 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Energy code compliance | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | NR |
Jim Sly
|
|
|
Shane Phone #: ###-#### No insulation installed yet.
|
BLD-Framing/Rough-in | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | NR |
Jim Sly
|
|
|
Shane Phone #: ###-#### No framing done yet........
|
BLD-Foundation | 7/24/2018 | 7/24/2018 | 7/24/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 7/23/2018 | 7/23/2018 | 7/23/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 7/13/2018 | 7/16/2018 | 7/16/2018 | P | NR |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo Lira
|
OVERRIDE | | | 7/13/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 7/12/2018 | 7/12/2018 | 7/13/2018 | | DEFR |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 7/12/2018 | | 7/13/2018 | | PASS |
Rob Patrick
|
|
|
Plan review passed per RDP
Site plan resubmittal per MDH
|
Routing - PLANNING | 7/12/2018 | | 7/13/2018 | | PASS |
Sue Cummings
|
|
|
Passed per ePlan. MDH
|
Plan assigned to (M_H) | 7/13/2018 | | 7/13/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 7/13/2018 | | DONE |
|
|
|
plan mod approved
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 7/13/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 7/12/2018 | | DONE |
Christina Prado
|
|
|
Site plan needs updated to reflect correct size, route to PLN & BLD
|
Inspection Record Card- Bld | | | 7/9/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/9/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/3/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 7/3/2018 | | DONE |
|
|
|
All requirements met
|
OVERRIDE | | | 7/2/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 6/15/2018 | 6/15/2018 | 7/2/2018 | | DONE |
Rob Patrick
|
|
|
6/28 sfd L1 ePlan...6/28 Failed for Tall Wall
|
Routing - PLANNING | 7/2/2018 | | 7/2/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - PLAN CHECK | 7/2/2018 | | 7/2/2018 | | FAIL |
Rob Patrick
|
|
|
Failed pending Planning comments addressed
|
Routing - PLAN CHECK | 7/2/2018 | | 7/2/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2018 | | DONE |
Rob Patrick
|
|
|
|
1st review completed | | | 6/28/2018 | | FAIL |
Rob Patrick
|
|
|
Tall Wall Engineering and other corrections.
|
Routing - PLAN CHECK | 6/15/2018 | | 6/28/2018 | | FAIL |
Rob Patrick
|
|
|
Tall Wall Engineering and other corrections
|
Route to Impact Fee Review | 6/15/2018 | 6/18/2018 | 6/18/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/15/2018 | | 6/15/2018 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/15/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/15/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/15/2018 | | PASS |
Brittany Hill
|
|
|
|
Routing - Addressing | 6/15/2018 | | 6/15/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/15/2018 | | 6/15/2018 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 6/4/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 4 2018 2:31PM
|
Routing - PLANNING | 6/15/2018 | | | | FAIL |
|
|
|
|