(COMMUNITY HOUSING) Front step for units 7, 8, 10, 11, 22. Exterior Stairs - Building is fully sprinklered and has an alarm system. Permit for tenant improvements to replace an existing exterior landing, step and handrail system per the approved plans of Unit 7,8,10,11 and 22. Adding handrail to both sides of concrete landing and steps. Grade is being modified as needed to allow steps as shown on plans (max. 7" rise). All work to be done per the approved plans and applicable codes and ordinances. This is a scope of work permit only with a certificate of compliance to be issued upon approval and completion of the project.***BJM***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection9/3/20199/3/20199/3/2019 DONE
DetailsJim Storey
Expires: 06/07/19
DOC - Permit Expired9/3/20199/3/20199/3/2019PPASS
DetailsJim Storey
Expires: 06/07/19
BLD-Aging Inspection4/22/20194/22/20194/22/2019 PASS
DetailsJim Storey
Expires: 06/07/19
OVERRIDE  6/7/2018  
Plan assigned to (BJM)6/5/20186/5/20186/7/2018 DONE
DetailsBrian McGowan
Community Housing - TI Level 1
Routing - PLAN CHECK6/5/2018 6/7/2018 PASS
DetailsBrian McGowan
1st review completed  6/7/2018 DONE
DetailsBrian McGowan
Case Summary (BLD)  6/7/2018 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  6/7/2018 DONE
DetailsBrian McGowan
Permit Ready to Issue  6/7/2018 DONE
Need
GC Form
JV account number
Inspection Record Card- Bld  6/7/2018 DONE
Meeting  6/7/2018 DONE
Left message for Gary to inform him the permit is ready, what fees are due and we need a 302 signed.
Issue & PRINT to be Invoiced  6/7/2018 DONE
gave Rita the JV #'ers
Routing - Design Review6/6/2018 6/6/2018 PASS
DetailsKayCee Babb
Routing - Erosion and Sediment6/6/2018 6/6/2018 PASS
DetailsMichael Zawacki
Waiver request approved
Plans ACCEPTED BY PLAN TECH  6/5/2018 DONE
Intake Approval  6/4/2018 PASS
per CDM
Application received 6/4/2018