BLD-Final | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Tony Young
|
|
|
|
DOC - Permit Finaled | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 6/21/2019 | 6/24/2019 | 6/24/2019 | A | DONE |
Tony Young
|
|
|
Scott Phone #: ###-####-call for access
|
BLD-Blower Door Test Results | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | DONE |
Tony Young
|
|
|
Scott Phone #: ###-####-call for access// 3.9
|
BLD-Final | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PEND |
Tony Young
|
|
|
Scott Phone #: ###-####-call for access,, needs hillside,, then ok
|
PubWorks Occupancy Approval | 6/21/2019 | 6/21/2019 | 6/21/2019 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
BLD-Other | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | PART |
Tony Young
|
|
|
Sofit // Sott Phone #: ###-####,, work in progress,, ok
|
BLD-Energy code compliance | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####
|
BLD-Framing/Rough-in | 11/2/2018 | 11/5/2018 | 11/5/2018 | P | PASS |
Tony Young
|
|
|
Scott Phone #: ###-####
|
BLD-Wall Bracing | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PASS |
Tony Young
|
|
|
exterior shear // scott johnson Phone #: ###-####
|
BLD-Footing | 8/24/2018 | 8/24/2018 | 8/24/2018 | P | PASS |
Tony Young
|
|
|
pat
|
PubWorks Subgrade Approval | 8/23/2018 | 8/23/2018 | 8/23/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 8/14/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/14/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/10/2018 | | |
|
|
|
|
Routing - FIRE | 8/10/2018 | 8/10/2018 | 8/10/2018 | | PASS |
Tim Frost
|
|
|
Fire sprinklers are to be provided due to fire flow availability.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 8/10/2018 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 7/9/2018 | | 8/10/2018 | | PASS |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 6/18/2018 | | 8/10/2018 | | DONE |
Michael Hanson
|
|
|
07/05 sfd L2 ePlan. 1st review completed - Structural and fire deficiencies. MDH 2nd review completed - Fire deficiences. MDH
|
Routing - FIRE | 7/25/2018 | 7/25/2018 | 7/25/2018 | | FAIL |
Tim Frost
|
|
|
Fire Sprinklers are required.
Show WUI zone.
|
Routing - FIRE | 7/12/2018 | 7/12/2018 | 7/12/2018 | | FAIL |
Tim Frost
|
|
|
Second request for fire flow information.
|
Routing - PLAN CHECK | | | 7/9/2018 | | FAIL |
Michael Hanson
|
|
|
Structural and fire deficiencies. MDH
|
1st review completed | | | 7/5/2018 | | FAIL |
Michael Hanson
|
|
|
Structural and fire deficiencies. MDH
|
Routing PW Grading-Hillside | 6/18/2018 | | 7/2/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - MECHANICAL | | | 6/20/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 6/18/2018 | 6/21/2018 | 6/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | | 6/18/2018 | 6/19/2018 | | FAIL |
|
|
|
Water flow information required
|
Routing - PLANNING | 6/18/2018 | | 6/19/2018 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Addressing | 6/18/2018 | | 6/18/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | | | 6/18/2018 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | | | 6/18/2018 | | PASS |
Michael Zawacki
|
|
|
Foothills home. Site prep inspection required.
|
Plans ACCEPTED BY PLAN TECH | | | 6/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/18/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/7/2018 | | FAIL |
|
|
|
Please provide either a REScheck analysis or prescriptive method (energy table) shown on plans.
|
Application received | | | 6/6/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 6 2018 1:57PM
|