Permit Information
Permit NumberBLD18-02006
StatusFinaled
Name SHADOW MOUNTAIN CONST INC
Site Address 4018 N SANDPOINT WAY
Project NameTivoli
Customer Number 
ePlanReviewYes
Description
***Prescriptive component energy approach*** WUI ZONE A REQUIREMENTS*** Permit for the construction of a new 3,075 sq. ft., one story single family dwelling with 4 bedrooms, 3 and a half bathrooms, approximately 352 sq. ft. of covered patio/porch and a 1,066-sq. ft. attached garage per the approved plans and any notations. A-1 zoning and setbacks per planning. MDH

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/24/20196/24/20196/24/2019PPASS
DetailsTony Young
DOC - Permit Finaled6/24/20196/24/20196/24/2019PPASS
DetailsTony Young
BLD-Final6/21/20196/24/20196/24/2019ADONE
DetailsTony Young
Scott Phone #: ###-####-call for access
BLD-Blower Door Test Results6/24/20196/24/20196/24/2019PDONE
DetailsTony Young
Scott Phone #: ###-####-call for access// 3.9
BLD-Final6/20/20196/21/20196/21/2019APEND
DetailsTony Young
Scott Phone #: ###-####-call for access,, needs hillside,, then ok
PubWorks Occupancy Approval6/21/20196/21/20196/21/2019 DONE
DetailsJason C. Taylor
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
BLD-Other11/13/201811/14/201811/14/2018APART
DetailsTony Young
Sofit // Sott Phone #: ###-####,, work in progress,, ok
BLD-Energy code compliance11/8/201811/9/201811/9/2018APASS
DetailsMike Jordan
Scott Phone #: ###-####
BLD-Framing/Rough-in11/2/201811/5/201811/5/2018PPASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Wall Bracing10/17/201810/17/201810/17/2018PPASS
DetailsTony Young
exterior shear // scott johnson Phone #: ###-####
BLD-Footing8/24/20188/24/20188/24/2018PPASS
DetailsTony Young
pat
PubWorks Subgrade Approval8/23/20188/23/20188/23/2018 DONE
DetailsMelissa Jannusch

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
Issue PAID IN FULL permit  8/14/2018 DONE
Inspection Record Card- Bld  8/14/2018 DONE
OVERRIDE  8/10/2018  
Routing - FIRE8/10/20188/10/20188/10/2018 PASS
DetailsTim Frost
Fire sprinklers are to be provided due to fire flow availability.
PLANS/APPL TAKEN TO FRONT DESK  8/10/2018 DONE
DetailsMichael Hanson
Permit Ready to Issue  8/10/2018 DONE
met
Routing - PLAN CHECK7/9/2018 8/10/2018 PASS
DetailsMichael Hanson
Plan assigned to (M_H)6/18/2018 8/10/2018 DONE
DetailsMichael Hanson
07/05 sfd L2 ePlan. 1st review completed - Structural and fire deficiencies. MDH 2nd review completed - Fire deficiences. MDH
Routing - FIRE7/25/20187/25/20187/25/2018 FAIL
DetailsTim Frost
Fire Sprinklers are required.
Show WUI zone.
Routing - FIRE7/12/20187/12/20187/12/2018 FAIL
DetailsTim Frost
Second request for fire flow information.
Routing - PLAN CHECK  7/9/2018 FAIL
DetailsMichael Hanson
Structural and fire deficiencies. MDH
1st review completed  7/5/2018 FAIL
DetailsMichael Hanson
Structural and fire deficiencies. MDH
Routing PW Grading-Hillside6/18/2018 7/2/2018 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
Routing - MECHANICAL  6/20/2018 PASS
DetailsTroy James
Route to Impact Fee Review6/18/20186/21/20186/19/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - FIRE 6/18/20186/19/2018 FAIL
Water flow information required
Routing - PLANNING6/18/2018 6/19/2018 PASS
DetailsNicolette Womack
Routing - Addressing6/18/2018 6/18/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS  6/18/2018 PASS
Routing - Erosion and Sediment  6/18/2018 PASS
DetailsMichael Zawacki
Foothills home. Site prep inspection required.
Plans ACCEPTED BY PLAN TECH  6/18/2018 DONE
Intake Approval  6/18/2018 PASS
Recd Pcfee & Taken To Pln CK  6/18/2018 DONE
Intake Approval  6/7/2018 FAIL
Please provide either a REScheck analysis or prescriptive method (energy table) shown on plans.
Application received  6/6/2018 DONE
Application submitted via PDS Online on Jun 6 2018 1:57PM